SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Bom) 448

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
A.S. CHANDURKAR, RAJESH S. PATIL, JJ.
Ebix Cash World Money Limited - Appellant 
Versus 
Ashok Kumar Goel - Respondents 
Commercial Arbitration Appeal (L) No. 32551 of 2024 With Interim Application No. 32629 of 2024 In Commercial Arbitration Petition (L) No. 25579 of 2024
Decided on : 26-03-2025

Advocate Appeared:
Mr. Mayur Khandeparkar, Advocate with Mr. Chetan Yadav and Ms. Pratibha Tiwari, Advocates, i/by R.V. & Co., for the
Appellant in CARBA(L)/35549/2024 and for Respondent No. 3 in CARBA(L)/32551/2024.
Mr. Sharan Jagtiani, Senior Advocate with Mr. Nitesh Jain, Ms. Juhi Mathur, Mr. Atul Jain, Ms. Sonia Dasgupta, Ms. Surbhi Agarwal and Mr. Abhimanyu Chaturvedi, Advocates, i/by Trilegal, for the Respondent in CARBA(L)/32551/2024.

The court upheld the validity of interim relief under Section 9 of the Arbitration Act, emphasizing that strict adherence to procedural rules is not mandatory if a prima facie case exists.

Headnote:

(A) Arbitration and Conciliation Act, 1996 - Section 37 and Section 9 - Commercial Arbitration Appeals - The appeals challenge the judgment dated 08.10.2024 allowing the Arbitration Petition filed under Section 9, directing the appellants to furnish a bank guarantee of Rs.145 crores and restraining them from dealing with their assets. The Court found that the appellants had breached the Share Holders Agreement, and the Emergency Arbitrator's decision was valid for interim relief. (Paras 2, 3, 4, 8, 10)

(B) Interim Relief - The Court emphasized that the principles under Order XXXVIII Rule 5 of the Code of Civil Procedure, 1908, need not strictly apply in arbitration cases, and a prima facie case with balance of convenience suffices for granting relief. (Paras 5, 8)

(C) Obstructionist Conduct - The court considered the appellants' conduct as obstructive, justifying the interim relief granted to respondents. (Paras 8, 9)

(D) Final Award - The Court held that the passing of the Final Award did not render the proceedings under Section 9 infructuous, as the relief sought was independent of the award enforcement. (Paras 8, 9)

Findings of Court:
The learned Judge did not commit any error in granting interim relief, and the appeals were dismissed as no demonstrable error was found in the lower court's decision.

Result: Appeals dismissed.

JUDGMENT :

(Per A. S. Chandurkar, J.

1.Admit. Both the Commercial Arbitration Appeals are taken up for final disposal.

2. The challenge raised in these appeals filed under Section 37 of the Arbitration and Conciliation Act, 1996 , (for short, ‘the Act of 1996’) is to the judgment dated 08.10.2024 passed by the learned Single Judge in exercise of jurisdiction under Section 9 of the Act of 1996. By the said judgment, the Commercial Arbitration Petition preferred by the respondent nos. 1 and 2 has been allowed and interim relief in terms of prayer clauses (b), (e) and (f) have been granted. As a result, the appellants have been directed to furnish an irrevocable bank guarantee of nationalized bank or any such other security in favour of the Prothonary, Bombay High Court, for a sum of Rs.145 crores being 80 percent of the Enhanced Call Price redeemable by the respondent nos. 1 to 3. The appellants have also been injuncted from dealing and/or encumbering and/or disposing off and/or creating third party rights and/or alienating any of the movable or immovable properties or assets owned by them. The appellants have also been directed to disclose all their assets on oath including providing fresh and better particulars along with all necessary details of such movable and immovable properties.

3. The facts that are relevant for considering the appeals are that on 12.05.2017, the appellants and the respondent nos. 1 to 5 entered into a Share Holders Agreement (SHA). On account of alleged breaches of the SHA being stated to be committed by the appellants, disputes arose as a result of which the same were referred to arbitration. The said proceedings were conducted in accordance with Singapore International Arbitration Chamber (SIAC). On 01.06.2023, the Arbitral Tribunal passed its Partial Award upholding the termination of the SHA and the obligation of the appellants to purchase the shares of the respondent nos. 1 and 2. The Arbitral Tribunal however rejected the valuation report that was submitted by Deloitte on the ground that it lacked independence. Fresh valuation was accordingly directed to be undertaken. The Arbitral Tribunal by its Order dated 01.09.2023, awarded an amount of Rs.9 Crores as costs in favour of the respondent nos. 1 and 2. The said respondents therefore filed petitions under Section 49 of the Act of 1996 before the Delhi High Court seeking enforcement of the Partial Award and the Cost Award. The respondent no. 1 on 30.11.2023 appointed Price Waterhouse and Company LLP (PwC) as the eligible valuer for determining the Enhanced Call Price. PwC submitted its valuation report on 02.01.2024 and determined the enhanced call price at the rate of Rs.181 crores. The respondent nos. 1 and 2 called upon the appellants to make payment of the aforesaid amount. The same was however refused by the appellants. On 19.01.2024, the Delhi High Court passed an order of status quo as regards the assets of the appellants in the proceedings for enforcement filed by respondent nos. 1 and 2. As the appellants failed to make payment at the Enhanced Call Price, the appellants initiated arbitration under Clause 20 of the SHA under the SIAC Rules. They also applied for emergency interim relief under Schedule-I of the SIAC Rules. Thereafter, on 13.03.2024 the Delhi High Court allowed the petitions filed by the respondent nos. 1 and 2 under Section 49 of the Act of 1996 for enforcement of the Partial Award and the Cost Award. These orders not having been challenged by the appellants, they have attained finality.

4. On 14.03.2024, the Emergency Arbitrator passed an Emergency Interim Award under Article 20.1 of the SHA and directed the appellants to furnish an irrevocable bank guarantee from an internationally recognised financial or other institution in Singapore or India for the sum of Rs.145 crores within a period of fourteen days. The respondent nos. 1 and 2 sought compliance of the aforesaid decision. However, according to the appellants, they were u

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top