SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Cal) 290

IN THE HIGH COURT AT CALCUTTA
I.P. MUKERJI, BISWAROOP CHOWDHURY, JJ.
MFAR Constructions Private Limited – Appellant
Versus
Bengal Shristi Infrastructure Development Limited – Respondent
FMAT (ARBAWARD) No. 30 of 2022
Decided On : 19-04-2024

Advocates:
Advocate Appeared:
For the Appellants : Soumabho Ghosh, T. Bhattacharya, Anujit Mookherji, Prithish Chandra.
For the Respondents: Hasnuhana Chakraborti, Aasia Hasan, Pathik Chowdhury.

IMPORTANT POINT
The main legal point established in the judgment is the distinction between conciliation and settlement efforts made by the arbitrator, emphasizing the encouragement of settlement efforts during arbitration and civil suits, and the interpretation of the provisions of the Arbitration and Conciliation Act, 1996.

Headnote:

Conciliation - Arbitration - Arbitration and Conciliation Act, 1996, Section 80, Section 30, Section 89, Order 23 Rule 3 - The court discussed the provisions of Section 80, Section 30, Section 89, and Order 23 Rule 3 of the Arbitration and Conciliation Act, 1996, and the Civil Procedure Code. It highlighted the distinction between conciliation and settlement efforts made by the arbitrator, emphasizing the encouragement of settlement efforts during arbitration and civil suits.

Fact of the Case:

The court set aside an arbitral award on the ground that the arbitrator had participated in a conciliation exercise between the parties, leading to the conclusion that the award was against the law and public policy.

Finding of the Court:

The court found that the arbitrator's efforts to encourage settlement were more akin to the attempts made by a judge in court to facilitate a settlement, rather than a formal conciliation proceeding under the Arbitration and Conciliation Act, 1996.

Issues: The key issue was whether the arbitrator's involvement in settlement efforts constituted a violation of the law and public policy, leading to the setting aside of the arbitral award.

Ratio Decidendi: The court emphasized the distinction between conciliation and settlement efforts made by the arbitrator, highlighting the encouragement of settlement efforts during arbitration and civil suits, and concluded that the arbitrator's actions did not warrant setting aside the arbitral award.

Final Decision: The impugned judgment and order setting aside the arbitral award was set aside, and the matter was remanded to the court below for re-determination of the Section 34 application strictly on merits. The appeal was allowed.

JUDGMENT :

I.P. MUKERJI, J.

1. A point of some importance is involved in this appeal. By his judgment and order dated 20th April, 2022 the learned judge, Commercial Court at Alipore set aside the arbitral award dated 29th December, 2017 on the solitary ground that the learned arbitrator had taken part in a conciliation exercise between the parties. The merits of the matter were not gone into by the learned judge.

2. The arbitrator was the Hon’ble Mr. Justice Amitava Lala, a former judge of this court and of the Allahabad High Court. The award was for a sum of Rs. 1,54,86,728/- together with interest at the rate of 18% per annum from the date of the award till the date of payment. The counterclaim made by the respondent was rejected. There is no dispute that the learned arbitrator had made an endeavour to enable the parties to arrive at a settlement.

3. The effort which the learned arbitrator made towards settlement is recorded in the following words in the award:

    “Settlement by Conciliation:

On 6th June 2017 as and when drawing of Award was for delivery excepting completion of formalities, respondent's representative Mr. Sunil Jha and Mr. Badri Kumar Tulsyan, working in a sister concern of the respondent approached the Arbitrator to get the disputes settled amongst the parties by way of conciliation when the representative of the claimant Mr. P.K. Rao, upon being present, wanted to obtain specific proposal of terms of settlement from the respondent and 3 to 4 months time to get final approval from the Board of Directors of the claimant company, who works or lives in different places. Accordingly the Arbitrator thought that no chance of settlement should be ignor ignored at any stage but to give appropriate opportunities to the parties. Thus by consent of the parties, the time was allowed by holding 61 sitting on 6th June 2017.

After expiry of considerable period, again by a letter dated 17th November 2017 with a copy to the claimant, the representative of the respondent approached the Arbitrator to hold a sitting for further discussion about settlement. Accordingly upon notice to the parties, the Arbitrator held 62nd sitting on 30th November 2017 when representatives of both the parties, upon being present, made their respective submissions. Mr. P.K. Rao was present on behalf of the claimant when Mr. Sunil Jha, Mr. Badri Kumar Tulsyan and Mr. Ashish Jha were present on behalf of the respondent. The main contention on the part of the respondent was that they are not supposed to pay the retention money when the work was foreclosed. For the payment of bill amount under claim no. 1, the respondent prayed time to pay by installments. As against the quarry of Mr. P.K. Rao, the representative of the claimant, for payment of interest, Mr. Sunil Jha, the representative of the respondent, flatly refused to pay any interest. It is significant to note there under that the approach of Mr. Sunil Jha was contrary to basic element of conciliation. On the other hand, the approach of Mr. Badri Kumar Tulsyan was quite cordial and genuine. Approach of Mr. Ashish Jha was similar to Mr. Tulsyan. Apparently Mr. P.K. Rao, the representative of the claimant, seemed to be unhappy with the approach of Mr. Sunil Jha. Mr. Tulsyan wanted to control the damage but it became uncontrollable by such time.

In any event, I approached Mr. P.K. Rao, representative of the claimant, to take time and think rationally thereafter come back on a date to be fixed by the Arbitrator.

However, on 8th December 2017 the claimant wrote a letter to the Arbitrator with a copy to the respondent saying that the management of the claimant has duly considered the offer made by the respondent and hereby expresses its inability to accept such offer for settlement. Thus the Arbitrator cannot compel them to accept the proposal made by the respondent.

Hence, the settlement by way of conciliation in terms of Section 30 of the Arbitration and Conciliation Act, 1996 stands failed. The minutes of 61st

          Click Here to Read the rest of this document
          1
          2
          3
          4
          5
          6
          7
          8
          9
          10
          11
          SupremeToday Portrait Ad
          supreme today icon
          logo-black

          An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

          Please visit our Training & Support
          Center or Contact Us for assistance

          qr

          Scan Me!

          India’s Legal research and Law Firm App, Download now!

          For Daily Legal Updates, Join us on :

          whatsapp-icon Back to top