SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Bom) 1616

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Shree Chandrashekhar, C.J., Gautam A. Ankhad, J.
M/s. Aswani Associates and ors. - Petitioners
Versus
The State of Maharashtra, Through its Secretary to the Department of Urban Development Department and ors. - Respondents
Writ Petition No.4896 of 2019
Decided On : 13-11-2025

Advocates Appeared:
For the Petitioner:Mr. Girish Godbole, Senior Advocate a/w Ms. Minal Chandnani, Mr. Arvind Aswani & Mr. Rajesh Ranglani, Advocates
For the Respondent:Mr. O.A. Chandurkar, Additional Government Pleader with Ms. M.P., Thakur, Additional Government Pleader, Mr. Deepak R. More with Mr. Shivram A. Gawade, Advocates

The court established that retrospective application of government directives curtailing vested rights is impermissible unless expressly stated, reinforcing the doctrine of promissory estoppel.

Headnote:(A) Maharashtra Regional and Town Planning Act, 1966 - Section 37(1)(AA) and Section 154 - Transferable Development Rights (TDR) - Petitioners' entitlement to TDR curtailed by 50% - Petitioners sought TDR in lieu of compensation after surrendering land to the municipal corporation - Court found entitlement for full TDR quantum valid under the 2016 notification - Promissory estoppel invoked as petitioners acted upon representations. (Paras 5, 9, 11)

(B) Administrative Law - Retrospective application of government directives - A governing directive affecting vested rights must be prospective unless explicitly stated otherwise. (Paras 9, 10)

(C) Government Liability - Doctrine of legitimate expectation - The government is bound by representations made that induce action by the affected party. (Paras 10)

Facts of the case:
The petitioners challenged the curtailment of their TDR entitlement after surrendering land subject to a development plan, having complied with all relevant regulations and obligations. The surrender took place on the basis of earlier assurances from municipal authorities regarding TDR entitlements, which were later modified, leading to the current dispute.

Findings of Court:
The court ruled in favor of the petitioners, stating the actions of the respondents were binding; hence the curtailment of TDR was arbitrary and not legally sustainable.

Issues: Whether the curtailment of TDR was justified under the government’s directives and whether the petitioners maintained their rightful claim based on prior promises.

Ratio Decidendi: The court determined that the unilateral modification of rights by the municipal corporation, post-surrender of land based on earlier promises, was not permissible, emphasizing the need for fairness in government actions.

Result: Writ petition partly allowed.

Table of Content
1. challenge to tdr reduction (Para 1 , 2 , 3 , 4)
2. entitlement to full tdr based on statutes (Para 5)
3. denial of petitioners' claims (Para 6)
4. binding nature of actions and implications of directives (Para 7 , 8)
5. doctrine of promissory estoppel in government assurances (Para 9 , 10 , 11)

JUDGMENT :

GAUTAM A. ANKHAD, J.

The petitioners have challenged the order dated 17th October 2017 passed by the respondent no.5 (Deputy Director of Town Planning, Pimpri-Chinchwad Municipal Corporation), whereby the petitioners’ entitlement to the Transferable Development Rights (TDR) in respect of their surrendered land has been curtailed for the extent of 50% of TDR.

2. The petitioners state that on 30th September 1999, the Development Plan was sanctioned under the MAHARASHTRA REGIONAL AND TOWN PLANNING ACT , 1966 (“MRTP Act”). In the said plan, Reservation No. 361 (Garden) and an 18-metre-wide D.P. Road (“the reservation”) was imposed on the petitioners’ land admeasuring approximately 7000 sq. metres. The petitioners initially had development rights in the property and in the year 2013 they became owners of the land. From 31st January 2013 to 27th January 2016 the petitioners issued five notices under Section 127 of the MRTP Act calling upon the respondents to acquire the reserved land upon expiry of 10 years from the sanction of the Development Plan. Although the initial demand was for compensation, on 20th April 2016, the petitioners addressed a letter to respondent no. 5 seeking TDR in lieu of compensation for surrender of the said land.

3. On 13th July 2016, respondent no. 5 prepared a report proposing grant of TDR to the extent of 12,696.48 sq. metres to the petitioners in accordance with the notification dated 28th January 2016. The following day, the respondent no.5 issued a public notice inviting objections to the proposed grant of TDR. On 7th October 2016, the TDR Committee of the respondent no.3 approved the proposal, subject to the condition that the petitioners shall pay the Nazarana to the State Government for non-agricultural use of the land, with the permission of the Collector.

4. The petitioners surrendered 5949.88 sq. metres of land acting on the directions of respondent no. 5 and the recommendations of the TDR Committee. The surrender was effected by executing and registering a possession receipt on 14th October 2016, confirming transfer of possession of the land to the respondent no.3. On 27th July 2017, the petitioners paid Nazarana of Rs. 1,70,88,055/- by bank transfer. Following the payment, the Additional Collector, Pune, by order dated 1st August 2017, granted permission for surrender of the land in favour of respondent no. 3 with certain conditions.

5. Mr. Godbole, the learned counsel for the petitioners submitted that in terms of the notification dated 28th January 2016 issued under Section 37(1)(AA) of the MRTP Act, the petitioners were entitled to TDR equivalent to twice the area of the surrendered land. Thus the petitioners are entitled to the normal TDR quantum of 12,696.48 sq. metres. He submitted that the petitioners have paid the requisite Nazarana as demanded, surrendered the land in question to respondent no.3 on 14th October 2016, and altered their position by acting on the representations and assurances extended by the respondents. According to him, although the entire land has been surrendered, respondent no. 3–Corporation has granted only 50% of the TDR entitlement of the surrendered land. He relied upon the doctrine of promissory estoppel, contending that had the petitioners been informed that they would not receive their entitlement of two times the TDR, they would not have surrendered the land. It is submitted that thereafter the land has been developed by the respondent no.3 and a garden has been constructed thereon, and therefore the respondents, having taken the benefit of the surrender, are estopped from denying the promised balance TDR benefits to the petitioners. He submitted

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top