2005 Supreme(Del) 1009
High Court Of Delhi
PREM SAGAR - Appellant
Versus
UNION OF INDIA - Respondent
Decided On : 11/18/2005
Subject
Land Acquisition - Delay and Laches
Act Referred
Headnote
[Paras 24 26]
( 1 ). THE impugned declaration under Section 6 of the land Acquisition Act was issued more than 32 years before the filing of these petitions. That kind of delay is manifestly inordinate. The only question is whether the petitioners have offered any explanation, and if so, whether the same is acceptable to the Court to prevent dismissal of the petitions on the ground of laches.
( 2 ) A large extent of land measuring 516 bighas situate in 7 different villages including Ziauddinpur was notified for acquisition in terms of a preliminary notification issued under Section 4 of the act as early as on 6th March, 1965. The acquisition was meant for the public purpose of planned development of Delhi. Seven different declarations one each for each one of the villages was issued by the competent authority under section 6 of the Act including a declaration dated 7th january, 1969 in relation to the lands under acquisition from Ziauddinpur. An award was eventually made by the collector, Land Acquisition, a decade later on 9th July, 1980. According to the respondents, possession of a part of the land covered by the above notifications, was also taken over from the owners.
( 3 ) AGGRIEVED by the acquisition proceedings, Shri m. L. Malhotra, predecessor-in-interest of petitioners in wp (C) No. 5661/01, filed Suit No. 236/80 (renumbered as 456/1987) for declaration that the said proceedings are illegal and for a direction restraining the defendants from dispossessing him from the suit property. Shri prem Sagar, petitioner in WP (C) No. 848/02 also filed a similar suit for a similar relief being Suit No. 59/84 and so did late Shri Babu Ram and four others who claimed to be the general attorneys of owners of land in Khasra no. 117/2 of village Ziauddinpur in Suit No. 60/84. The plaintiffs in all these suits secured orders of injunction against the defendants which remained in force till the suits were eventually dismissed on 9. 8. 2001 by the civil court in terms of Order VII Rule 11 of the CPC on the ground that the same were not maintainable. In coming to that conclusion, the Court placed reliance upon the judgment of the Supreme Court in State of Bihar Vs. Dhirendra Kumar and Ors. , (1995) 4 SCC 229.
( 4 ) WE have heard learned counsel for the parties and perused the record. Two distinct aspects fall for our consideration. The first is whether there is any explanation for the inordinate delay in the filing of the petitions challenging the acquisition proceedings. The second aspect relates to the merits of the challenge and would arise for consideration only if the writ petitions survive the objection to their maintainability on the ground of delay, laches and acquiescence.
( 5 ) THE period of over 32 years between the date when the declaration under Section 6 was issued and the filing of these writ petitions can, for the sake of convenience, be divided into two parts. The first part would cover the period of 11 years between 7th January, 1969 to 4th January, 1980, i. e. , the date on which the declaration under Section 6 was issued and the date of filing of the suit by the petitioner in WP (C) No. 5661/2001. The second part would cover the period between 1980 to 9th August, 2001 during which time the petitioners in WP (C) No. 5661/2001 were pursuing their remedy before the civil court. In the case of petitioners in WP (C) Nos. 846/02 and 952/02, this period would be between 1984 when the petitioners in those cases filed their suits to 9th August, 2001 when the same were dismissed.
( 6 ) IN so far as the period of more than 11 years between the year 1969 to the year 1980 and 1984 is concerned, the writ petitions do not make any averment or offer any explanation for the inaction of the petitioners during the said period. All that was argued by Mr. Sethi was that the petitioners were expecting the authorities to exclude the land in question from the acquisition proceedings in terms of a general policy under which built-up prope