IN THE HIGH COURT OF JUDICATURE AT BOMBAY
SANDEEP V. MARNE, J.
Vijay Shankar Patil - Appellant
Versus
UCO Bank - Respondents
Writ Petition No. 18098 of 2024
Decided on : 25-03-2025
(A) Industrial Disputes Act, 1947 - Section 33-C(2) - Interest on legal dues - Petitioners challenged CGIT's order denying interest on backwages from the Award dated 16 September 1999 - CGIT directed payment of Rs.8,58,825/- to legal heirs but denied interest, stating it created new rights - Court found CGIT erred, emphasizing that interest is compensatory for delayed payments and can be awarded under Section 33-C(2) - Court upheld the claim for interest at 6% p.a. from the date amounts became due until actual payment. (Paras 4, 10, 27, 29)
(B) Jurisdiction of Labour Court - The Labour Court can award interest on delayed payments under Section 33-C(2) of the I.D. Act, as established in previous judgments, including Prabhavati Ramgarib B. and Dushyant N. Dalal. (Paras 14, 18, 27)
(C) Delay in implementation - The Respondent-Bank's failure to implement the Award for over 17 years justified the award of interest, as it would prevent employers from benefiting from their own delays. (Paras 27, 28)
Facts of the case:
Petitioners, legal heirs of two workmen, challenged CGIT's order denying interest on backwages due from an Award made in 1999, which was upheld through multiple appeals.
Findings of Court:
The Court found that the CGIT erred in denying interest and ruled that the petitioners were entitled to interest at 6% p.a. on the awarded amounts.
Issues: Whether the CGIT had jurisdiction to award interest under Section 33-C(2) of the I.D. Act and the implications of the delay in implementing the Award.
Ratio Decidendi: The Court ruled that interest is compensatory and can be awarded under Section 33-C(2), emphasizing the importance of timely payments to prevent injustice.
Result: Petition allowed; Respondent-Bank ordered to pay interest at 6% p.a.
JUDGMENT :
1) Petitioners have filed this petition challenging the judgment and order dated 29 August 2024 passed by the Presiding Officer, Central Government Industrial Tribunal-II, Mumbai to the extent of denial of interest on the legal dues payable towards implementation of the Award dated 16 September 1999.
2) Two workmen-Vijay Shankar Patil and Dilip S. Kotharkar were working with the Respondent-Bank and were terminated from service. At their instance, Reference CGIT No.2/13 of 1999 relating to their demand for reinstatement was registered with Central Government Industrial Tribunal-II, Mumbai (CGIT). The Reference was answered by the CGIT in favour of the workmen by setting aside their termination and directing their reinstatement with full backwages w.e.f. 29 May 1997 alongwith continuity of service. The Bank filed Writ Petition No.4510/2000 in this Court challenging the Award dated 16 September 1999. The Petition came to be dismissed by the order of the learned Single Judge dated 30 August 2000. The Bank filed Letters Patent Appeal challenging the order of the learned Single Judge dated 30 August 2000, which was registered as LPA No.37/2013. The Appeal Court dismissed the Appeal by judgment and order dated 10 June 2014. It appears that simultaneously, the workmen had filed Writ Petition No. 8402 of 2012 seeking implementation of the Award dated 16 September 1999. By separate order passed on 10 June 2014, the Division Bench disposed of the said Petition reserving liberty for the workmen to exercise appropriate remedy for enforcement of Award before the CGIT.
3) The two workmen accordingly filed Application No.2/06 of 2014 before the CGIT under the provisions of Section 33-C(2) of the Industrial Disputes Act, 1947 (I.D. Act) seeking recovery of amount of Rs.27,55,500/-. The Application was resisted by the Respondent-Bank by filing Written Statement. The Bank contended that it had offered amount of Rs.1,99,280/- by demand draft dated 23 December 2014 which was returned by the workmen. That Shri. Vijay Patil never reported for duties and Shri. D.S. Kotharkar reported for duties as daily wager in July 2010 and continued to work till August 2015 after which he abandoned the service.
4) It appears that during pendency of the Application, the dues payable in respect of the two workmen were amended and scaled down to Rs.8,58,825/- each. The CGIT has partly allowed the application by directing that the amount of Rs.8,58,825/- be paid to the legal heirs of late, Dilip Kotharkar within a period of 2 months, failing which the said amounts would carry interest at the rate of 6% from the date of the order till realisation. The CGIT has however rejected the prayer for payment of 9% interest on the amount from the date of the Award. The legal heirs of the two workmen are aggrieved by the impugned order of the CGIT to the limited extent of denial of interest on the amount of wages and has accordingly filed the present petitions.
5) Mr. Gade, the learned counsel appearing for the Petitioners would submit that the award for reinstatement and backwages was passed on 16 September 1999 and the same was not implemented by the Respondent-Bank for a considerable period of time. That the Award has been upheld both by the learned Single Judge as well as by the Division Bench of this Court. Since the Award is upheld, the Petitioners must necessarily be paid interest on the amounts arising out of implementation of the Award. That Petitioners are not seeking interest in respect of the period prior to 16 September 1999. However, what becomes payable from 16 September 1999 and what is actually paid after the impugned order dated 29 August 2024 must necessarily carry interest.
6) Mr. Gade would submit that the CGIT has erred in holding that the award of interest would amount to creation of new right beyond the Award. He would rely upon judgment of this Court in Mrs. Prabhavati Ramgarib B. Versus. Divisonal Railway Manager, Western Railway Manager, , [2010 (4
The Labour Court can award interest on delayed payments under Section 33-C(2) of the Industrial Disputes Act, emphasizing that such interest is compensatory for delays in implementing awards.
Employees are entitled to claim interest on delayed payment of overtime wages under Section 33-C(2) of the Industrial Disputes Act, 1947, if the delay is not their fault and the cause of action arose....
The Labour Court lacks the authority to award interest in proceedings under Section 33C(2) of the Industrial Disputes Act, 1947, as such provisions are not included in the statutory framework governi....
Award of wages for intervening period – Merely because there was interim order/stay of order of reinstatement during pendency of proceedings, employee-appellant cannot be denied back wages/wages when....
The limitation provided for in it is for requesting appropriate government for issuance of recovery certificate, as provided in sub-section (1) of Section 33C of ‘the Act’ and present proceeding is n....
The general rule is that the workman is entitled to the benefits under Section 17B from the date of passing of the award unless there is undue delay on the part of the workman in approaching the Cour....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.