P.C.MALLICK
ARBN. SETH KERORIMAL ADWANI – Appellant
Versus
UNION OF INDIA – Respondent
( 1 ) THIS is an application under Section 33 of the Indian Arbitration Act challenging the validity of an arbitration agreement and an award passed thereunder. The petitioner undertook the construction of a runway at Gauhati Airfield under a contract with the Government evidenced by a tender submitted by him and accepted on behalf of the President, Indian Union by the Chief Engineer, C. P. W. D. , Aviation Wing, on or about October 28, 1950. Time allowed for completion of the work was six months from the date of the written order: to commence the work, which, in the instant case, is November 15, 1950. Work of construction was not completed within time and it is alleged in the petition that not only the petitioner cannot be held responsible for this delay but that it has been recognised in writing by the senior Government officials-that this delay is not attributable to any fault OF laches on the part of the contractor. The construction work was actually completed on October 29, 1951. On April 25, 1952, the contractor by his letter to the Executive Engineer claimed refund of the security deposit including the earnest money deposited by the contractor. It is alleg
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.