2022 Supreme(Cal) 1605

IN THE HIGH COURT AT CALCUTTA
KRISHNA RAO, J.
Union of India – Petitioner
Versus
Neo Built Corporation - Respondent
AP 1717 of 2015
Decided On : 13-07-2022

Advocates Appeared:
For the Petitioner: Ms. Aparna Banerjee.
For the Respondent: Mr. Sakya Sen, Mr. Supratim Laha, Mr. Sabyasachi Sen.

Headnote:

Arbitration and Conciliation Act, 1996 – Section 34 – Sought for settlement of dispute – Arbitrator Tribunal – Held, Court now come to fourth head of public policy, namely, patent illegality – It must be remembered that under Explanation to Section 34(2)(b), an award is said to be in conflict with public policy of India if making of award was induced or affected by fraud or corruption – Court finds that claimant had raised altogether 16(Sixteen) claims but Ld. Arbitral Tribunal allowed only 5 (Five) claims and Tribunal has allowed said claim after considering terms of contract and documents supplied by parties. Ld. Tribunal assigned well reasons while allowing claim of claimant – Dismissed.

JUDGMENT :

(Krishna Rao, J.) :

1. The petitioner has filed the instant application under Section 34 of the Arbitration and Conciliation Act, 1996 against the award passed by the Arbitrators dt. 01.9.2015.

2. On 03.10.2008, the Chief Engineer, Metro Railway/Calcutta had published a tender notice with respect of execution of ROB and road approaches at Kharagpur in replacement of Manned Level Crossing at KM 118/ 4-5, KM 0/18 and 123/2-3 in Kharagpur -Bhadrak Section of South Eastern Railway.

3. The respondent had participated in the said tender and the said work was awarded in favour of the respondent. The petitioners vide letter dt. 05.02.2009 accepted the rate quoted by the respondent for an amount of Rs. 18,77,85,218.89/- against the estimated value of Rs. 17,99,99,99.40/-.

4. On 29.09.2009, an agreement was executed between the petitioner and the respondent being agreement no. MTP/Civil/887 and the time of completion of the said work was 24 months from the date of issue of the letter of the acceptance.

5. On 05.02.2009 a letter of acceptance was issued in favour of the respondent but the progress of the work was very slow. In spite of several notices and reminders the progress of the work was very slow and accordingly vide notice dt. 12.07.2010, the petitioners by invoking Clause 62 of General Clause of Contract, 2001, the Contract was terminated.

6. As per the agreement the stipulated period of completion of the work was 04.02.2011 but the contract was cancelled 12.07.2010, much prior to the date of completion on the ground that the respondent had executed only 29 % of the work and 71 % of the work was remain to be completed.

7. The petitioner has terminated the Contract and has also not made the payment to the respondent and accordingly the respondent had sought for settlement of dispute through the arbitrator and accordingly, the petitioner had appointed consisting of three arbitrators.

8. The respondent had filed statement of claim consisting of 16 claims total amounting to Rs. 12,26,53,003.00/-along with interest which are as follows:-

Claim No.

Description

Amount (Rs.)

1(a)

Amount payable for the work executed but not paid (Details, vide, ANNEXURE – I,II,III)

3,19,50,515.00

1(b)

Price Variation as per Clause No. 2. 18, Page 42, Section 2, Special condition of Contract. (Details, vide, ANNEXURE – IV).

28,57,989.00

2

Amount payable for refund of Security Deposit (S.D) Wrongfully forfeited :

A) Earnest Money adjusted to S.D. = Rs.10,50,000.00

B) S.D. deducted from Bills = Rs. 16,82,660.00

TOTAL = Rs. 27,32,660.00

27,32,660.00

3.

Amount payable for refund of Performance Guarantee wrongfully encahsed/forfeited.

93,89,261.00

4.

Amount payable for dewatering work at different stages of work for the structures falling on ‘P’ & ‘X’ lines of R.O.B. (Details, vide, ANNEXURE – V).

2,87,725.00

5

Amount payable for filling and leveling up the swampy land which was being used as drainage basin/receptacle of drainage water from the adjoining areas (Sub-Divisional) Hospital side, I.I.T. side etc.) with earth, moorum, sand etc. for making the area fit for execution of R.O.B. (Details, vide, ANNEXURE – VI)

1,18,39,356.00

6

Amount payable for expenditures incurred for carriage of steel materials and cement by Van/Hand Cart from stack yard to workplace including loading, unloading etc. complete (Details, vide, ANNEXURE-VII).

3,53,875.00

7

Amount payable for expenditures incurred for re-handling and re-carriage of materials due to scarcity of space in the working site for stacking of materials (Details, vide, ANNEXURE – VIII)

2,37,200.00

8

Amount payable for expenditures incurred for cutting trees, dismantling Goomty adjacent to Signal Cabin & making table at the Signal Cabin. (Details, Vide, ANNEXU

    Click Here to Read the rest of this document
    1
    2
    3
    4
    5
    6
    7
    8
    9
    10
    11
    SupremeToday Portrait Ad
    supreme today icon
    logo-black

    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

    Please visit our Training & Support
    Center or Contact Us for assistance

    qr

    Scan Me!

    India’s Legal research and Law Firm App, Download now!

    For Daily Legal Updates, Join us on :

    whatsapp-icon Back to top