2012 Supreme(Del) 2153
HIGH COURT OF DELHI
S. MURALIDHAR, J
Union of India
Versus
Pt. Munshi Ram & Associates Pvt. Ltd.
O.M.P. No. 432 of 2011
Decided On: 21-12-2012
Important Points
Subject
Arbitration Law - Challenge to Award
Act Referred
Headnote
The Petitioner challenged an Award under Section 34 of the Arbitration and Conciliation Act, 1996. The disputes arose from the construction of Type-V quarters at R.K. Puram, New Delhi. The Petitioner raised preliminary objections on limitation, which were rejected by the Arbitrator. The court upheld the Arbitrator's view that the limitation clause was void under Section 28 of the Indian Contract Act, 1872. The court also found that the delay in completion of work was attributable to the Petitioner. The court rejected objections to the impugned Award in respect of certain claims and costs, but set aside the Award in respect of post-Award interest on the interest component and costs under Claim No.13.
For the Petitioner:Ajay Verma, Ananya Mitra, Advocates.
For the Respondent:Anusuya Salwan, Renuka Arora, Vikas Sood & Kunal Kohli, Advocates.
S. MURALIDHAR, J
1. The challenge in this petition under Section 34 of the Arbitration and Conciliation Act, 1996 (‘Act’) by the Petitioner Union of India through its Executive Engineer, Construction Division-III, Central Public Works Department (‘CPWD’) is to an Award dated 24th February 2011 passed by the learned sole Arbitrator in the disputes between the Petitioner and the Respondent, Pt. Munshi Ram & Associates Pvt. Ltd. arising out of the work of construction of certain Type-V quarters at R.K. Puram, New Delhi, for which an agreement was entered into.
2. In terms of the agreement, the work was to commence on 22nd December 1995 and was to be completed within 21 months, i.e., by 21st September 1997. According to the Petitioner, as per the provisional completion certificate recorded by it, the date of completion was 30th January 2001. It is stated that since there were outstanding defects and unfinished items, the Superintending Engineer (‘SE’) granted extension of time (‘EoT’) upto 30th June 2002 for the final completion. It is stated that no separate completion certificate was issued.
3. As a result of the disputes between the parties, the Respondent invoked the arbitration clause on 3rd January 2009. Thereafter, by an order dated 27th October 2009, in Arb. P. No.59 of 2009, this Court appointed the learned Arbitrator. The Respondent filed 14 claims before the learned Arbitrator, out of which four, namely, Claim Nos.3, 4, 6 and 11 were rejected. Clause prescribing limitation for preferring claims
4. As noted in the impugned Award, the Petitioner herein raised three preliminary objections on 30th March and 7th April 2010. One of the preliminary objections was that the claims were barred by limitation under Clause 25 of the agreement. It is contended that the work was provisionally completed on 30th January 2001 and the bill for the undisputed items was finalized on 2nd March 2007 and the balance towards escalation was paid on 30th March 2007. It was submitted that since the Respondent had invoked Clause 25 of the agreement only on 3rd January 2009, i.e., 7 years and 11 months after recording of the provisional completion and 1 year and 10 months after finalisation of the bill, the invocation of the arbitration clause was well beyond 90 days as prescribed in Clause 25.
5. In rejecting the above preliminary objection by order dated 1st May 2010, the learned Arbitrator observed that in view of Section 28(b) of the Indian Contract Act, 1872 (‘CA’) an amendment agreement in restraint of legal proceedings contrary to the mandate of Article 137 of the Limitation Act, 1963 (‘LA’) would be void and any clause extinguishing the right of a party or discharging any party from its liability in respect of the contract on expiry of a specific period, so as to restrict the time period would be void. It was further observed that the arbitration clause was invoked by the Respondent on 3rd January 2009 within the statutory limitation period of three years from the alleged date of 30th March 2007. Further, it was noted that the copy of the final bill, as submitted by the Petitioner herein and disputed by the Respondent, showed that Rs.40,000 was withheld for pending extra items and substituted items; Rs.10,000 was withheld for pending quality control; Rs.20,000 was withheld for pending sanction for deviation statement ALR and AHR items and Rs.20,000 was withheld pending sanction of non-ALR and non-AHR items. Also, the final bill did not bear the signature of the Respondent.
Accordingly, it was held that this could not be said to be the final bill. In fact, the Respondent had not received the final bill till 10th May 2008. Consequently, it was held that the claim was not barred by limitation. As noted in the impugned Award, the Petitioner then filed an application under Sections 12, 13 and 18 of the Act against the above order and this application was rejected by the learned Arbitrator by an order dated 23rd June 2010.