2019 Supreme(Bom) 2000

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
S.C. Gupte, J.
Municipal Corporation Of Greater Mumbai - Appellant
Versus
S.n. Thakkar Construction Company Private Limited - Respondent
Arbitration Petition No. 1060 of 2010
Decided On : 13-02-2019

Important Points

The measure of profit in a works contract is a matter of evidence and should be individually assessed in each case, and Indian law on damages only allows compensatory damages.

Subject

Arbitration Law - Construction Contract

Act Referred

CONTRACT ACT : S.73

Headnote

arbitration - construction contract - 2002 - 73 of the Contract Act

Fact of the Case:

The case involved disputes arising from a construction contract for the construction of diversion chambers for sewage. The arbitrator allowed several claims of the respondents and rejected the counter claim of the petitioner.

Finding of the Court:

The court found that the arbitrator's award on certain claims did not merit interference, as they were supported by evidence and were possible views. However, the court held that the award on loss of profit claim was based on no evidence and contrary to Indian law on damages.

Issues: The main issues were the validity of the arbitrator's award on various claims, including loss of profit, and the challenge to the award by the petitioner.

Ratio Decidendi: The court emphasized that the measure of profit in a works contract is a matter of evidence and should be individually assessed in each case. It highlighted that the Indian law on damages only allows compensatory damages and requires the party suffering from the breach to show what they were in a position to receive at the time the contract was broken.

Final Decision: The court set aside the arbitrator's award on the loss of profit claim and modified the award on interest, while sustaining the rest of the award.

Advocates Appeared:
P.G. Lad, Adv., R.Y. Sirsikar, Adv., D.S. Shingade, Adv., Nikhil Wadikar, Adv., Pradip Zende, Adv., S.S. Phadke, Adv.

JUDGMENT

S.C.Gupte, J. - This arbitration petition challenges an award passed by a sole arbitrator in the matter of disputes and differences between the parties arising out of a contract for construction for the Petitioner Municipal Corporation.

2. In 2002, the Petitioner invited tenders for providing and constructing diversion chambers for diverting sewage from SWD to sewerage system at seven locations in the city of Mumbai. The Respondents submitted their offer. The Petitioner accepted the offer and issued a work order directing the Respondents to commence the work from 01.10.2003 and complete the same by 31.05.2004. The Respondents were directed to get the work drawings approved before commencing the work and also to submit a PERT program and seek approval thereof. On 08.10.2003, the Respondents submitted a bar chart and cash flow statement. (This was after the due date of commencement of work.) During the course of the work, the Petitioner wrote several letters to the Respondents complaining of slow progress as also breaches of contract on the part of the Respondents and asking the latter for expediting the work. It is the case of the Petitioner that on 31.05.2004, the contract came to an end by efflux of time. On 09.08.2004, the Respondents applied for extension of time proposing various conditions, which, according to the Petitioner, were contrary to the terms of the contract. In the alternative, the Respondents requested for finalisation of accounts on "as is where is" basis. The Petitioner asked the Respondents to submit the list of compensatory events with documentary evidence without prejudice to the right of the Petitioner to grant extension, if any. It is the Petitioner''s case that the Respondents did not submit any details in response and instead alleged that these details were already available with the Petitioner. The Respondents made several allegations claiming that hindrances were caused to the work by the Petitioner. In these circumstances, when the Petitioner sought to invoke the bank guarantees submitted for mobilisation advance as also for performance, the Respondents offered to pay the amount of the mobilisation advance bank guarantee after deducting the sum already recovered from their running account bills. The Respondents also submitted a pay order to the Petitioner in lieu of performance bank guarantee. The Respondents thereafter raised several claims including a claim for wrongful encashment of bank guarantees under economic duress and financial pressure. Differences and disputes arose between the parties as a result, which were referred to the learned arbitrator. The Respondents were the claimants before the arbitrator, whereas the Petitioner was the respondent/counter claimant. The Respondents filed in all nine claims. The learned arbitrator, by this impugned award dated 04.02.2010, allowed Claim No.1 (partly), Claims Nos.2 and 3(fully), Claim No.4 (partly), Claim No.8 (partly) and Claim No.9 (partly) and rejected the counter claim of the Petitioner.

3. The award of the Respondents'' claims as above has been challenged by the Petitioner on various grounds. Learned Counsel for the Petitioner, however, mainly submitted that the award was based on no evidence and also was contrary to the documents submitted by the Petitioner. Learned Counsel submitted that the findings of the learned arbitrator on the alleged breaches of contract by the Petitioner and in particular, the delay in issuance of detailed construction drawings, were contrary to the record as well as the stipulations of the contract. Learned Counsel also submitted that the finding of the arbitrator that there was delay on the part of the Petitioner in making the site available for contract work or removing obstructions as also stoppage of work, etc. were either without evidence or contrary to the record. In particular reference to the Respondents'' claim for loss of profits, learned Counsel submitted that the award was contrary to public po