SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Bom) 1670

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Somasekhar Sundaresan, J.
Om Swayambhu Siddhivinayak - Appellant
Versus
Harischandra Dinkar Gaikwad and Ors. - Respondents
Arbitration Appeal No. 21 of 2025
Decided On : 04-11-2025

Advocates Appeared:
For the Appellant : Mr. Dinesh D. Tiwari a/w. Pulkeshi Gaikwad, Antony Parel and E. Siddiqui i/b Dinesh Tiwari and Associates
For the Respondent:Dr. Uday Warunjikar, Senior Advocate a/w. Sumit S. Kate

The court reaffirms the expansive nature of arbitration clauses allowing disputes from associated agreements to be subject to arbitration, notwithstanding allegations of fraud.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 8(1) - Appeal against an order rejecting application for arbitration reference - The Learned District Court ruled that the absence of an arbitration clause in the Supplemental Agreement prevents arbitration. The court clarified the standard for referral to arbitration is if a valid arbitration agreement exists, leading to a finding that disputes arose from the Development Agreement are arbitrable. (Paras 9-10, 21-22)

(B) Disputes arising from Development Agreement are subject to arbitration - Court found that the arbitration clause in the Development Agreement is expansive and covers all related disputes, including those arising from the Supplemental Agreement, countering the suggestion that such disputes fall outside the arbitration scope. (Paras 8-9, 21)

Facts of the case:
Appeal filed contesting the ruling refusing to compel arbitration on grounds the Supplemental Agreement lacks an arbitration clause. Disputes regarding specific performance sought by landowners under Development Agreement at the high court.

Findings of Court:
The Impugned Order was set aside leading to referral to arbitration, determining that valid arbitration agreement existed despite the issues concerning the Supplemental Agreement.

Issues: The central issues were the applicability of arbitration based on existing agreements and the role of fraud allegations in regard to arbitration jurisdiction.

Ratio Decidendi: The court established that failures to recognize an arbitration agreement under Section 8(1) can lead to unsuitable jurisdictional decisions, emphasizing the expansive nature of arbitration clauses and establishing that fraud allegations alone do not preclude arbitration.

Result: Appeal allowed, Impugned Order set aside.

Table of Content
1. context and background of the arbitration appeal. (Para 1 , 2 , 3 , 4)
2. parties' arguments regarding arbitration applicability. (Para 5 , 6 , 7)
3. court's observations on the arbitration agreement. (Para 8 , 9 , 12 , 14 , 19)
4. court's ratio decidendi regarding arbitration and fraud. (Para 10 , 21 , 29)
5. final decision and implications for arbitration. (Para 30 , 32 , 33)

JUDGMENT :

Somasekhar Sundaresan, J.

Context and Factual Background:

1. This is an Appeal filed under Section 37 of the Arbitration and Conciliation Act, 1996 (“the Act”) challenging an order dated March 11, 2025 (“Impugned Order”) rejecting an application filed by the Appellant under Section 8 of the Act. The disputes and differences between the parties relate to transactions between them arising out of a Development Agreement, dated May 3, 2011 (“Development Agreement”) and a further Supplemental Agreement dated May 25, 2021 (“Supplemental Agreement”).

2. The Appellant, Om Swayambhu Siddhivinayak (“Developer”) had agreed under the Development Agreement to provide a certain specified area of developed property to the Respondents, who are the owners of the land on which the development was to take place (“Owners”). The Owners have filed Special Civil Suit No. 157 of 2024 before the 4th Joint Civil Judge, Senior Division, Kalyan, inter alia, seeking specific performance of the provision of certain saleable area to the Owners (in the quantum of 8,937 sq.ft and 4927 sq.ft.), and a cancellation of the Supplemental Agreement.

3. It is the case of the Appellant that Clause 30 of the Development Agreement, which contains the arbitration clause, is an expansive clause and all disputes and differences between the parties in connection with the development contracted in that Development Agreement are amenable to arbitration, and therefore, no Civil Court could take cognizance of any dispute between the parties in connection with the Development Agreement.

4. A detailed reading of the Impugned Order would show that the Learned District Court was swayed by only one factor, namely, that Supplemental Agreement did not contain any arbitration clause and the Development Agreement alone contains an arbitration clause. In paragraph 4 of the Impugned Order, it is recorded by the Learned Judge that the suit is for cancellation of the Development Agreement as well as the Supplemental Agreement. The Learned Judge was persuaded to rule that in the absence of an arbitration clause in the subsequent agreement and considering the nature of the dispute, the arbitrator is not competent and empowered to decide the disputes between the parties. Therefore, the Learned Judge refused to refer the parties to arbitration and has continued to deal with the suit himself.

Contentions of the Parties:

5. Dr. Warunjikar, Learned Senior Advocate on behalf of the Respondents seeks to defend the Impugned Order on the premise that the parties had a layered and a structured approach of dispute resolution divided between Clause 13 of the Development Agreement, and Clause 30 of the Development Agreement. According to him, Clause 30 of the Development Agreement deals with all disputes and differences connected to the development contracted in the Development Agreement, but Clause 13 deals with the provision of the developed area in terms of Clauses 1 and 2, for which, the parties had agreed that they would approach a Court for a declaration which would be binding on the parties. Dr. Warunjikar would also contend that the Suit seeks a declaration that the Supplemental Agreement is a product of fraud and that arbitral tribunals cannot adjudicate serious allegations of fraud.

6. Mr. Dinesh Tiwari, Learned Advocate on behalf of the Appellant would submit that even a plain reading of the prayers in the Suit would demonstrate that the relief sought is of specific performance of the Development Agreement, which is subject matter of the arbitration agreement. As regards the distinction between Clause 13

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top