SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Cal) 1230

IN THE HIGH COURT AT CALCUTTA
KRISHNA RAO, J.
State of West Bengal – Petitioners
Versus
PAM Developments Private Limited – Respondent
AP-COM No. 102 of 2024 (Old No. AP 579 of 2008)
Decided On : 14-06-2024

Advocates:
Advocate Appeared:
For the Petitioners: Noelle Banerjee, Paritosh Sinha, Arindam Mandal, Shourya Samanta.
For the Respondents: Suman Dutt, Aniruddha Mitra, Monica Jaiswal, Madan Mohan Roy.

An arbitrator's award may be upheld if it conforms to contract terms, despite challenges regarding procedural compliance or interpretation, provided it does not contravene public policy.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to arbitration award for allegedly exceeding terms of contract - The petitioner's claims include: lack of assigned reasons by the arbitrator, violation of the Indian Contract Act's provisions, and considerations outside the contract's scope. (Paras 13, 51, 52, 53)

(B) Contract Law - When invoking escalation clauses, the arbitrator's discretion must align with agreement terms - Award must not contravene public policy or be arbitrary - Delay caused may affect the applicability of no-damage clauses. (Paras 41, 43, 48)

Facts of the case:
The State of West Bengal challenged an arbitration award wherein several claims by the contractor were allowed, despite the contractor having not completed the work within the agreed timeline.

Issues: The extent of the arbitrator's authority concerning contract terms and claims for damages due to delay.

Findings of Court:
The arbitrator was deemed to have acted within contractual bounds despite procedural concerns raised by the petitioner.

Ratio Decidendi: The court found no grounds for setting aside the arbitrator's award, affirming that the arbitrator adhered to the contractual terms while determining claims.

Result: Application dismissed.

Table of Content
1. background of contract and amendments (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9)
2. claims submitted to the arbitrator (Para 10 , 11)
3. arbitrator's observations on hinderances (Para 12 , 36 , 37)
4. grounds of challenge to the award (Para 13 , 14 , 15 , 16 , 18 , 19 , 21 , 22)
5. defense counterarguments from the respondent (Para 28 , 30 , 31)
6. legal standards for arbitration awards (Para 42 , 43 , 44 , 45)
7. conclusion and court order (Para 48 , 49)

JUDGMENT :

KRISHNA RAO, J.

1. The petitioner, State of West Bengal has filed the present application under Section 34 of the Arbitration and Conciliation Act, 1996, challenging the award passed by the Learned Sole Arbitrator dated 21st August, 2008.

2. The State of West Bengal, through its Superintending Engineer, State Highway Circle No. 1, P.W (Roads) Department issued Notice inviting Tender for the work “Construction of Reinforcement Concrete Viaduct Structures with bored piles foundation and the retaining wall on the eastern side of the proposed road over bridge over the Howrah-Bandel Railway line of the Eastern Railway on replacement of the existing level crossing No. 1/1A at Liluah Howrah under the Howrah Highway Division.”

3. The estimated value of the tender was for Rs.1,97,00,000/- and pursuant to the said tender, the respondent by a letter dated 30th September, 1997, submitted its offer in Parts “A” and “B” with certain conditions. The conditions were not acceptable to the petitioner and accordingly, the respondent by its letter dated 28th October, 1997, withdrew the conditions contained in Part “A” of the letter by reserving its right to go for arbitration in case of any disputes and submitted revised offer at 4.80% above the rate put to the tender and enclosed the bar chart showing the tentative programme for executing the tender work.

4. The Superintending Engineer by a letter dated 3rd December, 1997, had accepted the revised offer of the respondent for a sum of Rs.1,93,46,553/- . As per the letter dated 3rd December, 1997, the time for completion of work was 24 months and the same will be counted on and from 23rd December, 1997.

5. As per Clause 2 of the conditions of contract, the contractor is bound to execute 1/4th of the total work in 1/4th time, 1/2 of the work in ½ of the time, 3/4th of the work before 3/4th of the time and the total work within the total stipulated time and in the event, the contractor failed to execute the work in terms of the General Conditions of Contract, the Superintending Engineer concerned shall penalize the contractor for the remaining work still to be completed during the contract period to the extent of 1% or such smaller amount as he thinks fit.

6. Clause 5 of the contract provides for extension of time by or on behalf of the Superintending Engineer in favour of the respondent for completion of the works of the said contract.

7. As per Clause 12, the Executive Engineer shall have the power to make any alterations, omissions, additions or substitutions of the original specifications, drawings, designs and instructions that may appear to him to be necessary or advisable during the progress of the work and the contractor shall be bound to carry out the work in accordance with any instructions which may be given to the contractor in writing and such alterations shall not invalidate the contract but shall deemed to have been formed as work included in the original tender.

8. As per the request of the respondent, the Executive Engineer has extended the time to complete the work by communications dated 30th December, 1999, 28th June, 2000, 29th December, 2000, 22nd June, 2001 and on 14th September, 2001. On 28th December, 2001, the Executive Engineer of his own and without the request of the respondent had extended the time till 31st March, 2002 for completion of the work by the respondent. On 26th March, 2002, the respondent has again requested for extension of time and by a letter dated 27th March, 2002, time to complete the work

    Click Here to Read the rest of this document
    1
    2
    3
    4
    5
    6
    7
    8
    9
    10
    11
    SupremeToday Portrait Ad
    supreme today icon
    logo-black

    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

    Please visit our Training & Support
    Center or Contact Us for assistance

    qr

    Scan Me!

    India’s Legal research and Law Firm App, Download now!

    For Daily Legal Updates, Join us on :

    whatsapp-icon Back to top