SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Bom) 1016

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ALOK ARADHE, CJ., SANDEEP V. MARNE, J.
 
Oil and Natural Gas Corporation Limited - Petitioner 
Versus 
Jindal Drilling and Industries Limited – Respondent
Appeal No. 41 of 2016 In Arbitration Petition No. 768 of 2014 With Appeal No. 42 of 2016 In Arbitration Petition No. 1045 of 2014 With Appeal No. 43 of 2016 In Arbitration Petition No. 767 OF 2014 With Appeal No. 45 of 2016 In Arbitration Petition No. 587 of 2014
Decided On : 10-07-2025

Advocates Appeared:
For the Appellant :Mr. Pankaj Savant, Senior Advocate with Mr. Nishit Dhruva, Ms. Khushbu Chhajed and Mr. Pulkit Awasthi, i/by. MDP Legal.
For the Respondent:Mr. V. R. Dhond, Senior Advocate with Mr. Aseem Chaturvedi, Mr. Ravitej Chilumuri, Mr. Milind Sharma, Ms. Radhika Kulkarni and Ms. Karishma Rao i/by. Khaitan & Co.

The court held that undisputed claims made by a contractor cannot be offset by related entity liabilities where no jurisdictional linkage is established.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 34 and 16 - Appeals challenging the dismissal of arbitration petitions regarding an arbitral award made in favor of a contractor - The Appellant did not deny the claims made by the contractor and argued for adjustment against a related entity’s liabilities - The Court upheld the dismissal, noting that the linkage proposed by the Appellant between the contractor and the related entity was not established. (Paras 29, 30)

(B) Jurisdiction - The principle of ‘Group of Companies doctrine’ considered - The Arbitral Tribunal was held to improperly defer ruling on the jurisdictional issue until after evidence was presented - The Supreme Court mandates that jurisdictional issues be resolved prior to adjudicating claims. (Paras 60, 76).

Facts of the case:
The Appellant, a corporation, challenged the dismissal of petitions filed against an award in favor of a contractor that included claims for unpaid dues; the Appellant sought to establish a connection with another entity in order to offset liabilities.

Findings of Court:
The court found that the Appellant had not successfully established the linkage necessary to merge the claims and liabilities between the contractor and the entity, and therefore dismissed the appeals.

Issues: Whether the Appellant is entitled to effectuate an adjustment of dues with claims made by the contractor based on a non-existent relationship with another entity.

Ratio Decidendi: The court concluded that the claims made by the contractor were undisputed by the Appellant, and since no linkage could be established with the related entity, there was no ground for the adjustment sought.

Result: Appeals dismissed.

Table of Content
1. overview of arbitration disputes between ongc and discovery. (Para 1 , 2 , 3 , 4 , 5)
2. summary of arbitration proceedings and appeals (Para 10)
3. arguments presented by the parties related to jurisdiction and claims (Para 11 , 12)
4. ongc's defense relies on adjustment claims based on sister company connections. (Para 14 , 15 , 16)
5. supreme court's ruling to remand arbitration proceedings for fresh consideration. (Para 17 , 18 , 19)
6. court's reflections on processes in arbitration and negotiating terms (Para 21 , 26)
7. legal reasoning around jurisdiction and the implications of evidence management (Para 22)
8. hearing of ongc’s appeals after jurisdiction issue resolution. (Para 27 , 28 , 29)
9. final dismissal of appeals against the arbitral award. (Para 30 , 31)

JUDGMENT :

(Sandeep V. Marne, J.)

1) These Appeals are filed by the Appellant challenging the common judgment and order dated 28 April 2015 passed by the learned Single Judge dismissing Arbitration Petition Nos. 587 of 2014, 767/2014, 768/2014 and 1045/2014 filed under the provisions of Section 34 of the Arbitration and Conciliation Act, 1996 challenging Arbitral Award dated 9 October 2013.

2) Brief facts leading to filing of the Appeals are that, the Oil and Natural Gas Corporation Ltd. (ONGC) floated a tender for charter hire of a Floating Production Storage and Off-loading vessel (FPSO) in October 2005. M/s. Discovery Enterprises Pvt. Ltd. (Discovery) submitted its bid. On 22 March 2006, ONGC awarded the contract in favour of Discovery. Pursuant to the said contract, according to ONGC, Discovery imported the vessel FPSO (Crystal Sea) for oil and gas processing in the Bombay High in the offshore fields of ONGC. ONGC paid customs duty on the said vessel on behalf of Discovery of Rs.55,78,12,857/- with an understanding that the vessel would be exported under the duty drawback scheme and that Discovery would complete all the formalities for claiming the duty drawback. Discovery allegedly failed to comply with their part of obligation and accordingly the contract was terminated on 12 November 2006. ONGC issued notice dated 12 February 2007 to Discovery and demanded various amounts towards compensation. The dispute between ONGC and Discovery was accordingly referred to the Arbitral Tribunal.

3) In the arbitration proceedings between ONGC and Discovery, ONGC impleaded M/s. Jindal Drilling and Industries Limited (Jindal)-the present Respondent. Jindal filed an application on 23 August 2008 in the arbitration proceedings under Section 16 of the Arbitration and Conciliation Act, 1996 (the Act) praying for deletion of its name from the arbitration proceedings by raising the issue of jurisdiction. By order passed by the Arbitral Tribunal on 27 October 2010, the plea of Jindal was accepted and ONGC was directed to strike off Jindal’s name from the array of the parties. Aggrieved by the order dated 27 October 2010, ONGC filed Appeal under Section 37 of the Act which came to be dismissed by this Court vide order dated 27 June 2012. ONGC filed Special Leave to Petition against the order dated 27 June 2012 before the Supreme Court which remained pending. In the meantime, the Arbitral Tribunal passed final award dated 6 June 2013 in favour of ONGC and against Discovery. Discovery has apparently not challenged the said final award dated 6 June 2013.

4) In the meantime, ONGC entered into agreement with Jindal on 2 December 2006 and took on hire the drilling unit RIG Noble Charlie Yester from Jindal to conduct drilling operations in the offshore waters of India. Three contracts were executed with Jindal on 9 December 2004, 17 August 2006 and 23 December 2003 for three other works. The four contracts awarded to Jindal by ONGC were independent contracts not relating to each other and according to Jindal, not having any connection with the contract between ONGC and Discovery. Jindal apparently executed the works awarded under the said four contracts and submitted various bill

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top