IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ALOK ARADHE, C.J., BHARATI DANGRE, J.
Harsha Infra Power Pvt. Ltd. - Appellant
Versus
Bharat Petroleum Corporation Ltd. & Anr. - Respondents
Writ Petition No. 3076 of 2024
Decided On : 06-03-2025
(A) Policy for Holiday Listing of Bharat Petroleum Corporation Ltd. - Clauses 4.1.1(g)-(h), 4.2.1, 4.2.5, and 4.2.12 - Blacklisting of contractor - The petitioner challenged the validity of blacklisting for three years without a show cause notice, violating principles of natural justice - The court emphasized that blacklisting is stigmatic and should follow procedural safeguards. (Paras 7, 12, 18)
(B) Natural Justice - The court reiterated that an order of blacklisting must comply with principles of natural justice and cannot be based solely on contractual breaches without strong justification. (Paras 12, 14)
(C) Proportionality - The court found the blacklisting for three years disproportionate as no reasons were provided for such a maximum penalty. (Paras 18, 19)
Facts of the case:
The petitioner, a contractor, was blacklisted by the Corporation for not mobilizing labor after being awarded a contract. The petitioner argued that the blacklisting violated natural justice due to lack of a show cause notice.
Findings of Court:
The court held that the blacklisting was procedurally irregular and quashed the impugned orders, allowing the Corporation to proceed in accordance with the law.
Issues: The main issues were whether the blacklisting violated natural justice and if the clauses of the Policy were lawful.
Ratio Decidendi: The court ruled that blacklisting requires adherence to procedural safeguards and cannot be arbitrary, emphasizing the need for a show cause notice.
Result: Impugned orders quashed and set aside.
| Table of Content |
|---|
| 1. challenge to blacklisting (Para 2) |
| 2. contract awarded (Para 3) |
| 3. show cause notice issued (Para 4) |
| 4. contract termination (Para 5) |
| 5. blacklisting notice (Para 6) |
| 6. violation of natural justice (Para 7 , 9) |
| 7. contrary to supreme court decision (Para 8) |
| 8. considered rival submissions (Para 10) |
| 9. legal principles on blacklisting (Para 11) |
| 10. blacklisting requires natural justice (Para 12 , 13) |
| 11. blacklisting is stigmatic (Para 14 , 15 , 16 , 17 , 18) |
| 12. impugned orders quashed (Para 19 , 20 , 21) |
JUDGMENT :
ALOK ARADHE, C.J.
1. Rule. Rule is made returnable forthwith. By consent of the parties, heard finally.
2. In this petition, the petitioner has assailed the validity of Clause 4.1.1 (g)-(h) of Policy for Holiday Listing (Policy) of Bharat Petroleum Corporation Ltd.(Corporation) as well as the validity of orders dated 29th December 2023 and 29th March 2024. In order to appreciate the challenge of the petitioner to the impugned clauses of the Policy as well as the impugned orders, the relevant facts need mention which are stated infra.
3. The petitioner is a Company incorporated under the laws of India. The petitioner deals with contracts of laying down and maintenance etc. of water pipelines. The Respondent Corporation is a Public Sector Undertaking. The Corporation issued a Notice Inviting Bid for laying pipelines in Ahmednagar and Aurangabad in the State of Maharashtra. The petitioner on 13th March 2023 in the aforesaid tender was adjudged as successful bidder and a Letter of Acceptance (LoA) was issued to the petitioner on the same day.
4. The Project Management Consultant (PMC) of the Corporation, within a period of less than six weeks from issuance of LoA to the petitioner, issued a show cause notice to it on 24th April 2023 for not mobilizing the labour by which the petitioner was informed that in case it fails to mobilize the site in 45 days, the Corporation shall put the contractor on holiday list for future tendering process. The petitioner, on 27th April 2023 submitted a response to the PMC of the Corporation. The Corporation, vide communication dated 30th May 2023 again informed the petitioner that any further delay on its part will force the Corporation to invoke the clause as per the Policy. Thereafter, on 17th June 2023 a meeting was held between the parties in which the Corporation agreed to extend the period of completion of contract by three months i.e. upto 31st October 2023.
5. The Corporation, by communication dated 10th July 2023 issued another notice to the petitioner by which the petitioner was informed that on account of non-compliance of contractual obligations by the petitioner, the contract period shall not be extended further and shall be terminated on 12th July 2023. The petitioner, thereupon, submitted its response on 14th July 2023 and stated that after completion of the land acquisition process, it shall start the work within a week. The Corporation, however, on 24th July 2023 terminated the contract even before the extended deadline for completion of the work i.e. upto 31st October 2023.
6. The Corporation, on 11th September 2023 issued a notice to the petitioner terminating the contract and initiating the process of blacklisting under Clause 10(b) of General Conditions of Contract. The petitioner, on 18th September 2023 submitted a response. Thereafter, on 29th December 2023 the impugned order was passed by the Corporation blacklisting the petitioner for a period of three years, which is the maximum period prescribed under Clause 4.2.12 of the Policy. The petitioner, thereafter on 14th January 2023 filed an appeal before the appellate authority, which was dismissed by an order dated 29th March 2023. In the aforesaid factual back-ground the petitioner has approached this Court seeking the reliefs stated supra.
7. Learned Counsel for the petitioner submitted that no show cause notice, as mandated under clauses 4.2.1 and 4.2.5 read with Annexure-I of the Policy, was issued prior to bla
Gorkha Security Services Vs.Government (NCT of Delhi)
Blacklisting a contractor requires adherence to natural justice principles, including issuing a show cause notice, and cannot be arbitrary or disproportionate.
Imposing a 'Holiday Listing' without a personal hearing violates natural justice principles, affecting a party's ability to contract and thus constituting a civil consequence.
The requirement for a fair hearing and a specific show cause notice before imposing the severe civil consequence of blacklisting, and the need for the authority to determine the period of punishment ....
The main legal point established in the judgment is that before blacklisting a person/entity, adequate notice and an opportunity to be heard must be provided, in accordance with the principles of nat....
The judgment emphasizes the importance of fair play, natural justice, non-discrimination, equality, reasonableness, and proportionality in the process of blacklisting, and the need for a valid, parti....
Administrative authorities must adhere to the principles of natural justice when imposing penalties like debarment. This includes disclosing all adverse material and reports relied upon to the affect....
Blacklisting in public contracts requires compelling evidence of misconduct; mere disputes over contract terms do not justify severe penalties.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.