SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Cal) 429

IN THE HIGH COURT AT CALCUTTA
SHAMPA DUTT (PAUL), J.
Twamev Construction And Infrastructure Limited - Appellant
Versus
The Kolkata Municipal Corporation and Ors. - Respondent
WPO No. 1444 of 2021
Decided On : 12-08-2025

Advocates:
Advocate Appeared:
For the Appellant : Mr. Satarup Banerjee, Adv. Mr. Avishek Guha, Adv. Sk. Sariful Haque, Adv. Mr. Ankush Majumdar, Adv.
For the KMC : Mr. Alak Kumar Ghosh, Adv. Mr. Gopal Chandra Das, Adv.

The existence of an arbitration clause mandates dispute resolution through arbitration, and mere allegations of fraud do not preclude this process.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 8 - Writ petition - The petitioner sought relief for monetary claims following termination of a construction contract without proper arbitration process. Respondent invoked a bank guarantee citing project delays. The court emphasized respecting arbitration agreements, adjudicating disputes primarily through arbitration, and noted that mere allegations of fraud do not negate this obligation. The petitioner was directed to pursue remedy via arbitration. (Paras 20, 21, 23, 24)

(B) Contractual obligations - Importance of adhering to dispute resolution mechanisms laid down in contractual agreements was highlighted, with judicial intervention limited when an arbitration clause exists. (Paras 20, 22)

Facts of the case:
Petitioner, engaged in a public works project, alleged wrongful contract termination and sought reimbursement for withheld payment of Rs.5,46,10,108/- and bank guarantee invocation. Procedural failures in dispute resolution were noted.

Findings of Court:
The court found that the dispute is arbitrable and should be submitted to arbitration as per the contract agreement.

Issues: The core issues included the challenge to the validity of respondent's actions regarding contract termination and the appropriateness of seeking judicial remedy for monetary claims.

Ratio Decidendi: The court determined that adherence to the arbitration clause in the contract is essential and mere allegations of fraud do not exempt the parties from this obligation.

Result: Writ petition dismissed; parties directed to seek arbitration.

Table of Content
1. facts surrounding the contractual agreement (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8)
2. court's observations regarding arbitration and contract clauses (Para 9 , 10 , 11 , 12)
3. petitioner's claims and respondents' defenses (Para 14 , 15 , 16 , 17 , 18)
4. arbitration principles and judicial intervention limits (Para 19 , 20 , 21 , 22 , 23)
5. final directions regarding arbitration and case disposition (Para 25 , 26 , 27 , 28 , 29)

JUDGMENT :

SHAMPA DUTT (PAUL), J.

1. The writ application has been preferred praying for a direction upon the Kolkata Environmental Improvement Investment Program (KEIPP) being the respondent No.2 herein to refund/reimburse the extra amount of Rs.5,46,10,108/- withheld by the respondent no.2 along with interest accrued thereof to the petitioner.

2. The petitioner’s case is that by a tender dated 25th March, 2016, Kolkata Environmental Improvement Investment Program by a publication in a local newspaper invited bid for a project for sewerage and drainage network in Rania Box Catchment (Part of ward 111, 112, & 113) in Borough XI, Contract Package No.KEIIP/NCB/TR-2/SD10/2015-16, for an amount of Rs.76,02,79,999.80. The petitioner being eligible for such projects and adhering to the guidelines of the said tender, submitted its financial proposal on 17th October, 2016.

3. The respondent no.2 being the project director, by letter dated 17th October, 2016 accepted the bid and/or financial proposal dated 25th March, 2016 for execution of the sewerage and drainage network in Rania Box Catchment (Part of ward 111, 112, & 113) in Borough XI, Contract Package No.KEIIP/NCB/TR-2/SD10/2015-16 thereafter requested the petitioner to provide performance security in accordance of the clause 42.1 of Instruction of Bidders (ITB).

4. Thereafter as per the course of action to start the project the petitioner engaged its team at the project site initiating the project as soon as possible after receiving the notice to proceed dated 25th January, 2017 and infused an amount of Rs.37,13,022/- for mobilization of the project, moreover the petitioner deposited an amount of Rs.10,31,395/- as retention money with the respondent no.2 and also furnished a Bank Guarantee dated 25th November, 2016 valid till 22nd November, 2020 for an amount of Rs.7,60,28,000/- to the respondent no.2.

5. The petitioner’s further case is that during a joint inspection conducted on 27th December, 2017 the respondents were satisfied with the quality of work, but subsequently there was some delay in implementation of the project and, as such, several letters were exchanged between the petitioner and the respondent no.2 in regard to the progress of the work, quality of work and delay in execution the work. In the meantime, an application under Insolvency and Bankruptcy Code, 2016 was filed before the National Company Law Tribunal (NCLT) Kolkata Bench by State Bank of India and others for initiation of corporate insolvency resolution process in the year 2018. Subsequently, by an order date 13th March, 2019 the NCLT, Kolkata was pleased to admit the corporate debtor i.e., the petitioner herein in the corporate insolvency resolution process and accordingly an interim resolution professional was appointed, thereafter the company’s new committee of creditors was formed and subsequently, on 24th February, 2020, EDCL Infrastructure Limited and US Constructions Pvt. Ltd. was confirmed as successful resolution applicant.

6. Without any notice to the petitioner, the respondent no.2 illegally invoked the Bank Guarantee provided by the petitioner of Rs.7,60,28,000/- on 21st August, 2018.

7. It is submitted that that at the time of termination, an amount of Rs.1,84,62,208.37 was due and payable by the respondent in regard to the work done till the purported termination of the contract by the respondent no.1 being bill no.RA-3 amounting to Rs.1,81,95,818.60 and bill No.RA-4, amounting to Rs.2,66,389.77.

8. Being aggrieved and dissatisfied with the action of the resp

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top