IN THE HIGH COURT AT CALCUTTA
MOUSHUMI BHATTACHARYA, J.
Rolta Infrastructure and Technology Services Private Limited – Petitioner
Versus
Department of Information Technology and Electronics, Government of West Bengal – Respondent
AP 827 of 2023
Decided On : 05-01-2024
Arbitration - Stay of Termination Notice - The Arbitration and Conciliation Act, 1996 - Section 9
Fact of the Case:
The petitioner sought stay of a notice revoking a sub-lease agreement for 5 acres of land granted for an IT/ITeS Project. The respondent alleged non-performance of contractual obligations, while the petitioner alleged failure to provide essential services. The respondent initiated eviction proceedings, and the petitioner invoked the arbitration clause in the sub-lease agreement.
Finding of the Court:
The Court found that the dispute fell within the scope of the arbitration clause and granted stay of the termination notice to preserve the subject matter of arbitration until the arbitral tribunal is constituted.
Issues: The issues involved the validity of the termination notice, jurisdiction, non-arbitrability under The West Bengal Public Land (Eviction of Unauthorised Occupants) Act, 1962, and the applicability of interim relief under section 9 of The Arbitration and Conciliation Act, 1996.
Ratio Decidendi: The Court held that the dispute was arbitrable, the arbitration clause covered the termination of the sub-lease agreement, and the Court had jurisdiction to grant interim relief to preserve the subject matter of arbitration.
Final Decision: The application for stay of the termination notice was allowed, and the interim order of stay was to continue for 6 weeks or until appropriate orders were passed by the arbitral tribunal.
JUDGMENT :
Moushumi Bhattacharya, J.
1. The petitioner seeks stay of a notice dated 20th September, 2023 by way of the present application filed under section 9 of The Arbitration and Conciliation Act, 1996. The impugned notice was sent by the respondent revoking a Deed of Sub-Lease dated 4th July, 2008 by which the respondent granted 5 acres of land to the petitioner for 99 years.
2. The admitted facts brought to the notice of the Court are as follows.
3. The respondent granted the sub-lease of the land to the petitioner for construction of an IT/ITeS Project. The petitioner alleges that the respondent failed to provide power, water and sewage outlet by reason of which the petitioner was unable to complete the construction within the agreed time frame. The respondent, on the other hand, alleges that the petitioner failed to perform its contractual obligations. The respondent terminated the sub-lease on 20th September, 2023. The petitioner objected to the notice of termination by a letter dated 16th October, 2023. The respondent filed an application under the provisions of The West Bengal Public Land (Eviction of Unauthorised Occupants) Act, 1962 for evicting the petitioner from the leasehold land and the Collector also issued a show-cause notice to the petitioner. The petitioner appeared before the First Land Acquisition Collector, Kolkata, objecting to the jurisdiction by filing the response in the proceedings. The petitioner issued a notice on 8th November, 2023 invoking the arbitration clause contained in clause 5 of the sub-lease agreement.
4. Learned counsel appearing for the petitioner places clause 5 of the sub-lease agreement to urge that the dispute between the parties culminating in the impugned termination notice of 20th September, 2023 is covered by the arbitration clause in the agreement. Counsel submits that the termination is invalid and contrary to the sub-lease agreement and that the arbitrator should decide on the validity of the termination. Counsel submits that unless the letter of termination is stayed, the rights of the petitioner will irrefutably be prejudiced.
5. Learned counsel appearing for the respondent submits that the application should be rejected for want of territorial jurisdiction and that the application is akin to a suit for land. It is also submitted that the subject-matter of the present application is non-arbitrable since the West Bengal Public Land (Eviction of Unauthorised Occupants) Act, 1962 is a special statute for providing a speedy route to the Government for eviction of unauthorized occupants and also has overriding effect over The Arbitration and Conciliation Act, 1996. Counsel relies on sections 20A and 41(ha) of the Specific Relief Act, 1963 to urge that injunction cannot be granted in respect of infrastructure projects. Counsel submits on the factual aspect that the petitioner illegally mortgaged the lease-hold interest in the land consequent to which the concerned Bank invoked the SARFAESI Act. It is submitted that relief in the nature of injunction cannot be sought for where there has been a breach of contractual obligations.
6. The objection to jurisdiction should be decided first.
7. The present dispute is not a suit for land since the petitioner is not seeking injunction in respect of an immovable property or inviting the Court to decide any question of title or possession of the land. The petitioner merely seeks interim protection over the subject-matter of the arbitration agreement in view of clause 5 of the said agreement which covers disputes and differences between the parties in respect of the sub-lease agreement dated 4th July, 2008. There is a vital difference between an application for interim protection under section 9 of The Arbitration and Conciliation Act, 1996 and a suit for land where the essential question is to determine the title and possession of the land in question: Ref: P. Ranganathan v. Sai Jagannathan; 1995 (II) CTC 181. Moreover, the sub-lease ag
A.B.C. Laminart Pvt. Ltd. v. A.P. Agencies, Salem
The Court affirmed the power of the Court under section 9 of The Arbitration and Conciliation Act, 1996 to grant interim measures for preservation of the subject matter of arbitration, and clarified ....
Immediate intention to refer the dispute to arbitration is a prerequisite for granting interim relief under Section 9 of the Arbitration and Conciliation Act.
Disputes between landlords and tenants governed by rent control legislation are non-arbitrable and must be addressed exclusively by statutory authorities.
The relief sought under Section 9 of the Arbitration Act must be in the nature of interim measures to protect the subject matter of the arbitration and cannot extend to permanent injunctions.
The main legal point established in the judgment is that disputes governed by the Transfer of Property Act are arbitrable, while those governed by rent control legislation are non-arbitrable and can ....
Interim injunction – Jurisdiction under Section 9 of Arbitration and Conciliation Act, 1996, is not an adjudicatory substitute for final determination of rights, but a supportive mechanism to facilit....
The collateral efficacy of an unregistered lease deed and the jurisdiction of the Commercial Court under Section 9 of the Act, 1996, as per the terms of the sub-lease agreement.
The determination of the Lease Agreement's nature and the establishment of a prima facie case for restraining the respondent from acting on the Termination Notice were central legal points in the jud....
The court reaffirmed that the existence of an arbitration agreement is sufficient for appointing an arbitrator, emphasizing minimal judicial interference in arbitration processes.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.