1997 Supreme(Del) 213
High Court Of Delhi
NAV BHARAT CONSTRUCTION COMPANY - Appellant
Versus
DELHI DEVELOPMENT AUTHORITY - Respondent
Suit 1611A of 1994
Decided On : 02/28/1997
Important Points
Subject
Arbitration Law - AWARD - OBJECTION
Act Referred
CONTRACT ACT : S.73
Headnote
ARBITRATION - AWARD - OBJECTION - JURISDICTION - POWER OF COURT - INTERFERENCE - GROUNDS - MISCONDUCT - ERROR OF LAW - CONSTRUCTION OF AGREEMENT - DAMAGES - INTEREST.
Fact of the Case:
A dispute arose between the petitioner and the respondent regarding the construction of 656 LIG houses. The dispute was referred to arbitration, and the arbitrator passed an award in favor of the petitioner. The respondent filed objections to the award, alleging that the arbitrator had misconducted himself and erred in law in interpreting the agreement and awarding damages and interest.
Finding of the Court:
The court held that the arbitrator had not misconducted himself and had not erred in law. The court found that the arbitrator had taken into consideration all the relevant evidence and had come to a reasonable conclusion. The court also held that the arbitrator was entitled to award damages and interest, and that the amounts awarded were not excessive.
Issues: 1. Whether the arbitrator had misconducted himself. 2. Whether the arbitrator had erred in law in interpreting the agreement. 3. Whether the arbitrator had erred in law in awarding damages and interest.
Ratio Decidendi: 1. The court held that the arbitrator had not misconducted himself because he had taken into consideration all the relevant evidence and had come to a reasonable conclusion. 2. The court held that the arbitrator had not erred in law in interpreting the agreement because he had given a reasonable interpretation of the relevant clauses. 3. The court held that the arbitrator had not erred in law in awarding damages and interest because he was entitled to do so and the amounts awarded were not excessive.
Final Decision: The court rejected the respondent's objections and made the award a Rule of the Court. The petitioner was also entitled to interest at the rate of 15% per annum from the date of the decree till the date of realization.
Naresh Markanda, P.C.MARKANDA, SUMiT BANSAL
( 1 ) THE petitioner entered into an agreement with the respondent for construction of 656 LIG houses at Jahangirpuri, including works relating to water supply, sanitary work and internal development. As per the agreement entered into between the parties, the work was to commence on 22. 8. 1987 and the date of completion was 22. 8. 1988.
( 2 ) IN respect of the aforesaid agreement, disputes arose between the parties relating to payment to be made to the petitioner and accordingly, the said disputes were referred to the Arbitrator by the Engineer Member of the respondent in terms of Clause 25 of the agreement entered into between the parties. The Engineer Member appointed Shri S. K. Ahuja of the Department of Telecommunication as the Sole Arbitrator and the Arbitrator was specifically directed to give reasons for the award.
( 3 ) THE Arbitrator entered into the reference and accepted the statement of claims and counter statements of facts along with the rejoinder to the counter statement of facts and after hearing the parties made the award on 30. 3. 1994. The Arbitrator filed the award along with the records of the arbitration proceedings in this Court on receipt of which, notices of filing of the award were issued to the parties. On receipt of the aforesaid notices, the respondent has filed an objection against the award which was registered as I. A. No. 889/1995. The petitioner however filed a reply to the aforesaid objection, but did not file any objection against the award and prayed that the award be made a Rule of the Court.
( 4 ) ACCORDINGLY the Counsel appearing for the parties were heard, who took me through the records of the arbitration proceeding including the award.
( 5 ) THE jurisdiction and power of the Court to interfere with an award passed by an Arbitrator is by now well settled. Resolving of disputes through arbitration has come to be accepted in India for its quicker disposal and the same being a proceeding initiated, continued and completed by the consent of the parties. However, the Courts through various decisions have laid down that the Court has a duty to oversee that the Arbitrator acts within the norms of justice. In that context, the Arbitration Act has provided for the provisions of Sections 30 and 33 which enumerate the grounds on which the award could be set aside. The Court have also laid down the scope and limit of correction of an award by the Court, while dealing with the objections filed against the award under Sections 30 and 33 of the Act. The award of the Arbitrator can be interfered with or set aside or modified only within the four corners of the procedure provided by the Arbitration Act.
( 6 ) HALSBURY s Laws of England, Volume 2,4th Edition para 623 retiterates that an Arbitrator s award may be set aside for error of law apparent on the face of it. The award can be set aside if, inter alia, the Arbitrator misconducts himself or the proceedings. It is also laid down by the Supreme Court that it is not misconduct on the part of an Arbitrator to come to an erroneous decision or wrong conclusion or failure on his part to appreciate facts. (Seem/s. Hindustan Tea Co. v. K. Shashikant and Co. , AIR 1987 SC 81)
( 7 ) IN the instant case, the Arbitrator in terms of the reference was duty bound to make a speaking award, that is, to say he has to give reasons for his conclusions. In terms of the aforesaid reference, the Arbitrator in the instant case has passed a reasoned award. Therefore, the purpose would be to see whether the Arbitrator has taken a view which could not possibly be sustained on any view of the matter or that such reasons which are recorded by the Arbitrator are erroneous as propositions of law. In M/s. Sudarsan Trading Company v. Government of Kerala reported in AIR 1989 SC 890, it has been held that an award could be set aside if the Arbitrator has misconducted himself or has proceeded beyond his jurisdiction. It can also be set aside where there are errors apparen