2016 Supreme(Pat) 261

IN THE HIGH COURT OF JUDICATURE AT PATNA
VIKASH JAIN, J.
M/s. Vishal Rolling Mills Pvt. Ltd. – Petitioners
Versus
The Bihar State Power (Holding) Company Limited – Respondents
Civil Writ Jurisdiction Case No.2311 of 2014
Decided On : 25-04-2016

Advocates Appeared:
For the Petitioners:Mr. Rajeev Kumar Verma, Sr. Advocate Mr. Rajkishore Prasad, Advocate
For the Respondent:Mr.Vinay Kirti Singh, Advocate Mr. Akhileshwar Singh, Advocate
For the State : Mr. Ranjay Kumar Singh, AC to SC 16

Headnote:Bihar and Orissa Public Demands Recovery Act, 1914–Section 5–Certificate Proceeding–Requisition issued against the Managing Director of a Company for recovery of dues owing to the company–Such requisition is invalid–Certificate proceedings as well as the requisition quashed–Respondents given liberty to initiate fresh certificate proceeding. (Para 8)

       2002 (2) PLJR 553–Referred.

JUDGMENT :

1. Heard learned counsel for the petitioners, learned counsel for the respondent Power Company and for the State.

I.A. No. 537 of 2015

2. This Interlocutory Application has been filed for amendment in the prayer portion of the writ petition by incorporating prayer Nos. (iv) and (v) as enumerated. At the time of hearing, however, learned counsel for the petitioner does not press the proposed prayer No. (iv) and seeks permission to delete the same, which is granted. It is further prayed that prayer No. (v) be permitted to be incorporated in the writ petition, reading as follows :-

“(v) To issue an appropriate writs/orders/ directions in the nature of writ of Mandamus directing the respondents to grant an opportunity to file a detailed objection under Section 9 of the Bihar and Orissa Public Demands Recovery Act, 1914 (“PDR Act” hereinafter) and till the final adjudication of the objection so filed by the petitioners, the warrant of arrest directed to be issued against the petitioner no. 2 may be kept in abeyance.”

3. Having regard to the nature of prayer, the same is allowed.

4. I.A. No. 537 of 2014 stands disposed of.

CWJC No. 2311 of 2014

The present writ petition has been filed for quashing the entire certificate proceeding arising out of Certificate Case No. 59 of 2001-02 pending before the respondent Certificate Officer; and for connected reliefs.

2. Learned counsel for the petitioner raises several issues in the present writ petition and has made detailed submissions in support of his contention that the entire certificate proceedings are not maintainable. He has, inter alia, contended that the impugned proceedings are illegal on the ground that the Electrical Executive Engineer (Rev.), Electrical Circle, Saharsa, being the certificate holder, could not himself have acted as the Certificate Officer, and that consequently, the subsequent resumption of the same certificate proceedings by the District Certificate Officer, Saharsa after a lapse of several years is unsustainable. Having heard learned counsel for the petitioner, however, this Court is of the view that the writ petition can be disposed of on the foundational question relating to the validity of the requisition issued under Section 5 of the PDR Act by the Electrical Executive Engineer (Rev), and the merits of the remaining contentions of the Petitioner need not be entered into.

3. It is submitted that a bare perusal of the said requisition makes it obvious that the same has been issued in the name of Sri Kartik Kumar, the petitioner no. 2 herein, who happens to be the Managing Director of M/s Vishal Rolling Mills Pvt. Ltd., the petitioner no. 1. By the said requisition, a certificate proceeding is sought to be initiated for recovery of the dues relating to the said petitioner company. Learned counsel for the petitioner relies on a decision of this Court in Kanhaiya Lal vs. The State of Bihar and others [2002 (2) PLJR 553], in view of which it is submitted that dues owing by a company cannot be recovered from its Director.

4. Learned counsel for the respondent power company as well as for the State have been heard.

5. It is not in dispute between the parties that the requisition in Form no. 2 describing Sri Kartik Kumar, petitioner no. 2, as the certificate debtor in column 1 thereof has been issued by the certificate holder. It is also not in dispute that Rs. 1,39,31,286/- sought to be recovered through certificate proceeding represents the dues of the petitioner company and not of the petitioner no. 2. Based on such requisition, a certificate in Form no. 1 has been filed in the office of the Certificate Officer, Saharsa, column no. 3 whereof names the petitioner company as the certificate debtor.

6. Section 5 of the PDR Act provides for issuance of a written requisition in respect of any public demand which is due against a person to be sent to the certificate officer. Section 6 of the PDR Act makes it clear that the certificate may be filed upon receipt of the afo








Click Here to Read the rest of this document