IN THE HIGH COURT AT CALCUTTA, CIRCUIT BENCH AT PORT BLAIR
Harish Tandon, Rai Chattopadhayay, JJ.
The Union Of India Through The Deputy Chief Engineer, Alhw, Port Blair - Appellant
Vs.
M/s Srishaila Construction Private Limited - Respondent
Fmat(Arbaward) No. 1 of 2023
Decided On : 26-09-2023
Arbitration and Conciliation Act - Interpretation of Contract - Section 37
Fact of the Case:
The appellant raised a seminal point on the scope of Section 37 of the Arbitration and Conciliation Act, 1996 in relation to an interpretation of a contract entered into between the parties. The dispute arose from the development of the Baratang Jetty based on a detailed project report and subsequent claims and counterclaims between the parties.
Finding of the Court:
The majority view of the Arbitral Tribunal held that the agreement dated 10th March, 2016 is a concession agreement and awarded various claims to the respondent. The section 34 Court found that the Tribunal's interpretation of the agreement as a concession agreement did not invite interference under section 34 of the Act.
Issues: The seminal point involved in the instant appeal is whether the majority view of the Arbitral Tribunal needs interference on the ground enumerated under section 34 of the said Act.
Ratio Decidendi: The Court held that the scope of interference with the Arbitral award is within the limited compass of the grounds enumerated under section 34 of the Act. The interpretation of a contract is within the scope and jurisdiction of the Arbitral Tribunal, and the interference is only warranted when the Tribunal has traveled beyond the terms of the contract or the interpretation shocks the conscience of the Court.
Final Decision: The appeal failed, and no order as to costs was made.
JUDGMENT :
Harish Tandon, J.
1. The appellant raises a seminal point on the scope of Section 37 of the Arbitration and Conciliation Act, 1996 in relation to an interpretation of a contract entered into between the parties.
2. A prelude to the dispute between the parties are succinctly jotted down in order to the determine the question raised in the instant appeal more particularly the nature of a contract. Indubitably, the appellant took a conscious decision to develop the Baratang Jetty and a detailed project report was prepared containing various components viz., dredging of sea bed in the channel at the mouth of Middle Strait Creek, Construction of 12 nos. Navigational Aids founded on RCC bored case in the situ piles, Construction of RCC Jetty on pile foundation connecting the shore with RCC piled approach, etc.
3. Pursuant to the Detailed Project Report (DPR) a Notice Inviting Tender was published and advertised together with a Request For Qualification (RFQ) on 3rd December, 2014 for the aforesaid purposes. The intending purchasers were further directed to submit their bid in accordance with Request for Proposal (RPF) and Draft Concessional Agreement in format attached thereto. The respondent submitted the bid as contained in the Notice Inviting Tender in the requisite format and was found the lowest bidder and a Letter of Acceptance was issued on 31st January, 2016 followed with an agreement signed by the parties on 10th March, 2016.
4. It is also not in dispute that the project was completed but the respondent claimed right under the concession agreement, which was denied by the appellant treating such agreement under the EPC project which raises a dispute to be resolved through the Arbitral Tribunal. For the purpose of record, prior to taking recourse to determination of dispute through an Arbitral Tribunal, the parties have to pass through the Dispute Resolution Mechanism which in fact was exhausted and ultimately, the Arbitral Tribunal was constituted consisting of three members in terms of the arbitration clause.
5. The claims are jotted down as under:-
Claim No.1A: To direct the respondent to pay a sum of Rs.10,68,62,175/- towards difference in cost of project and grant provided.
Claim No.2: Claim towards compensation for the loss of revenue from the date of completion to the date of handing over of the site.
Claim No.3: Claim towards additional expenses incurred due to re-design in live load from 1T per Sq.Mt to 2T per Sq.mt.
Claim No.4: Claim towards interest on delay in release of Security Deposit collected against contract conditions.
Claim No.5: Claim towards damage to Pile by DSS vehicle ferry.
Claim No.6: Claim towards service tax and GST unpaid.
Claim No.7: Claim towards interest for the claims upto pre-reference period i.e., from 20.2.2018 to 15.2.2019.
Claim No.8: Claim towards interest for the period pending litigation and post award till realization of amount.
6. The appellant made counter claims in the following:
(a) Arbitrator hearing
(b) Cost of Learned Counsel
(c) Travelling charges of the Department Officials, Counsel, Venue charges etc.
(d) Manpower (4 Officers, 2 Clerks, Cost of Typing, Stationery, Photostat, Binding)
Claim No.2: Interest on cost of materials issued to the claimant (R153).
Claim No.3: Payment made to the claimant due to oversight.
Claim No.4: Extra amount paid to the claimant due to change of depth of fascia beam and top level of jetty at approach.
7. Out of three members constituting the Arbitral Tribunal, two of its member jointly published the award whereas the third Arbitrator dissented with the view taken by the majority. The majority view of Arbitral Tribunal would reveal that the counter claim filed by the appellant was rejected in toto whe
MMTC Ltd vs. M/s Vedanta Limited reported in (2019) 4 SCC 163
Associate Builders vs. Delhi Development Authority reported in (2015) 3 SCC 49
The interpretation of a contract is within the scope and jurisdiction of the Arbitral Tribunal, and the interference is only warranted when the Tribunal has traveled beyond the terms of the contract ....
The court reaffirmed the limited scope of review for arbitral awards under Section 34 of the Arbitration Act, focusing on patent illegality and contractual obligations as defined within the signed ag....
The judgment emphasizes the limited scope of interference with arbitral awards and the principle that courts should not interfere with arbitral awards unless there is a patent illegality or violation....
The court emphasized that judicial interference with arbitral awards is strictly limited, focusing only on issues of public policy or jurisdictional errors and cannot re-evaluate the merits of the aw....
The court confirmed that judicial interference in arbitral awards is limited to cases of patent illegality or perverse findings, respecting the finality of arbitration.
The court reaffirmed the limited scope of judicial review of arbitral awards under Sections 34 and 37 of the Arbitration and Conciliation Act, emphasizing that courts cannot reappraise evidence or in....
Appeal against arbitral award – Scope of jurisdiction under Section 34 and Section 37 of Act is not akin to normal appellate jurisdiction – Mere possibility of an alternative view on facts or interpr....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.