High Court Of Delhi
OIL AND NATURAL GAS CORPORATION LTD - Appellant
Versus
AMTEK GEOPHYSICAL PVT.LTD - Respondent
O.M.P. 288 of 2004
Decided On : 10/14/2004
Arbitration Act - Oil and Natural Gas Corporation Limited v. Amtek Geophysical Pvt. Ltd. - Sections 43, 21, 37 of the Arbitration Act, 1940 and Arbitration and Conciliation Act, 1996 - The court discussed the applicability of the Arbitration Act, 1940 and the Arbitration and Conciliation Act, 1996 to the arbitral proceedings, the institution of proceedings, and the time limitation for filing a counter claim. The court emphasized the importance of invoking the arbitration clause and initiating proceedings promptly, and ruled that a counter claim must be filed within the limitation period.
Fact of the Case:
The case involved a dispute between Oil and Natural Gas Corporation Limited (Petitioner) and Amtek Geophysical Pvt. Ltd. (Respondent) regarding arbitral proceedings governed by the Arbitration Act, 1940 or the Arbitration and Conciliation Act, 1996. The dispute arose from a contract for acquisition of 2d Seismic Data in India, and the subsequent delay and non-performance of contractual obligations by the Respondent.
Finding of the Court:
The court found that the Petitioner's delay in filing a counter claim was not justified, and emphasized the importance of promptly invoking the arbitration clause and initiating proceedings. The court ruled that the counter claim must be filed within the limitation period, and dismissed the petition.
Issues: The issues included the applicability of the Arbitration Act, 1940 and the Arbitration and Conciliation Act, 1996 to the arbitral proceedings, the institution of proceedings, and the time limitation for filing a counter claim.
Ratio Decidendi: The court emphasized the importance of promptly invoking the arbitration clause and initiating proceedings, and ruled that a counter claim must be filed within the limitation period.
Final Decision: The petition was dismissed.
( 1 ) THE parties have been litigating with each other with ferocity for several years. Observations were made by this Court to the effect that the Oil and Natural Gas corporation Limited (hereinafter referred to as the petitioner) had adopted dilatory tactics in the Claims raised by Amtek Geophysical Pvt. Ltd. (hereinafter referred to as the Respondent) which are the subject matter of arbitration proceedings. One of the contentions that had arisen was whether the Arbitration Act, 1940 or the Arbitration and Conciliation Act, 1996 would govern the arbitral proceedings. In SLP No. 5211/2002 the Hon ble supreme Court had passed the following Order while disposing of the Petition on 19. 4. 2002: by consent of parties, the order of the High Court is modified as follows: the arbitration proceedings will go on under the provisions of the new Arbitration Act. However, any party aggrieved by the Award to be passed by the Arbitrator will be at liberty to challenge the same either under the old or the new Act and, if any objection is raised by any of the opposing parties as to the applicability of the old or the new Act, the same shall be decided by the court concerned independently without being influenced by the impugned order in this special leave petition. With this modification, the SLP is disposed of.
( 2 ) THE contentions that have been raised before me have been articulated by Mr. Sundaram, learned Senior counsel for the Petitioner as follows:
1. For the purpose of limitation what is relevant is the institution of proceedings and not filing of pleadings.
2. In some cases like a suit under CPC, institution of proceedings arises through the filing of pleadings.
3. However, under the Arbitration Act, the institution of proceedings for the purpose of limitation is through giving of notice of dispute. See Sections 43 (2) and section 21.
4. Any delay would only be for condoning the delay in filing pleadings as directed and there is no bar under section 3 of the Act that such delay should not be considered. This is in the context of the decision dated 17. 8. 2004 of the learned Arbitral Tribunal dismissing the Counter claim filed by the Petitioner for the reason that it could not be entertained on the date on which it was filed. The application seeking condonation of delay was dismissed.
( 3 ) THE annals of the litigation, in brief, is that the Petitioner had, in 1986, invited Tenders for acquisition of 2d Seismic Data in India. After detailed discussions and negotiations Works were awarded on 17. 10. 1988 to the Respondent for Cambay Basin (Gujarat) and Assam/nagaland region; and for the Cauvery Basin and krishna Gadavary Basin on two other parties. The Contract was executed between the Petitioner and the Respondent on 19. 10. 1989. It is the case of the Petitioner that even after the expiry of the stipulated period of nine months for mobilisation of equipment and crew, it gave as many as ten extensions to the Respondent. The Petitioner further asserts that almost no work was carried out by the Respondent in the Cambay area. On 28. 12. 1993 several notices were issued by the Petitioner to the Respondent for resumption of work. Eventually on 31. 12. 1993 the petitioner invoked a Bank Guarantee furnished by the respondent. This led to the filing of a petition under section 20 of the Arbitration Act, 1940 by the Respondent being the springboard for the litigation which had reached the Hon ble Supreme Court which was disposed of by its Order dated 19. 4. 2002. On 23. 4. 1997 the Petitioner appointed Justice Rajinder Sachar, Retired Chief Justice of the Delhi High Court as its Arbitrator. By a communication dated 9. 11. 1996 the Respondent appointed late Shri R. V. Reddy as their Arbitrator. In December 1997 Justice K. Amareswari (Retired) was appointed as the presiding Arbitrator by these two Arbitrators. On 22. 11. 2002 Shri R. V. Reddy died and consequently Dr. Avtar Singh was appointed in his place in December, 2002. It ha
REFERRED TO : Sundaram Finance Ltd. vs. NEPC India Ltd.
Ashok Traders and Another vs.Gurumukh Das Saluja and Others
Ramesh Chand Ardawatiya vs. Anil Panjwani
A.A.Haja Muniuddian vs. Indian Railways
Union of India and another vs. M/s. Vijay Construction Co.
Oriental Building and Furnishing Co. Ltd., New Delhi vs. Union of India
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.