SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Anuja Prabhudessai, J.
Raymond Limited & Ors. – Appellants
Versus
New Sarnath Co-Op. Hsg. Society Limited & Ors. – Respondents
Writ Petition (Stamp) No. 6563 of 2021
Decided On : 06-05-2022

Advocates Appeared:
Mr. Shyam Devani with Ms. Anshika Mishra and, Mr. Vedanta Jalan, M/s. AZB, for the Appellant; Mr. A.N. Narula with Ms. Meena Bhalla i/b. M/s. Jhangiani Narula, for the Respondent.

Amendments to pleadings should be allowed if necessary for determining the real controversy between the parties and not inconsistent with existing pleadings. However, amendments introducing new causes of action or changing the fundamental nature of the suit should not be allowed.

Headnote:

Amendment of Pleadings - Real Controversy - Order VI Rule 17 - Sale Agreements - Statutory Obligation - Occupation Certificate - Recreational Space - JK House Construction

Fact of the Case:

The Defendants challenged the order allowing the amendment of the plaint, arguing that the relief of declaration was barred by limitation and that the proposed amendment was malafide and caused prejudice to them. The Plaintiffs sought to amend the cause title, user of common terrace, non-execution of conveyance deed, obtaining complete occupancy certificate, use of recreational ground, and construction of JK House. The Court considered the necessity of the amendments and their relevance to the real controversy between the parties.

Finding of the Court:

The Court found that some proposed amendments were necessary to determine the real question in controversy and were not inconsistent with the existing pleadings. However, the proposed amendment regarding the construction of JK House in Plot A and utilization of FSI/TDR was disallowed due to delay and introducing a new cause of action. The amendment to convert interim relief into final relief was allowed as it rectified a defect in the pleading.

Issues: The issues revolved around the necessity and relevance of the proposed amendments, their consistency with existing pleadings, and whether they introduced new causes of action.

Ratio Decidendi: The Court held that amendments should be allowed if necessary for determining the real controversy between the parties and not inconsistent with existing pleadings. It also emphasized that amendments introducing new causes of action or changing the fundamental nature of the suit should not be allowed. The Court considered the necessity and relevance of each proposed amendment in light of the real controversy between the parties.

Final Decision: The Court partly allowed the Writ Petition, setting aside the impugned order regarding the construction of JK House in Plot A and utilization of FSI and TDR, while allowing the amendment to convert interim relief into final relief.

JUDGMENT

1. With consent, matter is heard finally at the stage of admission.

2. The Petitioners, who are the Defendant Nos.1 and 2 in the suit (hereinafter referred to as Defendants) have challenged the impugned order dated 17.02.2021, passed by the learned Judge, City Civil Court, Gr. Bombay allowing the Chamber Summons No.1236 of 2016 for amendment of the plaint as per the schedule.

3. Mr. Devani, learned counsel submits that by amendment as proposed in Clause E, the Respondent Nos.1 and 2 (hereinafter referred to as the Plaintiffs) have sought declaration that certain clauses of the Agreements executed between the members of the Plaintiff No.1 society and the Defendants are illegal, void, ab-initio and not binding upon the members. He submits that the said Agreements were executed some time in the year 1976. The Plaintiffs/members were in possession of these Agreements and there is no explanation for seeking such relief at a belated stage. He submits that the relief of declaration is ex-facie barred by law of limitation and such preliminary objection could not have been relegated to the stage of trial. He therefore submits that the impugned order is unsustainable. Reliance is placed on the decision of FGP Ltd. vs. Saleh Husseini Doctor & Anr 2014 (6) ABR 124 to contend that when the Plaintiff does not approach the Court with clean hand and does not explain the delay, then such belated application for amendment deserves to be rejected.

4. Learned Counsel for the Defendants further submits that the Plaintiffs have relied on several documents, proposed Exhibits Ml to M12, which were always in their possession and within their knowledge. If any cause of action had accrued on the basis of the said documents, the said documents ought to have been produced along with the suit. He further submits that the Plaintiffs are seeking to introduce a new cause of action which is unconnected and irrelevant to the suit. It is stated that right once accrued in favour of the Defendants, cannot be defeated by way of amendment. The learned Judge was therefore not justified in allowing the chamber summons.

5. Learned counsel for the Defendants further submits that an attempt is made to convert the interim relief in prayer clauses (d) to (h) into final relief after lapse of 12 years. It is contended that such reliefs as on the date of amendment are barred by law of limitation, and as such the learned Judge was not justified in allowing the Plaintiffs to convert the prayers for interim relief into final relief. Reliance is placed on the decision of Ashutosh Charutvedi v/s. Prano Devi & Ors. 2008 (15) SCC 610.

6. Learned counsel for the Defendants further submits that by the proposed amendment, the Plaintiffs have sought to introduce new facts and seek additional reliefs solely on the basis of new cause of action. Reliance has been placed on the decision of the Honourable Supreme Court in the case of Revajeetu Builders and Developers vs. Narayan Swami & Sons. (2009) 10 SCC 98 to contend that the basic test which should govern the Courts discretion in granting or refusal of the amendment is whether such amendment is necessary for the determination of the real question in controversy. Learned counsel for the Defendants states that the plaint is sought to be amended after a lapse of 12 years by blaming the erstwhile lawyer for not bringing on record the relevant facts. It is contended that the proposed amendment is malafide and allowing the application has caused prejudice to the Defendants.

7. It is further stated that the issues were settled in November 2014 and the matter was listed for recording of evidence. Since the trial in the matter had already commenced, the proposed amendment could not have been allowed, particularly when the Plaintiffs had failed to establish due diligence. Reliance is placed on the decisions of Apex Court in Revanna vs. Anjanamma (Dead) By Lrs. & Ors. (2019) 4 SCC 332; Vidyabai & Ors. vs. Padmalatha (2009) 2 SCC 409; Chander Kant

            Click Here to Read the rest of this document
            1
            2
            3
            4
            5
            6
            7
            8
            9
            10
            11
            SupremeToday Portrait Ad
            supreme today icon
            logo-black

            An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

            Please visit our Training & Support
            Center or Contact Us for assistance

            qr

            Scan Me!

            India’s Legal research and Law Firm App, Download now!

            For Daily Legal Updates, Join us on :

            whatsapp-icon Back to top