2020 Supreme(Pat) 683
IN THE HIGH COURT OF JUDICATURE AT PATNA
ASHUTOSH KUMAR, J.
CWJC No.19624 of 2016
(17.2.2020)
M/s Supreme Enterprises ... Petitioner
vs.
State of Bihar & Ors. – Respondents
Subject
Contract Disputes - Breach of Contract
Headnote
Government Contract – Cancellation of Work Order – Supply of vehicles – Very fact that a vehicle (Sky lift) has already been purchased through another source and respondent corporation is not in need of any other vehicle of that kind and has also entered into an agreement with company for maintenance of street lights for seven years, this Court ought not to and cannot issue any direction to Corporation to accept vehicle (Sky lift) offered by Petitioner – However, with respect to no notice having been served upon petitioner for cancelling work order and giving an expectation in estimation of petitioner that delay in supply of vehicle has been condoned and legitimate expectation that supply would be accepted, petitioner would be at liberty to sue Corporation for damages before appropriate forum. (Paras 14 and 15)
For the Petitioner: Mr. Anurag Saurav.
For the Respondent: M/s Kinkar Kumar, Ms. Deepika Sharma, Ravish Chandra.
For the Corporation : Mr. Gyan Prakash Ojha.
Ashutosh Kumar, J. – Heard Mr. Anurag Saurav, learned advocate for the petitioner, Mr. Gyan Prakash Ojha for Municipal Corporation, Bihar Sharif, Mr. Ravish Chandra, AC to SC-6 and Ms. Deepika Sharma, AC to SC-9 respectively.
2. The petitioner had supplied a chassis mounted skylift to Bihar Sharif Municipal Corporation against a tender in which a contract was entered into between the corporation and the petitioner.
3. The dispute now is that the corporation has taken a stand that since the delivery was much beyond the stipulated time, the vehicle was not accepted at any point of time; rather another skylift was purchased, seeing the urgency, from another organization/firm.
4. The case of the petitioner is that he was asked to supply the aforesaid vehicle with a warranty period for three years. Later, on the showing of the petitioner that there was an agreement, in principle, for providing only one year warranty, necessary amendment in the work order was made. Thereafter, when the vehicle was not supplied, a warning letter was issued to the petitioner. Shortly thereafter, the petitioner purchased the vehicle and also obtained the permission of the corporation for temporary registration as such vehilce could not have been transported from the manufacturer to the premises of the corporation without temporary registration.
5. It appears that such permission was granted. It is on the basis of the aforesaid permission for temporary registration that the petitioner claims that the delay in supply of vehicle was condoned and the agreement between the petitioner and the corporation was made to subsist. The vehicle was put to a 3rd party test and according to the petitioner, the same was delivered and kept in the premises of the corporation.
6. These facts have been controverted by the learned advocate for the corporation on various counts viz. the presence of the vehicle in question in the premises of the corporation and condonation of the delay in supply of the vehicle.
7. It was at that stage that the present writ petition was filed for setting aside the order of respondent no. 3, terminating the work contract/supply of skylift and for a direction to accept the same without demur.
8. The matter was heard on several dates by this Court but no definitive pronouncement could be given because of the fact that the corporation did not have a full fledged Commissioner/Chief Executive Officer.
9. Be that as it may, from the orders passed by this Court, it can be gleaned that one point of time, an adjournment was granted for the corporation to take a decision in that matter.
10. Be it noted that the primary grievance of the petitioner viz. no show cause notice having been issued to him before cancelling the work order, subsisted was continuously agitated throughout the present proceeding and in the proceedings before the Municipal Corporation.
11. It further appears from the records that an Empowered Standing Committee of which the Mayor of the city was also a member was constituted and deliberations were held. The deliberations of the Empowered Standing Committee referred to above have been brought on record by way of supplementary affidavit on behalf of the corporation (respondent no. 3). The order dated 12.07.2018 contained in Memo No. 2200 indicate the stages through which the claim of the petitioner was put to. The order of the standing committee takes note of the fact that the warranty period was reduced from three years to one year but no specific promise was doled out to the petitioner for any extension of time supply of the vehicle/apparaturs in question. It is precisely for this reason that the petitioner got a 3rd party inspection done and claims to have delivered the vehicle in the premises of the corporation. The order takes note of the fact that the limitation period for supplying the vehicle started running from 29.06.2016 and when, after the lapse of thirty days, the vehicle was not supplied, a reminder was issued but to no avail. On 11