SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Bom) 361

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
HON'BLE SHRI JUSTICE SOMASEKHAR SUNDARESAN
Keller Ground Engineering India Private Limited - Appellant
Versus
Archon Powerinfra India Pvt. Ltd. & Ors. - Respondent
COMMERCIAL ARBITRATION PETITION NO.426 OF 2024
Decided On : 23-01-2025

Advocates Appeared:
Mr. Shyam Kapadia a/w. Ravitej Chilumuri, Aishwarya Singh,
Kanika Sharma i/b. Khaitan & Co., Advocate for Petitioner.
Mr. Abhileen Chaturvedi a/w. Mr. Mohit Prabhu, Mr. Sayyad
Saqib Ali & Mr. Sparsh Khosia i/b. Cyril Amarchand
Mangaldas, Advocate for Respondent No.1.
Mr. Mahalakshmi Ganapathy a/w. Rahul Dhawan, Tanmay
Bhave & Apoorv Bansal, Advocates for Respondent No.2.

The designation of a venue in an arbitration clause serves as the seat of arbitration, granting jurisdiction under Section 11 of the Arbitration and Conciliation Act, 1996.

Headnote:

(A) Arbitration and Conciliation Act, 1996 - Sections 9 and 11 - Jurisdiction of the court under Section 11 to appoint an arbitrator - The court held that the venue of arbitration being Mumbai, it has jurisdiction to exercise powers under Section 11 despite objections on territorial jurisdiction and privity of contract - The existence of arbitration agreements between the parties was established, and the court emphasized that merits of the case should be addressed by the arbitral tribunal, not the Section 11 court. (Paras 10, 11, 25, 30)

(B) Jurisdiction - The court clarified that the designation of a venue in the arbitration clause also serves as the seat of arbitration, thus attracting jurisdiction under Section 11 of the Act. (Paras 22, 24)

Facts of the case:
The case involves disputes arising from two work orders between the petitioner and the contesting respondents, with Indian Oil added as a party for interlocutory reliefs. The arbitration agreements in the work orders designate Mumbai as the venue for arbitration.

Findings of Court:
The court found that it has jurisdiction under Section 11 to appoint an arbitrator, as the arbitration agreements exist and Mumbai is the agreed venue. The merits of the disputes are to be resolved by the arbitral tribunal.

Issues: The main issues were whether the court has jurisdiction under Section 11 based on the venue of arbitration and the privity of contract regarding the arbitration agreements.

Ratio Decidendi: The court ruled that the venue of arbitration being Mumbai grants jurisdiction under Section 11, and the merits of the case should be addressed by the arbitral tribunal, not the court.

Result: The Section 11 Petition is disposed of with the appointment of a Sole Arbitrator.

JUDGEMENT :

Somasekhar Sundaresan J.

The Petitions:

1. Commercial Arbitration Petition No.426 of 2024 (“Section 9 Petition”) is filed under Section 9 of the Arbitration and Conciliation Act, 1996 (“the Act”) seeking various interlocutory reliefs in connection with disputes and differences said to have arisen between Keller Ground Engineering India Private Limited, the Petitioner (“Keller”) on the one hand, and Arcon Powerinfra India Pvt. Ltd., Respondent No.1 and Chhabra’s Associates, Respondent No. 2 (“Contesting Respondents”).

2. Indian Oil Corporation Limited (“Indian Oil”) has been added as Respondent No.3 in the Section 9 Petition since the interlocutory relief to preserve the subject property underlying the arbitration proceedings, required issuance of directions to Indian Oil.

3. Commercial Arbitration Application No.227 of 2024 (“Section 11 Petition”) seeks reference of disputes and differences between Keller and the Contesting Respondents to an arbitral tribunal, in accordance with the arbitration agreement between the parties, in exercise of powers under Section 11 of the Act.

Factual Matrix – Two Work Orders:

4. The facts relating to the existence of the arbitration agreement in this case are a bit piquant. Indian Oil gave a work order to Respondent No. 1, and Respondent No. 1 sub-contracted it with Keller. Thereafter,the parties agreed that Respondent No. 1 would commission the work to Respondent No. 2, which would then sub-contract it to Keller – all for the very same work.

5. Respondent No. 2 and Keller executed a Work Order dated October 30, 2019, which is contained at Page No.102 of the Section 11 Petition. The arbitration agreement in that Work Order is contained at Page No.109 of the Section 11 Petition. Another Work Order pertaining to the very same work and activity was subsequently executed between Respondent No. 1 and Keller on November 15, 2019. The arbitration agreement in that Work Order is contained at Page 160 of the Section11 Petition.

6. In the interest of brevity, the arbitration agreement contained in each Work Order is not extracted here. Suffice it to say that Mumbai is stated to be the agreed venue of arbitration.

Respondents’ Objections – Territorial Jurisdiction:

7. The reference to Mumbai, in fact, lies at the heart of dealing with the issue raised by the contesting Respondents. To begin with, Mr. Abhileen Chaturvedi, Learned Counsel for Respondent No.1 submits that nothing in the activity envisaged in the Work Orders has been carried out in the State of Maharashtra. Merely because the arbitration clause refers to Mumbai as the venue of arbitration, he would submit, it would not follow that this Court has jurisdiction to exercise powers under Section 11 of the Act. Learned Counsel also submits that Respondent No.1 is not located in Mumbai and therefore, no part of thecause of action claimed against this Contesting Respondent has arisen in Mumbai. Consequently, he submits, this Court will not have jurisdiction under Section 11 of the Act.

8. Ms. Mahalakshmi Ganapathy, Learned Counsel for Respondent No.2 submits that Respondent No.2 is not privy to the arbitration agreement contained in the Work Order dated November 15, 2019, under which the work is carried out. All the work is carried out for Respondent No.1 under the Work Order executed by that Contesting Respondent. Not having privity to the Work Order between Keller and Respondent No. 1, she submits, nothing has been done under the Work Order signed by Respondent No.2. Therefore, disputes and differences could only arise under the Work Order to which Respondent No. 2 is not a party. Learned Counsel insinuates that the Work Order executed by Respondent No.2 needs to be proved. According to her, the letterhead that has been annexed in the Affidavit-in-Reply filed by Respondent No.2 is different in design and some of the contents, from the letterhead on which the Work Order dated October30, 2019 signed by Respondent No.2 as annexed in the Section 11 Pet

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top