IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Vibha Kankanwadi, Y.G. Khobragade, JJ.
Nagnath – Appellant
Versus
State of Maharashtra – Respondent
Civil Application No. 16000 of 2022
Decided On : 11-04-2023
Limitation Act - Delay Condonation - Land Acquisition Act - Sec. 5 of the Limitation Act, 1963 - Sec. 4, Sec. 18, Sec. 54 of the Land Acquisition Act - Summary of Acts and Sections: The court discussed the provisions of Sec. 5 of the Limitation Act, 1963 and Sec. 4, Sec. 18, Sec. 54 of the Land Acquisition Act. The court emphasized the discretion in condoning delay, the importance of substantial justice, and the need for reasonable and justifiable grounds for delay condonation.
Fact of the Case:
The applicants sought condonation of a 3776-day delay in filing an appeal against a judgment and award passed by the Joint Civil Judge, Senior Division, Ahmedpur, under the Land Acquisition Act. The applicants claimed that the delay was due to the death of the original award holders and their lack of knowledge about the pending land acquisition proceeding.
Finding of the Court:
The court found that the delay was inordinate and not bona fide, as the applicants failed to provide reasonable and justifiable grounds for the delay. The court noted that the applicants, including the surviving original award holder, were aware of the judgment and award but did not take steps to file an appeal for over ten years. The court rejected the application for delay condonation.
Issues: The main issue was whether the delay of 3776 days in filing the appeal could be condoned under Sec. 5 of the Limitation Act, 1963.
Ratio Decidendi: The court held that the discretion to condone delay must be exercised judiciously and reasonably, and that substantial justice deserves to be preferred over technical considerations. The court emphasized the need for reasonable and justifiable grounds for delay condonation, especially in land acquisition matters.
Final Decision: The court rejected the application for delay condonation, finding that the grounds provided by the applicants were not satisfactory.
JUDGMENT
Y.G.KHOBRAGADE,J. - The applicants have filed the present application under Sec. 5 of the Limitation Act, 1963 and prayed for condonation of delay of 3776 days caused in filing Appeal against the judgment and award dtd. 4/10/2011 passed by the learned Joint Civil Judge, Senior Division, Ahmedpur, District Latur in L.A.R. No.683 of 2002.
2. Heard Mrs. P. G. Sontakke, learned Advocate for the applicants and Mr. R. V. Dasalkar, learned AGP for non-applicant Nos.1 and 2. Though the non-applicant No.3 served, but remained absent.
3. Having regard to submissions canvassed on behalf of both sides, we have gone through the record. Applicants were the owners and possessors of land Survey/Gut No.123 admeasuring 4 Hectare 20 Are (i.e. 4,57,380 square feet) situated at village Tembhurni, Taluka Ahmedpur, District Latur. That land was acquired by the non-applicant No.3 Acquiring Body for public project as per Notification dtd. 14/12/1997 published under Sec. 4 of the Land Acquisition Act. On 15/1/2001 the Land Acquisition Officer determined compensation in respect of the acquired land at the rate of Rs.30,000.00 per Hectare, which was accepted by the applicants under protest.
4. Being dissatisfaction with said award dtd. 15/1/2001, the applicants preferred reference bearing L.A.R. No.683/2002 under Sec. 18 of the Land Acquisition Act, 1894 before the learned Joint Civil Judge, Senior Division, Ahmedpur and claimed compensation of acquired land at the rate of Rs.90.00 per square feet along with statutory benefits. The learned Joint Civil Judge, Senior Division, Ahmedpur, has partly allowed said LAR No.683/2002 on 4/10/2011 and granted compensation at the rate Rs.36,000.00 per Acre with statutory benefits. Being dissatisfaction of said award dtd. 4/10/2011, the applicants/ original claimants intend to file appeal, by invoking jurisdiction of this Court under Sec. 54 of the Land Acquisition Act, 1894 read with Sec. 96 of the Code of Civil Procedure. However, since there is delay, in approaching this Court, they have filed present application.
5. The learned Advocate appearing for the applicants submitted that the original award holder No.2 Gajrabai was suffering from serious ailment, therefore, her husband award holder No.1 Nagnath was taking her care. Unfortunately, Smt. Gajrabai died on 10/5/2015 due to her ailment. Original award holder No.1 Nagnath also died on 15/8/2018 at the age of 85 years, due to the depression because of death of wife Gajrabai. The applicants 1 and 2 are the legal heirs of original award holders 1 and 2, but they were not having knowledge about pendency of land acquisition proceeding. Therefore, they preferred application for issuance of heir-ship certificate before the learned 2nd Joint Civil Judge, Junior Division, Ahmedpur, District Latur. The learned Civil Court granted legal heir certificate in their favour on 30/8/2019. Since the applicants 1 and 2 were helpless due to death of their father. After receiving legal advice from their Counsel, they decided to file appeal. However, delay of 3776 days has been caused in filing appeal. The said delay is bona-fide and not intentional. Hence, prayed for condonation of the same.
6. In support of the submissions, the learned Advocate for the applicants relied on the case of Tukaram Kana Joshi and others Vs. M.I.D.C., passed by the Hon'ble Supreme Court on 2/11/2012 in Civil Appeal No.7780/2012, wherein, the Hon'ble Apex Court held that the question of condonation of delay is one of discretion and has to be decided on the basis of the facts of the case at hand, as the same vary from case to case. In para Nos. 11 to 15, the Hon'ble Supreme Court held as under:
"11. The question of condonation of delay is one of discretion and has to be decided on the basis of the facts of the case at hand, as the same vary from case to case. It will depend upon what the breach of fundamental right and the remedy claimed are and when and how the delay arose. It is not that there is any p
Collector, Land Acquisition, Anantnag and Anr. vs. Mst. Katiji
Dayal Singh and Ors. vs. Union of India
Dehri Rohtas Light Railway Company Ltd. vs. District Board, Bhojpur
Durga Prasad vs. Chief Controller of Imports and Exports
P.S. Sadasivaswamy vs. State of T.N
Shankara Co-Op Housing Society Ltd. vs. M. Prabhakar
State of M.P. and Ors. vs. Nandlal Jaiswal
The main legal point established in the judgment is that the discretion to condone delay must be exercised judiciously and reasonably, and that reasonable and justifiable grounds for delay condonatio....
The main legal point established in the judgment is that the appellant must provide a reasonable and plausible explanation, absence of negligence or malafides, and legal and adequate reasons to condo....
A government body cannot benefit from its own negligence; explanations for condonation of delay must be reasonable, and inordinate delay jeopardizes the rights of others.
The main legal point established in the judgment is the requirement to show sufficient cause for delay as per Section 5 of the Limitation Act, 1963, and the need for a reasonable and plausible explan....
The central legal point established in the judgment is the judicial approach to condonation of delay in land acquisition matters, emphasizing the need for a liberal approach due to the illiteracy and....
Legal representatives cannot re-agitate disputes over compensation post-finality; delay in appeal without compelling justification is not condoned.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.