Limitation Act, 1963 – Article 1 and 19 - Repayment of Loan - Rent – Interest - Case of Respondent that amounts advanced towards the loan to the Appellants were agreed to be repaid with interest at the rate of 17.5% per annum - Amount of monthly rent, which Respondent was obliged to pay was being adjusted towards repayment of the loan amount - It was stated in the plaint that last amount towards loan advanced to Appellants - Monthly rent of Rs.350/- payable to the Appellants was being adjusted by the Respondent towards the amount due from the appellants and, in that context, Respondent claimed to have maintained an account from 1981 till the date of filing of the suit - Whether the suit filed by the Respondent was within limitation. According to Respondent (original Plaintiff), suit was filed within limitation by application of Article 1 of the Schedule to the Limitation Act, 1963, while Appellants claim that suit was barred by limitation by applying Article 19 thereof – Held, Respondent issued notice to appellants and adjustment of monthly rent towards repayment of loan was stopped in August/September 2002 and the Suit was filed immediately - This was clearly within three years of close of the year in which last item was entered in the account, applying position of law to facts of the present case, it is found that no error was committed by Appellate Court in holding that Article 1 of Schedule to the Limitation Act applied and that the Suit for recovery filed by Respondent was within the limitation period of three years - Appeal is dismissed.
JUDGMENT :
1. The only question that arises for consideration in this Appeal is, as to whether the suit filed by the Respondent was within limitation. According to the Respondent (original Plaintiff), the suit was filed within limitation by application of Article 1 of the Schedule to the Limitation Act, 1963, while the Appellants claim that the suit was barred by limitation by applying Article 19 thereof.
2. The Respondent filed suit against the Appellants on 31.10.2002, for a Decree directing the Appellants to pay a sum of Rs.4,20,538.61 along with interest at the rate of 17.5% per annum from 01.11.2022 till actual payment. According to the Respondent, the said amount was due towards loan amounts advanced to the Appellants on various dates between 1981 to 1997. It was the case of the Respondent that it had taken a house situated in Salcete, Goa, from the Appellants on rent, initially for a monthly rent of Rs.300/- and after one year, for rent at the rate of Rs.350/- per month. It was the case of the Respondent that the amounts advanced towards the loan to the Appellants were agreed to be repaid with interest at the rate of 17.5% per annum. The amount of monthly rent, which the Respondent was obliged to pay was being adjusted towards repayment of the loan amount. It was stated in the plaint that the last amount towards loan advanced to the Appellants was on 23.07.1997. The monthly rent of Rs.350/- payable to the Appellants was being adjusted by the Respondent towards the amount due from the appellants and, in that context, the Respondent claimed to have maintained an account from 1981 till the date of filing of the suit.
3. It was the case of the Respondent that on 07.09.2001, the Respondent caused a notice to be issued through Advocate to the Appellants, stating the amount due towards the repayment of loan as on 31.08.2001. It was stated in the notice that since the amount of monthly rent credited to the account of the Appellants was insufficient to repay the loan and since the interest was mounting thereon, in the month of July 2000 itself, the Respondent had asked the Appellants to take some concrete steps to repay the loan along with interest. Yet the Appellants had neither given proposal for liquidating the loan under the loan account nor were the dues liquidated. On this basis, the Appellants were called upon to repay the loan amount along with interest within a period of one month, failing which, the Respondent would be constrained to initiate appropriate proceedings for recovery.
4. On 18.10.2001, the Appellants through their Advocate, sent reply to the aforesaid notice and denied that the Respondent had advanced loans to them. It was stated that no loan account existed and the claims of the Respondent were denied. Instead, it was stated that there were amounts due from the Respondent for occupation of the premises in question and if payment of the same was not made within 30 days, the Appellants would terminate the Agreement and initiate proceedings for evicting the Respondent.
5. It is in this backdrop, that on 31.01.2002, the Respondent filed the aforesaid suit for recovery of the amount specified herein above. In the plaint, the Respondent not only stated that specific amounts were advanced to the Appellants by way of loan and that there was an Agreement that the monthly rent would be adjusted towards the repayment of the loan amounts with interest, a detailed statement of the loan amounts was given in paragraph 7 of the plaint. The Respondent also filed statement of account as a document with the plaint, wherein it was specifically stated that monthly rent of Rs.350/- was adjusted towards the amount due from the Appellants up to September, 2002. On this basis, the specific amount due from the Appellants was calculated and a Decree was sought in that regard. The Respondent also placed on record two Agreements dated
Hindustan Forest Company Vs. Lal Chand & Others
M/s. Roshan Lal Kuthiala & Another Vs. Raja Rana Yogendra Chandra & Others
Shivam Construction Co., Ahmedabad & Others Vs. Vijaya Bank, Ahmedabad & Others
Kesharichand Jaisukhal Vs. Shillong Banking Corporation
Plaintiff had failed to prove liability of defendants to pay him any amount which could be said to be within the period of limitation.
The main legal point established in the judgment is that the suit filed beyond the limitation period as per Article 19 of the Limitation Act, 1963, for seeking recovery of a loan where no time period....
The court clarified conditions for a reciprocal, mutual account under the Limitation Act, excluding claims due to lack of independent obligations among parties.
(1) Preliminary issue – When issues of both law and facts arise in same suit, Court may dispose suit by trying issue of law first.(2) Money suit – Issue as to whether claim of appellant is barred by ....
The court established that the limitation period for recovery of loans starts from the date of the loan agreement, with the first day excluded in the computation.
The court clarified the applicability of Arts. 19 and 37 of the Limitation Act concerning installment agreements and confirmed recoveries for timely payments.
The Respondent's claim was barred by res judicata as the cause of action had merged with a prior judgment, and the limitation period for the claim had expired.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.