IN THE HIGH COURT OF JUDICATURE AT CALCUTTA
SOUMEN SEN, RAVI KRISHAN KAPUR, JJ.
Laxmi Pat Surana - Appellant
Versus
Voltas Ltd. - Respondent
A.P.O.T. No. 25 of 2019, G.A. No. 789 of 2019 with A.P. No. 478 of 2017
Decided On : 05-07-2019
Arbitration and Conciliation Act - Claim for price of goods sold and delivered and for services rendered - Section 34 - Summary of legal principles under Section 34 of the Act
Fact of the Case:
The appellant challenged an order dismissing an application under Section 34 of the Arbitration and Conciliation Act, 1996, regarding an award for price of goods sold and delivered and for services rendered. The appellant had placed a work order for a central air-conditioning system, and the respondent claimed a balance sum of Rs.22,31,532.60/- inclusive of interest. The appellant counterclaimed for an amount of Rs. 6,21,154.30/- for delay in completion of works and liquidated damages.
Finding of the Court:
The court found that the Arbitrator and the Learned Single Judge had duly considered the correspondence and interpreted the same, and the award contained reasons based on relevant materials. The court upheld the impugned order and award, emphasizing the limited role of the court in reviewing arbitral decisions under Section 34 of the Act.
Issues: The issues included the interpretation of correspondence, breach of contract, entitlement to liquidated damages, furnishing of guarantees and warranties, and the entitlement to interest.
Ratio Decidendi: The court's decision was based on the principle that the court's role in reviewing arbitral decisions under Section 34 of the Act is limited, and the interpretation of the contract and correspondence is within the arbitrator's jurisdiction.
Final Decision: The court upheld the impugned order and award, dismissing the appeal and the connected application without costs.
JUDGMENT :
RAVI KRISHAN KAPUR, J.
1. This is an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 ("the Act"). In this appeal, the appellant has challenged an order and judgment dated 6 December, 2018 ("impugned order") whereby the Learned Single Judge had dismissed an application filed under Section 34 of the Act challenging an award dated 28 March, 2017 ("impugned award") passed by the Sole Arbitrator.
2. The question before the Sole Arbitrator concerned a claim for price of goods sold and delivered and for services rendered. By the impugned award, the Arbitrator has directed the appellant to pay a sum of Rs.22,31,532.00/- alongwith interest @ 6% per annum from November 19, 2008 till realisation of its dues to the respondent.
3. Briefly stated, by a contract dated 7 April, 2007 the appellant had placed a work order for design, engineering, testing and commissioning of a water cooler type central air-conditioning system for a complex situated at Kharagpur. The respondent accepted the work order and by a letter dated 20 April, 2007 confirmed the value of the entire project at Rs. 1,24,23,086/- subject to levy of statutory duties and taxes. The contract provided that the entire work was to be completed by the respondent by 30 June, 2007. The other terms and conditions of the contract stipulated that the respondent was to provide warranties/guarantees and satisfactory completion certificates upon completion of the said work and completion of a performance test. Admittedly, the respondent provided a handing over certificate on 21 August, 2008. The claim of the respondent before the Arbitrator was for price of goods supplied and delivered.
4. It is the case of the respondent that notwithstanding satisfactory completion of the work, the claimant had failed to pay the balance sum of Rs. 22,31,532.60/- inclusive of interest. On the other hand, the appellant had filed a counterclaim for an amount of Rs. 4,32,81,496.20/- under various heads including for liquidated damages. It is an admitted position that before the Arbitrator at the 22nd sitting, the appellant withdrew five of his initial claims after which the counterclaim was restricted to Rs. 6,21,154.30/- on account of liquidated damages and for delay in completion of works by the respondent. The appellant also claimed an additional amount on account of the delay in execution of works and cost of electricity. It was the primary grievance of the appellant that the respondent had failed, neglected and refused to carry out the performance test as stipulated under the contract despite repeated reminders on 5 September 2008, 6 January 2009, 16 June 2009, 28 June 2010 and 11 August, 2010. The appellant further contended that he was ready and willing to make payment to the respondent but only on the contractual terms and after completion of all the obligations of the respondent under the contract. The appellant also contended that the respondent was liable to compensate the claimant for the delay in completion of the works.
5. Mr. L. P. Surana, the appellant (appearing in-person), contended that the award passed by the Arbitrator is erroneous both on facts and on law and is liable to be set aside. He urged that the award was based primarily on the admissions of the claimant contained in the letter dated 16 June, 2009, wherein the appellant had recorded its appreciation for the good air conditioning and plant installation and commissioning by the respondent and further requested them to continue to provide the good services for the proper operation and maintenance of the air conditioning system. In the said letter, the appellant had also sought for time to make payment of the balance amount to the respondent on the ground of facing acute financial crisis. It was further contended by the appellant that the said letter did not contain an unequivocal and categorical admission of liability and the same should have been read alongwith the other letters dated 16 June 2009, 28 June
Associate Builders Vs. Delhi Development Authority (2015) 3 SCC 49
McDermott International Inc. Vs. Burn Standard Co. Ltd. (2006) 11 SCC 181
Navodaya Mass Entertainment Ltd. Vs. J.M. Combines (2015) 5 SCC 698
MMTC Ltd. Vs. Vedanta Ltd. (2019) 4 SCC 163
Mahanagar Telephone Nigam Ltd. Vs. Finolex Cables Limited reported at 2017 (166) DRJ 1
Steel Authority of India Vs. Gupta Brothers Steel Tubes Limited (2009) 10 SCC 63
Sumitomo Heavy Industries Limited Vs. Oil and Natural Gas Corporation (2010) 11 SCC 296
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.