IN THE HIGH COURT AT CALCUTTA
SHAMPA SARKAR, J.
TIL Limited - Petitioner
Versus
Shapoorji Pallonji & Co. Private Limited - Opposite Party
C.O. No. 2080 of 2023
Decided On : 28-08-2023
Recall Application - Execution of Arbitral Award - Arbitration and Conciliation Act, 1996 - Section 34, Section 36 - Code of Civil Procedure, 1908 - Order VI Rule 15A - Section 42 - Associated Contractors (2015) 1 SCC 32, Sundaram Finance Limited (2018) 3 SCC 622 - Commercial Court's Jurisdiction - Verification of Pleadings
Fact of the Case:
The court rejected an application for recalling an order related to the execution of an arbitral award. The award holder sought directions for the judgment debtor to furnish security or deposit the entire amount in a fixed deposit. The court directed the award debtor to secure the entire amount with a renewable bank guarantee. The award debtor filed a recalling application, which was dismissed by the court.
Finding of the Court:
The court found that the execution of the arbitral award required the award holder to be secured, and the recalling application did not meet the criteria for recall as per legal precedents. The court also held that the verification defect in the application did not affect the maintainability of the execution case.
Issues: The issues included the jurisdiction of the commercial court, the applicability of Section 42 of the Arbitration and Conciliation Act, 1996, and the verification of pleadings under Order VI Rule 15A of the Code of Civil Procedure.
Ratio Decidendi: The court relied on legal precedents to determine the requirements for recalling an order and the jurisdiction of the commercial court in executing arbitral awards. It also considered the applicability of Section 42 of the Arbitration and Conciliation Act, 1996, and the interpretation of verification of pleadings under Order VI Rule 15A.
Final Decision: The revisional application was dismissed, and the court allowed the petitioner to raise all points available at the time of hearing, except the question of the applicability of Section 42 of the Arbitration and Conciliation Act, which was decided in the judgment. The court's observations were not to influence the lower court's decision in the execution case.
JUDGMENT :
1. The revisional application arises out of an order dated June 13, 2023 passed by the learned Judge, Commercial Court at Alipore in Arbitration Execution Case No.03 of 2022. By the order impugned, the learned court rejected I.A. No.02 of 2023, which was an application for recalling of an order dated April 5, 2023 passed in I.A. No.01 of 2022.
2. I.A. No.01 of 2022 was filed by the award holder with prayers for directions upon the judgment debtor to furnish security to the extent of Rs.3,19,30,564/- or in the alternative to deposit the entire amount in a short term interest bearing fixed deposit till the execution was satisfied. Such application was disposed of on April 5, 2023, by the learned Commercial Judge directing the award debtor to secure the entire amount within four weeks from the date of the order in the form of a renewable bank guarantee in favour of the petitioner/award holder, to be deposited with the learned Registrar, Alipore, till further orders.
3. The learned Commercial Judge considered the allegations made by the award holder that the award debtor was trying to surreptitiously withdraw the money lying in the bank account and was also selling out valuable assets.
4. Relying on the decisions of the Hon’ble Apex Court in the matter of Pam Development Pvt. Ltd. Versus State of West Bengal reported in (2019) 8 SCC 112, Satyen Construction Versus State of West Bengal reported in 2020 SCC OnLine Cal 805 and Siliguri Jalpaiguiri Development Authority Versus Bengal Unitech Universal Siliguri Projects Limited reported in 2022 SCC OnLine Cal 1754, the learned court held that the law mandated that for the execution proceeding to remain stayed, the money awarded would have to be secured. While the rights of the award holder were not crystallised till the disposal of the application under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘said Act’), the award holder had the statutory safeguard under Section 36 of the said Act to be secured in a fruitful manner, for the entirety of the arbitral award.
5. Relying on the decisions of the Hon’ble Apex Court, the learned Commercial Judge held that the award holder should be secured for the amount awarded by the learned Arbitral Tribunal along with interest amounting to Rs.3,19,30564/-, and directed that renewable bank guarantee of the entire amount in favour of the award holder be deposited with the learned Registrar, Alipore, till further orders.
6. The award debtor filed an application for recalling of the said order on the following grounds:-
“(i) The Award Holder should not be permitted to rely on the application filed by them since the verification of the application filed by the Award Holder was not in the manner as per the Order VI Rule 15A of Code of Civil Procedure, 1908, as amended, by the Commercial Court Act, 2016. It was submitted that the effect of not verifying a pleading in the manner provided in order VI Rule 15A of Code of Civil Procedure, 1908, as amended, particularly sub-rule (4) thereof, is that a party shall not be permitted to rely on such pleading.
(ii) The application filed by the Award Holder cannot be entertained since this Ld. Commercial Court cannot entertain the execution application.”
7. The said recalling application was dismissed on the ground that except under situations enumerated by the Hon’ble Apex Court in several decisions, a court could not recall its own order. The Commercial Judge did not recall the order dated April 5, 2023.
8. According to the learned Judge, the tests were laid down in the decision of Budhia Swain and Others versus Gopinath Deb and Others reported in (1994) 4 SCC 396 and the decision of Indian Bank Versus M/s. Satyam Fibres India Pvt. Ltd. reported in 1996 (5) SCC 550. Unless the award was obtained by fraud, misrepresentation or the court committed an apparent error, the power of recall could not be exercised. Referring to the decision of A.R. Antulay Versus R.S. Nayak & Anr
Pam Development Pvt. Ltd. Versus State of West Bengal
Indian Bank Versus M/s. Satyam Fibres India Pvt. Ltd.
A.R. Antulay Versus R.S. Nayak & Anr.
State of West Bengal and Others Versus Associated Contractors
Sundaram Finance Limited Versus Abdul Samad and Another
Harji Engineering Works Pvt. Ltd. Versus Hindustal Steelworks Construction Ltd.
AI
The court emphasized the need for securing the arbitral award and clarified the criteria for recalling an order. It also provided interpretations of the jurisdictional issues and the verification of ....
The execution application for an arbitral award is valid in the court of initial recognition, irrespective of concurrent challenges in other jurisdictions.
Execution of arbitral awards must occur in the court where the original arbitration application was filed, as per Section 42 of the Arbitration and Conciliation Act.
The main legal point established is that the Commercial Court has jurisdiction to entertain execution proceedings arising from an award under the Arbitration and Conciliation Act, and the award holde....
The doctrine of res judicata bars re-litigation of issues, ensuring judicial efficiency by preventing repetitive and vexatious claims, particularly in arbitrational contexts.
The court held that under the Arbitration and Conciliation Act, only the court that entertained the initial arbitration application has jurisdiction to enforce the award, reinforcing exclusive enforc....
The enforcement of an arbitral award can be initiated anywhere in the country where the decree can be executed, without requiring a transfer of decree from the court with jurisdiction over the arbitr....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.