SABYASACHI BHATTACHARYYA
Debashis Mitra – Appellant
Versus
Union Of India – Respondent
JUDGMENT
Sabyasachi Bhattacharyya, J. - Upon succeeding in a tender floated by the Bharat Sanchar Nigam Limited (BSNL) for the purpose of outsourcing maintenance and provisioning of landline and broadband for external plant of copper network in CTD under Business Area-West, the petitioner was awarded a contract.
2. Sub-clause 3.6(b) of the said contract provides that the contract will be terminated and PBG forfeited upon non-performance and failure to meet all the SLAs, that is, MTTR, Provisioning, fault clearance and repeat fault parameters for consecutive three months. It was further stipulated in the said clause that notice shall be served for non- performance in the first month, second month and third month before final termination.
3. It is contended that although the petitioner gave written replies to each of the three notices issued by the respondent-Authorities, none of those was considered by the respondents.
4. It is submitted that the respondent-Authorities asked the petitioner to continue the work, while in the same breath issuing show-cause notices on allegations of faults on the part of the petitioner.
5. Learned counsel for the petitioner places reliance on the several re
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.