2014 Supreme(Del) 1207
IN THE HIGH COURT OF DELHI AT NEW DELHI
VIPIN SANGHI, J.
STEEL AUTHORITY OF INDIA LTD (SAIL) - Petitioner
Versus
DAMPSKIBASELSBAKET NORDEN A/S - Respondent
O.M.P. 773/2013 AND I.A. No. 14983/2013
Decided On : 30.04.2014
Mr. A.K.Ganguli, Sr. Advocate with Ms. Monika Garg and Mr. George Varghese, Advocates
Mr. Prashant S.Pratap, Sr. Advocate with Mr. O.P.Gaggar, Advocate and Mr. Aditya Gaggar, Advocate
The time lost in waiting for a berth is to be treated as if the vessel were in berth and at the disposition of the charterer for carrying out the loading or discharging operation, and the charterer is entitled to a pro-rata reduction in demurrage for the pre-berthing period corresponding to the breakdown of a crane.
Headnote:
The court set aside the arbitral award to the extent that it denied the charterer's claim for a pro-rata reduction in demurrage for the pre-berthing period corresponding to the breakdown of a crane. The court held that the tribunal erred in failing to apply the principle established in the Darrah case, which requires that the time lost in waiting for a berth be treated as if the vessel were in berth and at the disposition of the charterer for carrying out the loading or discharging operation. Accordingly, the court remitted the matter back to the tribunal for reconsideration of this aspect.
Fact of the Case:
The dispute arose from a contract of affreightment (COA) between a ship owner and a charterer for the carriage of a cargo of coking coal from Newport News, Virginia, USA to Vishakhapatnam, Paradip, and Haldia, India. The COA required the owner to nominate vessels for three shipments, two of which were MV Nord Fighter and MV Navios Kypros. During the discharge operations at Vishakhapatnam and Haldia, one of the cranes on each vessel suffered a breakdown, resulting in a reduction in the discharge rate. The charterer deducted the corresponding amount from the balance freight, claiming that the despatch amount earned by it was USD 97,395.83 for MV Nord Fighter and USD 43,291.67 for MV Navios Kypros. The owner, on the other hand, calculated the laytime on the basis of the NOR tendered by it on arrival of the vessels at the respective ports and claimed an additional amount of USD 312,104.16 for MV Nord Fighter and USD 105,875.00 for MV Navios Kypros. The dispute was referred to arbitration, and the arbitral tribunal upheld the owner's stand, awarding a sum of USD 417,979.16 along with interest amounting to USD 70,556.34 in favor of the owner.
Finding of the Court:
The court found that the tribunal erred in its interpretation of the relevant clauses of the COA, particularly clauses 1(a), 35, 40, 43, and 44. The court held that the tribunal's interpretation of clause 35, which provides for the commencement of laytime, was overly narrow and did not take into account the effect of other relevant clauses, such as clause 1(a), which imposes an obligation on the owner to provide a minimum number of functional cranes and grabs within a specified time of berthing. The court also found that the tribunal's interpretation of clauses 40, 43, and 44, which deal with the consequences of breakdown of a crane, was unreasonable and did not give effect to the intention of the parties as expressed in the COA.
Issues: 1. Whether the tribunal erred in its interpretation of clause 35 of the COA, which provides for the commencement of laytime, by failing to take into account the effect of other relevant clauses, such as clause 1(a), which imposes an obligation on the owner to provide a minimum number of functional cranes and grabs within a specified time of berthing? 2. Whether the tribunal erred in its interpretation of clauses 40, 43, and 44 of the COA, which deal with the consequences of breakdown of a crane, by failing to give effect to the intention of the parties as expressed in the COA?
Ratio Decidendi: The court applied the principle established in the Darrah case, which requires that the time lost in waiting for a berth be treated as if the vessel were in berth and at the disposition of the charterer for carrying out the loading or discharging operation. The court held that this principle applies equally to the pre-berthing period as it does to the post-berthing period, and that the charterer is entitled to a pro-rata reduction in demurrage for the pre-berthing period corresponding to the breakdown of a crane.
Final Decision: The court set aside the arbitral award to the extent that it denied the charterer's claim for a pro-rata reduction in demurrage for the pre-berthing period corresponding to the breakdown of a crane. The court remitted the matter back to the tribunal for reconsideration of this aspect in light of the principle enunciated in the Darrah case.
VIPIN SANGHI, J.
1. The petitioner has filed the present petition under section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the Act) for setting aside of the award dated 26/27.2.2013, rendered by a three member arbitral tribunal. Under the award, a sum of USD 417,979.16 along with interest amounting to USD 70,556.34 has been awarded in favour of the respondent herein.
Background facts:
2. Facts of the case are that a Contract of Affreightment (hereinafter referred to as COA) was executed between DAMPSKIBSSELSKABET NORDEN A/S, COPENHAGEN as owner-respondent herein, and Steel Authority of India Ltd (SAIL) as charterer-petitioner herein, on 03.03.2008, whereby a cargo of 3x 50,000 MT, more or less 5%, coking coal in bulk was to be loaded from Newport News or Norfolk, Virginia, USA for discharge at Vishakhapatnam, Paradip and Haldia. Pursuant to the COA, the respondent owner was required to nominate vessels for three shipments. Two of such nominated vessels were MV Nord Fighter and MV Navios Kypros.
3. As agreed in the said contract, MV Nord Fighter was loaded at Newport News, Virginia, USA with 51544.726 MT coal-with cargo quantity of 25,189 MT to be discharged at Vishakhapatnam, and balance quantity of 26,355.73 MT to be discharged at Haldia. It arrived at the port of Vishakhapatnam on 12.05.2008 and notice of readiness (NOR) was given on 12.05.2008 at 9.45 hours. The vessel berthed at GCB berth in Vishakhapatnam on 17.05.2008 at 1700 hours, and commenced discharging at 1830 hours. The vessel had arrived at the said port with a non functional crane (crane no.3), fitted with a grab, which was under repair and made available/ready only on 20.05.2008 at 2200 hours. Completing discharge at Vishakhapatnam port on 21.05.2008 at 03.45 hrs, the vessel then sailed to Haldia to discharge the balance cargo quantity. The discharge at Haldia was completed on 24.05.2008 at 2140 hrs. The petitioner, accepting the NOR from the time when all the 4 cranes with 4 grabs were made available in operational condition, i.e. 20.05.2008, as opposed to the time when it was tendered by the respondent on 12.05.2008, calculated the lay time accordingly. As per petitioner’s calculations, the despatch amount earned by it was USD 97,395.83, and so, it made a payment of USD 461,300.74 to the respondent towards balance freight, after taking into account the load port demurrage and discharge port despatch so calculated. The respondent, on the other hand, calculated the lay time on basis of the NOR tendered by it on arrival of the vessel at Vishakhapatnam on 12.05.2008. Thus, disputing the deduction of the said despatch amount, it claimed an additional amount of USD 312,104.16.
4. Similarly, the other vessel MV Navios Kypros was loaded at Newport News, Virginia, USA with 53731.008 MT coal -with cargo quantity of 25743 MT to be discharged at Vishakhapatnam, and the balance quantity of 27988.008 MT to be discharged at Haldia. On arrival at Vishakhapatnam port, the vessel gave the NOR on 28.07.2008 at 1400 hrs. It berthed on 31.07.2008 at 11.30 hrs, and commenced discharging at 15.30 hrs, which was completed on 02.08.2008 at 2130 hrs. While discharging at the said port, crane no.2 suffered a breakdown on 01.08.2008, which could not be repaired even until the completion of the discharge operation at the said port. Thereafter, the vessel sailed to the second port of discharge, i.e. Haldia, with a non functional crane fitted with a grab. It arrived at the port of Haldia on 04.08.2008 and NOR was given at 1900 hours. It berthed on 05.08.2008 at 02.30 hrs, and commenced discharging at 04.15 hrs. The discharge at Haldia was completed on 09.08.2008 at 1000 hrs. Pertinently, the non functional crane was repaired and made functional only on 08.08.2008 at 1250 hours. The petitioner, accepting the NOR for the second discharge port from the time when all the 4 cranes with 4 grabs were made available in operational condition at Haldia, i.e