2007 Supreme(Del) 1525

High Court Of Delhi
VIPIN SANGHI
SIMPLEX CONCRETE PILES (INDIA) PVT. LTD - Appellant
Versus
UNION OF INDIA - Respondents
. A. 2039 Of 1989
Decided On : 07/27/2007

Subject

Arbitration Law - Award

Headnote

Arbitration Act, 1940

        Sections 30 & 33 - Objections to the Arbitral Award — Entitled to interest — A matter may be considered to be not pending when it has been finally disposed of by a court or authority and nothing more needs to be determined/or nothing survives for determination — Till the objections filed in pursuance of the notice of filing of the award in court are pending, or awards has not been decree of the court, it cannot be said to be final — Held that the Petitioner is entitled to pendente lite interest (during arbitration proceedings) on the awarded amount @ 10% per annum.

Advocates Appeared:
Nitinjya Chaudhary, SALEEM AHMAD, Sushma Sachdeva, V.P.Chaudhary

VIPIN SANGHI, J.

( 1 ) BY this order I proceed to dispose of the objections filed by the parties before me to the Arbitral Award dated 31. 10. 1988, made by the sole arbitrator, Shri J. P. Singhal.

( 2 ) VIDE his letter dated 5th December 1988, the learned Arbitrator had filed the award in Court to be made a 'rule' of the Court. Both the parties to the award,. e. , the claimant and the respondent before the Arbitrator filed their objections on 15. 2. 1989 (registered as. A. No. 1961/1989) and 7. 2. 1989 (registered as. A. No. 2039/1989) respectively.

( 3 ) BRIEF facts leading to the passing of the award are that Union of India (referred to as 'respondent' hereinafter) had invited tender for the work of construction of flyover at Lodhi Hotel inter-section, New Delhi at an estimated cost of Rs. 2,04,66,773/ -. Work contract was awarded to M/s. Simplex concrete Piles India (P) Ltd. (referred to as the 'claimant' hereinafter) for rs. 2,48,85,564/- to be completed within a period of 16 months starting 1. 1. 1981. However, the work could not be completed in time, and was thus delayed by a month, though extension had been granted for, upto 31. 12. 1982.

( 4 ) FINAL Bill was raised and some deductions etc. were made to the amount claimed and consequently differences/disputes arose between the parties which were referred to the sole Arbitrator.

( 5 ) THE Claimant has objected to the award to the extent it fails to award pendente lite interest to it as an error apparent on the face of the award.

( 6 ) THE respondent has challenged the award so far as it relates to claim nos. 1, 2, 3, 5, 7, 13 (iii) and 21. Objections of Respondent:

( 7 ) CLAIM No. 1 for Rs. 28,30,000/- was made on account of reduction of capacity of piles by the Respondent/department,. e. , from 110 tonnes to 80 tonnes, which resulted in increase in the number of piles by 82. It is alleged that the Arbitrator misconducted himself in coming to the conclusion that the claimants had, in accordance with clause No. 2. 5. 5 of the additional condition to the agreement, offered a guaranteed safe load carrying capacity of 110 tonnes, inasmuch as, there was no acceptance of the above offer by the Respondent. On the contrary the requirement of clause 2. 5. 3 of the agreement required the claimant to submit preliminary calculations for arriving at the size, length and load carrying capacity of the piles.

( 8 ) IT is also argued that the arbitrator also misconstrued the provisions contained in clause No. 2. 4. 2 of the agreement at Page 135 which was binding on the Claimant. The Arbitrator construed the clause to imply that trial bores and testing of soil samples was primarily necessary for checking design of retaining walls etc. , where design of foundation was other than piles. , whereas the words used in the said clause were ". . . for checking and final design of the foundations of flyover and its approaches at suitable location. . . . " Thus no distinction was made by the arbitrator whether foundations were walls or concrete piles.

( 9 ) IT is alleged that the Arbitrator also misconducted himself by holding that it was the field load test, which ought to have been regarded, and the process static formula adopted by the respondent ought to have been disregarded. As far as the field load testing was concerned the Arbitrator ignored the provisions of clause 5. 8. 3 and 5. 8. 4 of IS:2911 Part 1 Section 1 1979 regarding the factor of safety on the test load. The factor of safety adopted by the Claimant was `2' only, whereas it ought to have been "2. 5". Thus, the Arbitrator erroneously upheld the contention of the Claimant that the fixation of capacity of piles as 80 tonnes by the Respondent and its intimation to the Claimant on 6. 4. 1981 was contrary to the provisions of the agreement. This was also in violation of clause 4. 3 of the agreement.

( 10 ) THE Arbitrator also erred in concluding that the value of 'k'. e. the co-efficient of the earth pressure fixed by the R




























1
2
3
4
5
6
7
8
9
10
11