2013 Supreme(Del) 1553

THE HIGH COURT OF DELHI AT NEW DELHI
BADAR DURREZ AHMED, R.V.EASWAR, JJ.
M/S INDU PROJECTS LTD-Appellant
Versus
UNION OF INDIA-Respondent
M/S INDU PROJECTS LTD-Appellant
Versus
UNION OF INDIA-Respondent
M/S INDU PROJECTS LTD-Appellant
Versus
UNION OF INDIA-Respondent

M/S INDU PROJECTS LTD-Appellant
Versus
UNION OF INDIA-Respondent
FAO(OS) 529/2013, 530/2013, 531/2013, 532/2013
Decided On : NOVEMBER 21, 2013

Subject

Bank Guarantee - Unconditional Bank Guarantee

Act Referred

ARBITRATION AND CONCILIATION ACT : S.9

Headnote

Arbitration and Conciliation Act, 1996 - Section 9 - Indian Contract Act, 1872 - Sections 73, 74 - Injunction - Bank guarantee - Invocation - Injunction against encashment of the performance bank guarantee - There has been a delay in the execution of the contract - There is a breach of terms, which has resulted in an injury to the respondent - Letter of invocation in terms of the bank guarantee speaks of the loss/damage, which would be caused to it by reason of breach, which is, estimated to exceed the value of the bank guarantee - Bank guarantee is an independent contract - Bank, which has furnished the bank guarantee, at the behest of the contractor is not to look to the terms of the main contract entered into between the contractor and the beneficiary - Held, observations are prima facie in nature and they would have no impact on the merits of the disputes when, the petitioner, was to take recourse to arbitral proceedings - Petition is dismissed.

Advocates Appeared:
For the Appellant :Mr Dushyant Dave and Mr Ashok Bhan, Senior Advocates with Mr Ashish Bhan and Mrs Genny Jetley Rautray
For the Respondent: Mr Rajeeve Mehra, ASG with Mr Sumeet Pushkarna, Mr Jaswinder Singh and Ms Sana Sundaram

JUDGMENT

BADAR DURREZ AHMED, J (ORAL)

CM Nos. 18349-52/2013

The exemptions are allowed subject to all just exceptions.

FAO(OS) 529/2013, 530/2013, 531/2013 & 532/2013

1. These appeals have been preferred against the judgments dated 18.11.2013 delivered by a learned Single Judge of this court in O.M.P Nos. 1112-1115/2013. The said OMPs were all petitions under Section 9 of the Arbitration and Conciliation Act, 1996 seeking injunctions in respect of encashment of identical performance bank guarantees. The facts in all four cases are identical except that the numbers of the bank guarantees and the amounts and the underlying contracts are different. However, the bank guarantees, the invocation letters and the underlying contracts are in identical terms. It is for this reason that we shall be referring only to the bank guarantee No. 2010133IBGP0326 dated 25.10.2010 in OMP No. 1112/2013 and the relative invocation letter dated 23.10.2013.

2. The learned Single Judge after analyzing the law on the subject and on going through the facts and circumstances of the case has declined to grant injunctions against the encashment of the bank guarantees. Several points were argued before the learned Single Judge, one of them being that the bank guarantees themselves have been wrongfully invoked. Another aspect which was argued was that the factum of loss or damage has not been established and therefore the invocation was bad / fraudulent. It was also argued that special equities arose in the case, inasmuch as, according to the appellants / petitioners there were difficulties with regard to the availability of site, availability of steel and unprecedented rains which delayed the execution of the underlying contracts. It was also argued that because of these difficulties extensions had been granted from time to time.

3. After examining these facts in the light of the law on the subject, the learned Single Judge came to the conclusion that the invocations were within the terms of the bank guarantees and that it was not necessary for the appellants / petitioners to have quantified the loss or damage which had occurred or was likely to be suffered by the respondent. It was also concluded by the learned Single Judge that this was not a case in which the concept of special equities could have been invoked. He was of the view that the expression “special equities” have been interchangeably used with the expression “irretrievable injury” or “irreparable injustice”. The learned Single Judge further concluded that a broad test as to whether such an irretrievable injury or irreparable injustice had been caused or special equities had arisen would be to find out as to whether the aggrieved party would be in difficulty to realise or recover the amounts which are reflected in the bank guarantees from the opposite party if the aggrieved party were to ultimately succeed in the principal action based on the underlying contract that it may launch against the opposite party. For this the learned Single Judge placed reliance on the Supreme Court decision in the case of Vinitec Electronics Pvt. Ltd. v. HCL Infosystems Ltd. (2008) 1 SCC 544 (paragraph 29). The learned Single Judge concluded that if he was to apply the said test to the present case, the same would not come within the ambit of special equities.

4. Mr Dave, the learned Senior counsel, appearing on behalf of the appellants submitted that the invocation was not in terms of the bank guarantee and, therefore, the same could be injuncted. He submitted that it was incumbent upon the respondent to have quantified the loss or damage caused or which was likely to be caused or suffered and unless and until that was done, the invocation itself was bad. He drew out attention to the terms of the guarantee and, in particular, to paragraph (1) and (2) thereof which reads as under:-

“1. The IDBI Bank Limited, D.No. 5-9-89/1, Chapel Road, P.B.No.370, Hyderabad Main Branch, Hyderabad – 500001 (herein after referred to




























1
2
3
4
5
6
7
8
9
10
11