IN THE HIGH COURT OF CALCUTTA
Sabyasachi Bhattacharyya, J.
Joyanti Electronics, Represented By Sri. Kartick Maji (Bauri) - Appellant
Versus
West Bengal State Electricity Distribution Company Limited And Others - Respondent
W.P.A. No. 22399 of 2019
Decided On : 14-03-2022
WBSEDCL - Contract Dispute - Office Order No.1171, Code of Criminal Procedure, Constitution of India - The judgment discusses the selection process for maintenance and repair work of Substations by WBSEDCL, allegations against the petitioner, and violation of fundamental rights. Key legal provisions include natural justice, right to equality, and right to carry on business under the Constitution of India. The court's decision sets aside the engagement of respondent no.6 and directs the initiation of a transparent tender process for the remaining tenure.
Fact of the Case:
The petitioner, an enlisted contractor under WBSEDCL, challenged the engagement of respondent no.6 for maintenance work, alleging unfair selection process and false allegations against the petitioner.
Finding of the Court:
The court found serious allegations against the petitioner, lack of transparency in the selection process, and violation of fundamental rights. The engagement of respondent no.6 was set aside, and a transparent tender process was directed for the remaining tenure.
Issues: Unfair selection process, false allegations, lack of transparency, violation of fundamental rights, engagement of respondent no.6.
Ratio Decidendi: The court emphasized the importance of transparency in the selection process, the need for natural justice, and the violation of fundamental rights. The engagement of respondent no.6 was set aside due to lack of transparency and violation of the petitioner's rights.
Final Decision: W.P.a. No. 22399 of 2019 is allowed, setting aside the engagement of respondent no.6 and directing the initiation of a transparent tender process for the remaining tenure. Costs were awarded to the petitioner, and the respondents were permitted to take appropriate legal steps if misconduct is proved.
JUDGMENT
Sabyasachi Bhattacharyya, J. - The petitioner is an enlisted contractor under the West Bengal State Electricity Distribution Company (WBSEDCL) for certain allotted categories and was engaged in several projects undertaken by the WBSEDCL.
2. It is alleged by the petitioner that the WBSEDCL, vide its Office Order No.1171 dated February 7, 2017, specifically decided that when there is dearth of suitable contractors or agencies, such kind of jobs may be awarded to agencies and/or contractors having provisional enlistment, after verifying their credentials and performances, in consultation with authorities of a rank not below that of additional Chief Engineer and Zonal Manager. a copy of the said Officer Order is annexed as annexure P-5 to the writ petition.
3. The petitioner, in the capacity of a small scale contractor and general order supplier of materials of equipment and also an enlisted contractor under the Distribution Wing of the WBSEDCL, having Renewal Enlistment No.:- Distribution Enlistment - R/2018-19/149, was not only provisionally enlisted as a contractor of the WBSEDCL long back but was also subsequently extended in such capacity for the years 2015-16, 2016-17, 2017-18 and 2018-19. The copies of the relevant licences, Renewal of Enlistment and other related documents are annexed collectively as annexure P-1 to the writ petition.
4. The Divisional Manager, Bishnupur (O & M) Division of the WBSEDCL decided to deploy an enlisted agency and/or contractor for R & M Work of 33 KV and 11 KV HTOH lines emanating from Ramsagar 33/11 KV Substation.
5. The petitioner contends that, time and again, the petitioner wrote to the respondent-authorities requesting the petitioner's selection for such work. However, the respondents took no initiative in that regard till the date of allotment of such work. Copies of such representations are also annexed and collectively marked as annexure P-6 to the writ petition.
6. Subsequently, the petitioner learnt that the Divisional Manager, Bishnupur Division (respondent no.3 herein), by his impugned Memo No. BSPD/2RSO/1231 dated October 3, 2019, issued Work Order in favour of respondent no.6 (M/s. Ghosh Construction) in connection with the said R & M work at Ramsagar and had directed respondent no.6 to commence maintenance work immediately after causing necessary inspection. Such Work Order is annexed as annexure P-7 to the writ petition.
7. Learned counsel for the petitioner submits that the Work Order itself reveals that respondent no.6 was selected pursuant to prayers made on his behalf vide Receipt No.6995 dated January 9, 2019 and Receipt No.2072 dated July 3, 2019, vide approval No.533 dated July 16, 2019. No tender process was initiated for such selection.
8. In terms of credentials and performance, the petitioner contends to be far more eligible for the work-in-question than respondent no.6. The petitioner was also engaged as a sub-contractor of a turn-key agency, which constructed the said Ramsagar 33 KV line and 11 KV line and associate works of line as well as for Ramsagar 33/11 KV Substation Switchyard Electrical Works and had specific practical knowledge about the said substation, which has to be maintained as per the Work Order.
9. The present writ petition has been preferred, challenging the Memo No. BSPD/2RSO/1231 dated October 3, 2019 issued by respondent no.3 engaging respondent no.6 and seeking ancillary reliefs.
10. Learned counsel appearing for the petitioner vociferously contends that false allegations have been made against the petitioner in the affidavit-in-opposition filed respectively by respondent nos. 1 to 5 and respondent no.6 in the writ petition. Learned counsel points out that, in paragraph no.4 of the affidavit-in-opposition used by respondent no.6, it has been stated that the respondent-authorities duly rejected the petitioner's application on the ground that the writ petitioner is a miscreant involved in illegal activity at Ramsagar Substation and that the writ
Bharat Singh and others vs. State of Haryana and others
Erusian Equipment Chemicals Ltd. vs. State of West Bengal and another
UMC Technologies Private Limited vs. Food Corporation of India and another
AI
The judgment establishes the principle that transparency in the selection process, adherence to natural justice, and respect for fundamental rights are essential in contractual engagements with publi....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.