IN THE HIGH COURT AT CALCUTTA
SUVRA GHOSH, J.
Jagran Prakashan Limited and Another – Appellants
Versus
State of West Bengal and Others – Respondents
W.P.A. No. 10632 of 2018
Decided On : 09-09-2025
| Table of Content |
|---|
| 1. details of petitioners' claims and facts. (Para 1 , 2) |
| 2. arguments regarding construction delays and penalties. (Para 3 , 4) |
| 3. counterarguments from kmda about contractual obligations. (Para 5 , 6) |
| 4. court's consideration and dismissal of claim. (Para 8 , 9 , 23) |
| 5. contractual terms interpretation and implications. (Para 10 , 12) |
| 6. policy decisions and implications on contract enforcement. (Para 14 , 15 , 16) |
| 7. final conclusion of the court on the petition. (Para 22 , 24 , 25) |
JUDGMENT :
SUVRA GHOSH, J.
1. The petitioners have prayed for issuance of writ of certiorari quashing/setting aside the penal charges and interest imposed by the respondents/KMDA for delay in construction and delay in payment of penal charges. The petitioners have also sought a direction upon the respondents to refund the amount deposited by them on protest.
2. The factual matrix of the case is as hereunder:-
The first petitioner applied before the KMDA for lease of a plot of land for expanding the printing infrastructure of his company in West Bengal. Since process of acquisition of the land comprising the property was not completed by the State of West Bengal, the KMDA was not in a position to grant lease of the land and agreed to grant permissive possession of 30.037 cottahs in plot no. I-V/III/Zone-1 of the EKADP in anticipation of grant of future lease of the said land. Possession certificate was issued in favour of the petitioners on November 8, 2006 and deed of license was executed by the KMDA in favour of the first petitioner on August 21, 2007. The first petitioner applied for mutation of the plot on August 22, 2008 and mutation certificate was issued in his favour on November 17, 2008 recording his name as the licensee and the KMDA as the licensor. On November 22, 2009 the first petitioner informed the respondents about taking necessary steps for the purpose of applying for sanction of building plan. The first petitioner sought extension of the period of commencement of work till December, 2010 which was allowed by the KMDA on June 23, 2010 subject to payment of penal charges @ 10% of the then land value. Since sanctioned plan was not granted to the petitioners on the ground that they were mere licensees, the petitioners informed the same to the KMDA and requested them to advise the KMC to sanction building plan in favour of the petitioners. The building plan was sanctioned by the KMC on November 27, 2010 and the petitioners commenced construction on December 31, 2010 upon serving notice of commencement of work upon the KMC. The petitioners were directed to deposit a sum of Rs. 63,11,473/- as penal charges for delayed construction alongwith a sum of Rs. 38,17,790/- as penal interest for delay in payment of the penal charges. The petitioners’ request for waiver of such charges was turned down by the respondents for which the petitioners were compelled to deposit such charges on protest. The deed of lease was executed by the KMDA in favour of the first petitioner on May 3, 2016.
3. Learned counsel for the petitioners has submitted that though clause-4 (iii) of the deed of license stipulated that the licensee would start construction within two years from the date of execution of the deed, such construction could not have been commenced without obtaining the sanctioned plan. The delay in obtaining the sanctioned plan cannot be attributed to the petitioners. The petitioners were refused sanction since they were mere licensees and they had to request the respondents to take up the issue with the KMC. The respondents wrote to the KMC only on July 14, 2010 after which the building plan was sanctioned on November 27, 2010. The petitioners commenced construction soon thereafter. The petitioners’ request for extension of time to complete the construction was granted and despite their being no provision in the license deed for levy of penalty by the respondents, they levied penal charges on the petitioners and also withheld execution and regi
Imposing penal charges for contract breaches is valid when stipulated policies and terms align with contractual obligations, and acceptance of penalties post-acceptance negates protest claims.
Supplementary lease deeming additional built-up area integral with no time limit overrides original four-year completion clause for composite construction; penalty demands arbitrary, illegal; payment....
Lease penalty for construction delay invalid where lessor nondiscloses material site defects, supplementary deed removes time limit for additional built-up area, delays due to approvals/statutory fac....
Additional premium demand for construction delay under lease held arbitrary where caused by statutory approvals, late commencement certificates, and extra built-up area without timeline; applicable s....
The court affirmed the cancellation of the license deed due to the appellant's failure to comply with the stipulated conditions of the agreement.
Penalty for construction delay under lease quashed due to delays from court stay, statutory approvals, additional area; writ maintainable for arbitrary state action; 6-year extension non-discriminato....
A mandamus issued by the court creates vested rights that restrict the imposition of additional charges for planning permission if initial conditions were met according to earlier mandates.
The termination of a commercial license is justified if the licensee fails to adhere to stipulated contractual obligations, as it undermines public interest and lawfulness under the contract terms.
Unilateral retrospective enhancement of lease rent by an authority, without executing a supplementary deed, is illegal, and higher authority’s orders must be implemented by lower bodies.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.