SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Bom) 276

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
SHREE CHANDRASHEKHAR, CJ.,  SUMAN SHYAM, J.
Reliance Industries Limited – Appellant
Versus 
Mumbai Metropolitan Region Development Authority (MMRDA) – Respondent 
Writ Petition No. 242 of 2018 With Interim Application No. 2172 of 2020
Decided On : 08-04-2026

Advocates Appeared:
For the Appellant :Mr. Vikram Nankani, Senior Advocate, with Mr. Vikramaditya Deshmukh, Mr. Ashwin Dave, Mr. Ameya Nabar & Ms. Swati Jain, i/b A. S. Dayal & Associates
For the Respondent:Dr. Birendra Saraf, Senior Advocate, with Mr. Nishant Chotani, Mr. Nivit Srivastava, Ms. Sneha Patil, Ms. Aditi Sinha, Mr. Hrishikesh Joshi & Ms. Isha Vyas, i/b Maniar Srivastava Associates.

Penalty for construction delay under lease quashed due to delays from court stay, statutory approvals, additional area; writ maintainable for arbitrary state action; 6-year extension non-discriminatory; coerced payment refunded.

Headnote:(A) Constitution of India - Articles 14 and 226 - Lease deed clauses 2(d) and 2(e) under Disposal of Land Regulations 1977 - Demand for additional premium/penalty for delay in construction completion - Writ petition challenging demand notices - Maintainable despite contractual nature where public law element and arbitrariness involved; no bar for disputed facts if based on admitted documents; no effective alternative remedy under appeal provisions - Delays due to interim court order, additional built-up area allotment requiring revised plans and statutory approvals (environment clearance, height clearance, etc.), commencement certificate issuance - Four-year completion period computed from commencement certificate date, excluding stay period; no time limit for additional area per authority communication; promissory estoppel applies to exclude stay and impose no time limit - Six-year extension policy applicable even to prior leases to avoid discrimination; penalty demand arbitrary, without prior show cause notice, violating natural justice - Payment under protest/coercion refundable under Section 72 Contract Act. (Paras 46-55, 63-102)

(B) Promissory Estoppel - Authority representations (no time limit for additional area, exclude stay period) binding; cannot resile prejudicially. (Paras 74-76)

(C) Contract Interpretation - Composite construction with common basement/foundation; timelines not severable; construction commences post-commencement certificate; delay not attributable to lessee if due to approvals beyond control. (Paras 66-73, 77)

(D) Refund of Coerced Payments - Deposit under threat of withholding occupation certificate and lease termination recoverable; undertaking under duress not binding. (Paras 85-92)

Facts of the case:
Petitioner leased plot for convention centre and commercial complex (initial 1,15,000 sq mtrs built-up area). Additional areas allotted (72,500 then 1,25,000 sq mtrs, total 3,12,500 sq mtrs) requiring plan revisions, approvals. Interim order restrained part utilization till 2012; commencement certificate for full project in 2014. Authority demanded penalty for 7 years 12 days delay post-4 years from lease; further demand for additional area delay. Petitioner deposited under protest, challenged notices.

Findings of Court:
Impugned notices quashed; entitled to refund of Rs.646,77,68,594 deposited; bank guarantees valid 90 days; refund within 90 days else interest; 6-year completion + excluded stay period applicable; no penalty due.

Issues: Maintainability of writ in contractual dispute; validity of penalty under lease clauses for delay; computation excluding stay/approvals/additional area; applicability of 6-year policy to prior leases; refund of coerced deposit.

Ratio Decidendi: Penalty demands invalid as delays not lessee's fault (court stay, approvals, integrated project); timelines from effective commencement certificate; authority bound by promises; discriminatory policy violative of equality; process lacked natural justice; writ jurisdiction extends to arbitrary state action in contracts.

Result: Writ petition allowed.

Table of Content
1. petition challenges mmrda delay penalty demand. (Para 1 , 2 , 3 , 4)
2. lease mandates construction within four years. (Para 5 , 6)
3. additional fsi allotment stayed by court. (Para 7 , 8 , 9 , 10)
4. court stay delays composite construction commencement. (Para 11 , 12 , 13 , 14)
5. further fsi increases require revised approvals. (Para 15 , 16 , 17 , 18)
6. mmrda demands penalty despite extension resolutions. (Para 19 , 20 , 21 , 22 , 23)
7. payments made under protest amid court stays. (Para 24 , 25 , 26 , 27)
8. parties dispute contract breach and discrimination. (Para 28 , 29 , 30)
9. petitioners argue delays from approvals, stays. (Para 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39)
10. respondents defend mandatory penalty clauses. (Para 40 , 41 , 42 , 43 , 44 , 45)
11. writ maintainable against arbitrary state action. (Para 46 , 47 , 48 , 49 , 50 , 51 , 52 , 53 , 54 , 55)
12. prior judgment supports writ jurisdiction. (Para 56 , 57 , 58 , 59 , 60 , 61 , 62)
13. lease clauses unfair absent approval timelines. (Para 63 , 64 , 65 , 66 , 67)
14. composite project timeline from effective cc. (Para 68 , 69 , 70 , 71 , 72 , 73)
15. promissory estoppel excludes stay periods. (Para 74 , 75 , 76 , 77)
16. no delay attributable to lessee. (Para 78 , 79 , 80 , 81)
17. penalty recovery violates natural justice. (Para 82 , 83 , 84 , 85 , 86)
18. coerced payments refundable under duress. (Para 87 , 88 , 89 , 91 , 92 , 93)
19. precedents distinguished; prior ruling applicable. (Para 94 , 95 , 96)
20. six-year extension applies to prior leases. (Para 97 , 98 , 99 , 100 , 101)
21. demands quashed; penalty refunded with interest. (Para 102 , 103 , 104 , 105 , 106 , 107 , 108)

Judgment :

Suman Shyam, J.

1. Rule. Rule is made returnable forthwith.

2. By consent of the parties, the matter is taken up for final hearing.

3. Assailing the demand-cum-show cause notice dated 12th September 2017 (Exhibit “R”), whereby, the Respondent No.1– Mumbai Metropolitan Region Development Authority (“MMRDA”) had demanded additional premium/penalty as per statements ‘A’ and ‘B’ annexed thereto, for the alleged delay of 7 years and 12 days in completion of construction of a Convention & Exhibition Centre and Commercial Complex on Plot No. C-64, ‘G’ Block, Bandra-Kurla Complex, Mumbai, the Petitioners have approached this Court by filing this Writ Petition invoking the jurisdiction of this Court under Article 226 of the Constitution of India. During the pendency of the Writ Petition, by the communication dated 13th June 2019 (Exhibit “X”) a further amount of Rs.1116,83,10,102/- was demanded from the Petitioner No. 1 as additional premium, along with interest, towards extension of time for completing the construction of the building by using the additional built up area of 72,500 sq mtrs. allotted under the Supplementary Lease Deed dated 13th July 2007. The said Notice is also under challenge in this Writ Petition. The facts and circumstances giving rise to the filing of the present Writ Petition, shorn of unnecessary details, are as hereunder.

4. The Petitioner No.1 is a company incorporated under the provisions of the Companies Act, 1956. As per statements made in the Writ Petition it is engaged inter alia in the business of exploration of petroleum products and allied activities. Petitioner No.2 is a shareholder of the Petitioner No.1 company. The expression “Petitioner” shall here-in-after refer to the Petitioner No.1 company. The Respondent No.1, MMRDA, is a statutory authority constituted under Section 3 of the Mumbai Metropolitan Region Development Authority Act, 1974. Respondent Nos.2 and 3 are its officers.

5. In the month of December 2005, Respondent No.1, being the owner of the land, had invited bids for leasing out Plot No. C- 64 admeasuring approximately 75,000 sq. mtrs. situated in ‘G’ Block of Bandra-Kurla Complex (BKC) for the purpose of construction of “Convention and Exhibition Centre and Commercial Complex”. The Petitioner had submitted its bid for the s

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top