SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Cal) 874

IN THE HIGH COURT AT CALCUTTA
SOUMEN SEN, ACJ., APURBA SINHA RAY, J.
State Of West Bengal Represented By La Collector, Purba Burdwan - Appellant
Vs.
Md Sabed, Since Deceased Represented By Kamar Jahan And Ors. - Respondent
FAT 375 of 2025 with CAN 1, 2, 3 of 2025
Decided On : 22-09-2025

Advocates:
Advocate Appeared:
For the Appellant : Mr. Rabindra Narayan Dutta, Adv. Mr. Arkoday Mukherjee, Adv.
For the Respondent: Mr. Kingsuk Mondal, Adv. Mr. Sk. Omar Sarif, Adv.

A government body cannot benefit from its own negligence; explanations for condonation of delay must be reasonable, and inordinate delay jeopardizes the rights of others.

Headnote:(A) Land Acquisition Act, 1894 - Section 18 - Limitation Act, 1963 - Application for condonation of delay - Delay of 3900 days - Inordinate delay not sufficiently explained - Valuable rights accrued in favor of legal heirs of the claimant; appeal dismissed. (Paras 1-2, 5-6, 17)

(B) Condonation of delay - Explanation must be reasonable and satisfactory; mere bureaucratic delays or procedural red tape do not constitute sufficient cause for delay. (Paras 10-12)

(C) Government negligence - A government cannot benefit from its own wrong; casual approach to procedural compliance is unacceptable and detrimental to justice. (Paras 8, 16)

Facts of the case:
The appellant delayed the appeal regarding land compensation for 3900 days, attributing it to bureaucratic changes, administrative issues, and COVID-19 pandemic disruptions. Evidence showed a marked lack of action leading to delay.

Findings of Court:
The court found the provided explanations unsatisfactory and held that the inaction was unreasonable, leading to the dismissal of the appeal and application for condonation of delay.

Issues: The main issues concerned the sufficiency of the reasons provided for the significant delay in filing the appeal and the priority of the rights accrued to the land award holders.

Ratio Decidendi: The court ruled that a liberal approach to condonations must not ignore unreasonable delays, especially those resulting from negligence. A government must comply equally with procedural laws and cannot evade responsibility.

Result: Application for condonation of delay dismissed, and the appeal subsequently dismissed.

Table of Content
1. explanation of delay in appeal due to administrative issues. (Para 1 , 2 , 3)
2. arguments for liberal approach in appeal's condonation. (Para 4 , 6 , 7)
3. court's observations on inaction and administrative negligence. (Para 5 , 10 , 15)
4. principle against government benefiting from its own wrong. (Para 8 , 14)
5. final orders dismissing appeal and mandating payment. (Para 17 , 18 , 20 , 21 , 22 , 23 , 24)

JUDGMENT :

Re: CAN 1 of 2025

1. There is a delay of 3900 days in preferring the appeal. The inordinate delay in preferring the appeal has not been sufficiently explained in the application for condonation of delay. The valuable right has accrued in favour of the legal heirs of the original claimant. They cannot be deprived of the benefits of the award dated 7th August, 2014, passed in connection with the Land Acquisition case arising out of a reference under Section 18 of the LAND ACQUISITION ACT I of 1894.

2. The referring claimant is the respondent in the appeal. The lands of the referring claimant were acquired by the L.A. Collector, Burdwan in connection with L.A. Case No.15(IV)/1995-1996, vide Notification dated 25.11.1997 for construction of Housing Scheme at Mouza-Alisha. The admitted position is that the acquired lands were classified as 'Sali' and the said lands were of Mouza – Alisha. The L.A. Collector awarded a sum of Rs.26,509/- as compensation for the acquisition of the plot of land No.74 of Mouza–Alisha, J.L. No.77 measuring 0.1075 acre.

3. The referring claimant was dissatisfied with the said compensation amount and has made a reference under Section 18 of the L.A. Act before the learned Additional District Judge, 3rd Court, Burdwan, being L.A. Case No.02/2001. The Executive Officer, Zilla Parisad of Burdwan and the Executive Officer, B.D.A., Burdwan, contested the reference. The requiring bodies were made parties. The learned Additional District Judge on consideration of the materials on record and relying upon comparable units enhanced the compensation amount along with statutory interest. The said judgment was pronounced on 7th August, 2014.

4. The memorandum of appeal was filed on 13th August, 2025 with a prayer for condonation of delay. The Additional Stamp Reporter has reported that there is a delay of 3900 days in preferring the appeal. In the application for condonation of delay, the following explanations were offered for not being able to prefer the appeal within the period of limitation:-

“7. That the concerned officer of the appellant during the relevant period, when the award was passed in respect of the land in question as acquired under Act 1 of 1894 and subsequent to passing the impugned judgement and decree, the said officials have been transferred time to time and due to change of the officials of the appellant, who used to deal with the above Land Acquisition matters sought for legal opinion of the Learned Government Pleader, the then Burdwan thereafter the appellant send his subordinate officials to deal with the aforesaid cases to the Department of Legal Remembrancer, Government of West Bengal with a request for engagement of Learned State Advocate in filing appeal arising out of the L.A. Case being No.74/110 of 2007/2006.

8. That during the relevent time, District Bardhaman was divided in two parts, i.e. Purba Bardhaman and Paschim Bardhaman by the Gazette Notification vide 80/AR/O/2R-3/12 dated 24/03/2017 with effect from 07th April, 2017 as such in the meantime, office was heavily engaged in its administrative function to pursue before Department of Legal Remembrancer, Government of West Bengal with a request for engagement of Learned State Advocate in filing appeal.

This office sent status report to Purba Bardhaman Zilla 1738/ LA /Law Parishad vide Cell/RC/65/136/08/17 dated 19.07.2017 and then sent a request to the Purba Bardhaman Zilla Parishnd seeking suitable action toward mitigating the four Execution Cases in view of previously discussed amicable settlements in ear

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top