2015 Supreme(Del) 2667
IN THE HIGH COURT OF DELHI
RAJIV SAHAI ENDLAW, J.
Jhansi Orai Tollway Private Limited – Petitioner
Versus
Union of India & Others – Respondents
W.P. (C) No. 9628 of 2015
Decided On : 9.10.2015
Important Points
Subject
Contract Law - Termination of Agreement
Act Referred
MEDICAL COUNCIL OF INDIA ACT : S.10(a)(4)
Headnote
Performance Security - Termination of Concession Agreement - Clause 9.1.2 - Summary of Acts and Sections: Clause 9.1.2 of the Concession Agreement - Summary: The court discussed the termination of a Concession Agreement between the petitioner and the National Highways Authority of India (NHAI) for operation and maintenance of a highway stretch. The court analyzed the petitioner's failure to furnish the Performance Security within the stipulated time and the legal implications of the termination notice issued by NHAI. The court highlighted the provisions of Clause 9.1.2 of the Concession Agreement and emphasized that the petitioner's failure to fulfill its contractual obligations disentitled it from challenging the termination by NHAI.
Fact of the Case:
The petition impugns the termination of the Concession Agreement dated 5th February, 2013 between the petitioner and NHAI for operation and maintenance of a highway stretch. The petitioner failed to furnish the Performance Security within the stipulated time, leading to the termination of the agreement by NHAI.
Finding of the Court:
The court found that the petitioner's failure to furnish the Performance Security within the stipulated time disentitled it from challenging the termination by NHAI.
Issues: The issues revolved around the petitioner's failure to fulfill its contractual obligations, the legality of the termination notice issued by NHAI, and the petitioner's entitlement to specific performance of the Concession Agreement.
Ratio Decidendi: The court held that the petitioner's failure to fulfill its contractual obligations disentitled it from challenging the termination by NHAI. The court emphasized that the deeming provision in Clause 9.1.2 of the Concession Agreement was enforceable, and the petitioner was not entitled to specific performance of the agreement.
Final Decision: The petition was dismissed with no costs, and the petitioner was given liberty to approach the Arbitrator or the Civil Court as may be appropriate.
For the Petitioner:Mr. Garvesh Kabra and Mr. A.H. Lohiya, Advocates.
For the Respondent:Ms. Anjana Gosain and Mr. Vishu Agarwal, Advocates.
For the Union of India:Mr. Ravi Sikri, Senior Advocate with Mr. Mukesh Kumar, Ms. Meenakshi Sood, Mr. Shantnu Awasthi and Mr. Binay Kumar Thakur, Advocates.
RAJIV SAHAI ENDLAW, J.
1. Allowed, subject to just exceptions.
2. The applications are disposed of.
W.P. (C) No. 9628 of 2015 & C.M. No. 22827 of 2015 (for stay)
3. The petition impugns the letter dated 3rd March, 2014 of the respondent No. 2 National Highways Authority of India (NHAI) of termination of the Concession Agreement dated 5th February, 2013 entered into between the petitioner and the respondent No. 2 NHAI for operation and maintenance of Jhansi-Orai section stretch admeasuring 135.413 Km. of NH-25 in the State of Uttar Pradesh on Operation Management Transfer (OMT) basis.
4. The petition impugning the termination dated 3rd March, 2014 has come up for the first time today before this Court. It is the case of the petitioner that the petitioner was not aware of the said termination and has been informed of the same for the first time only on 22nd July, 2015 and the copy of the letter dated 3rd March, 2014 has been furnished to the petitioner on 11th September, 2015.
5. The counsel for the petitioner has been heard.
6. It is not in dispute that within sixty days of the execution of the said Concession Agreement, the petitioner was required to furnish a Performance Security to the respondent No. 2 NHAI. Clause 9.1.2 of the Concession Agreement is as under:-
“9.1.2 Notwithstanding anything to the contrary contained in this Agreement, in the event Performance Security is not provided by the Concessionaire within a period of 60 (sixty) days from the date of this Agreement, the Authority may encash the Bid Security and appropriate the proceeds thereof as Damages and thereupon all rights, privileges, claims and entitlements of the Concessionaire under or arising out of this Agreement shall be deemed to have been waived by and to have ceased with the concurrence of the Concessionaire, and this Agreement shall be deemed to have been terminated by mutual agreement of the Parties.”
7. It is also not in dispute that the petitioner within the said period of sixty days did not furnish the Performance Security.
8. It is the case of the petitioner that the said period of sixty days was extended to 180 days with effect from 14th May, 2013 in terms of the Circular dated 29th May, 2013 of the respondent No. 2 NHAI.
9. However, the fact remains that the petitioner did not furnish the Performance Security even within the said extended period of 180 days and which resulted in the respondent No. 2 NHAI issuing a termination notice dated 18th February, 2014 to the petitioner and relevant paragraphs whereof are as under:-
“Whereas, in term of clause 9.1.2 of the Concession Agreement the Concessionaire viz. Jhansi-Orai Tollway Pvt. Ltd. was required to provide Performance Security within a period of 60 days from 5th February, 2013.
Whereas, the due date for submission of Performance Bank Guarantees has expired on 4th April, 2013 but the Concessionaire has failed to comply with its contractual obligation despite giving additional time to submit the Performance Bank Guarantee. The Concessionaire continues to be in breach of its contractual obligations by not submitting the Performance Bank Guarantee.
Whereas after execution of the Concession Agreement, submission of Performance Bank Guarantee was one of the essential and foremost steps to be undertaken by the Concessionaire as a mark of commitment to undertake the project work which the Concessionaire is no more interested and has no intention to undertake the project work.
Whereas upon failure of the Concessionaire to fulfil one of the Condition Precedent under Article 4.1.2, read in conjunction with Article 9.1.2, the Authority was constrained to encash the Bid Security on 30.10.2013.
Now therefore, the Authority has come to irresistible conclusion that this a fit case to invoke provision of 9.1.2 of the Concession Agreement wherein the Concessionaire is deemed to have waived its all rights, privileges, claims and entitlement under or arising of this agreement and this agreement is d