IN THE HIGH COURT OF JUDICATURE AT BOMBAY
SHREE CHANDRASHEKHAR, CJ., SUMAN SHYAM, J.
Reliance Industries Limited – Appellant
Versus
Mumbai Metropolitan Region Development Authority (MMRDA) – Respondent
Writ Petition No. 242 of 2018 With Interim Application No. 2172 of 2020
Decided On : 08-04-2026
| Table of Content |
|---|
| 1. petition challenges mmrda delay penalty demand. (Para 1 , 2 , 3 , 4) |
| 2. lease mandates construction within four years. (Para 5 , 6) |
| 3. additional fsi allotment stayed by court. (Para 7 , 8 , 9 , 10) |
| 4. court stay delays composite construction commencement. (Para 11 , 12 , 13 , 14) |
| 5. further fsi increases require revised approvals. (Para 15 , 16 , 17 , 18) |
| 6. mmrda demands penalty despite extension resolutions. (Para 19 , 20 , 21 , 22 , 23) |
| 7. payments made under protest amid court stays. (Para 24 , 25 , 26 , 27) |
| 8. parties dispute contract breach and discrimination. (Para 28 , 29 , 30) |
| 9. petitioners argue delays from approvals, stays. (Para 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39) |
| 10. respondents defend mandatory penalty clauses. (Para 40 , 41 , 42 , 43 , 44 , 45) |
| 11. writ maintainable against arbitrary state action. (Para 46 , 47 , 48 , 49 , 50 , 51 , 52 , 53 , 54 , 55) |
| 12. prior judgment supports writ jurisdiction. (Para 56 , 57 , 58 , 59 , 60 , 61 , 62) |
| 13. lease clauses unfair absent approval timelines. (Para 63 , 64 , 65 , 66 , 67) |
| 14. composite project timeline from effective cc. (Para 68 , 69 , 70 , 71 , 72 , 73) |
| 15. promissory estoppel excludes stay periods. (Para 74 , 75 , 76 , 77) |
| 16. no delay attributable to lessee. (Para 78 , 79 , 80 , 81) |
| 17. penalty recovery violates natural justice. (Para 82 , 83 , 84 , 85 , 86) |
| 18. coerced payments refundable under duress. (Para 87 , 88 , 89 , 91 , 92 , 93) |
| 19. precedents distinguished; prior ruling applicable. (Para 94 , 95 , 96) |
| 20. six-year extension applies to prior leases. (Para 97 , 98 , 99 , 100 , 101) |
| 21. demands quashed; penalty refunded with interest. (Para 102 , 103 , 104 , 105 , 106 , 107 , 108) |
Judgment :
Suman Shyam, J.
1. Rule. Rule is made returnable forthwith.
2. By consent of the parties, the matter is taken up for final hearing.
3. Assailing the demand-cum-show cause notice dated 12th September 2017 (Exhibit “R”), whereby, the Respondent No.1– Mumbai Metropolitan Region Development Authority (“MMRDA”) had demanded additional premium/penalty as per statements ‘A’ and ‘B’ annexed thereto, for the alleged delay of 7 years and 12 days in completion of construction of a Convention & Exhibition Centre and Commercial Complex on Plot No. C-64, ‘G’ Block, Bandra-Kurla Complex, Mumbai, the Petitioners have approached this Court by filing this Writ Petition invoking the jurisdiction of this Court under Article 226 of the Constitution of India. During the pendency of the Writ Petition, by the communication dated 13th June 2019 (Exhibit “X”) a further amount of Rs.1116,83,10,102/- was demanded from the Petitioner No. 1 as additional premium, along with interest, towards extension of time for completing the construction of the building by using the additional built up area of 72,500 sq mtrs. allotted under the Supplementary Lease Deed dated 13th July 2007. The said Notice is also under challenge in this Writ Petition. The facts and circumstances giving rise to the filing of the present Writ Petition, shorn of unnecessary details, are as hereunder.
4. The Petitioner No.1 is a company incorporated under the provisions of the Companies Act, 1956. As per statements made in the Writ Petition it is engaged inter alia in the business of exploration of petroleum products and allied activities. Petitioner No.2 is a shareholder of the Petitioner No.1 company. The expression “Petitioner” shall here-in-after refer to the Petitioner No.1 company. The Respondent No.1, MMRDA, is a statutory authority constituted under Section 3 of the Mumbai Metropolitan Region Development Authority Act, 1974. Respondent Nos.2 and 3 are its officers.
5. In the month of December 2005, Respondent No.1, being the owner of the land, had invited bids for leasing out Plot No. C- 64 admeasuring approximately 75,000 sq. mtrs. situated in ‘G’ Block of Bandra-Kurla Complex (BKC) for the purpose of construction of “Convention and Exhibition Centre and Commercial Complex”. The Petitioner had submitted its bid for the s
State of Punjab and Ors. vs. Dhanjit Singh Sandhu
State of Goa vs. Dr. Alvaro Alberto
Banda Development Authority, Banda vs. Motilal Agarwal & Ors.
Constitution of India. In E.P..Royappa v State of Tamil Nadu
Motilal Padampat Sugar Mills Co. Ltd. vs.State of Uttar Pradesh & Ors)
Penalty for construction delay under lease quashed due to delays from court stay, statutory approvals, additional area; writ maintainable for arbitrary state action; 6-year extension non-discriminato....
Supplementary lease deeming additional built-up area integral with no time limit overrides original four-year completion clause for composite construction; penalty demands arbitrary, illegal; payment....
Additional premium demand for construction delay under lease held arbitrary where caused by statutory approvals, late commencement certificates, and extra built-up area without timeline; applicable s....
Lease penalty for construction delay invalid where lessor nondiscloses material site defects, supplementary deed removes time limit for additional built-up area, delays due to approvals/statutory fac....
Imposing penal charges for contract breaches is valid when stipulated policies and terms align with contractual obligations, and acceptance of penalties post-acceptance negates protest claims.
The court emphasized that administrative discretion must be exercised fairly, considering both parties' interests, especially when external factors impede contractual obligations.
The court ruled that the lack of adherence to procedural fairness in demanding additional lease premium necessitated reconsideration, balancing the interests of both parties.
Building permits must comply with statutory provisions, and challenges to such permits must be timely; delay may waive the right to contest approvals.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.