IN THE HIGH COURT OF DELHI AT NEW DELHI
NAVIN CHAWLA, J.
SINTEX OIL AND GAS LIMITED – Appellant
Versus
UNION OF INDIA & ORS. - Respondents
OMP (I) (COMM) NO. 359 of 2017
Decided on : 22-12-2017
force majeure - Petroleum Exploration - Article 9.1 of the agreement - Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engineering Works (P) Ltd. (1997) 6 SCC 450 - Vinitec Electronics Private Ltd. v. HCL Infosystems Ltd. (2008)1 SCC 544 - Gujarat Maritime Board v. Larsen and Toubro Infrastructure Development Projects Limited and Anr. (2016) 10 SCC 46 - Himadri Chemicals Industries Ltd. v. Coal Tar Refining Co. (2007) 8 SCC 110
Fact of the Case:
The petitioner sought an ad interim ex-parte stay on the termination of a Production Sharing Contract (PSC) and the encashment of bank guarantees due to force majeure conditions arising from resistance by villagers, litigations, and protests, leading to the inability to carry out exploration activities.
Finding of the Court:
The court found that the petitioner failed to establish force majeure conditions justifying the injunction against the invocation of bank guarantees, citing precedents and emphasizing the unconditional nature of bank guarantees.
Issues: The issues revolved around force majeure conditions, the validity of the termination of the PSC, and the invocation of bank guarantees.
Ratio Decidendi: The court applied the legal principles established in Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engineering Works (P) Ltd. (1997) 6 SCC 450, Vinitec Electronics Private Ltd. v. HCL Infosystems Ltd. (2008)1 SCC 544, Gujarat Maritime Board v. Larsen and Toubro Infrastructure Development Projects Limited and Anr. (2016) 10 SCC 46, and Himadri Chemicals Industries Ltd. v. Coal Tar Refining Co. (2007) 8 SCC 110 to determine the validity of the injunction against the invocation of bank guarantees.
Final Decision: The petition was dismissed, and the interim order in favor of the petitioner was vacated.
1. The petitioner has filed the present petition inter alia praying for the following relief.
“(a) grant an ad interim ex-parte stay on the effect and operation of the termination letter dated 01st September, 2017 issued by the Respondent No.1 to the Petitioner thereby terminating the PSC dated 30th June 2010;
(b) pass ad-interim ex-parte orders restraining the Respondents from taking any coercive or precipitate steps in respect of, or invoking, encashing, depositing/receiving any payment under, the following:
(i) The Bank Guarantee No.PBGI00701700138 dated 23.03.2017 for an amount of INR 8,30,00,000/- (Rupees Eight Crore Thirty Lac Only) issued by the Respondent No.3 in favour of the Respondent No.1; and
(ii) the Bank Guarantee No.PBGI00701600310 dated 07.06.2016 for an amount of INR 4,33,62,231/- (Rupees Four Crore Thirty Three Lac Sixty Two Thousand Two Hundred Thirty One Only) issued by the Respondent No.3 in favour of the Respondent No.1”.
During the course of the oral submissions, the learned senior counsel for the petitioner confined his submissions only with respect to prayer (b) quoted above, presumably because the petitioner itself vide letter dated 24.04.2017 had requested the respondent to accept the letter of surrender of Block-1 granted in its favour under “Production Sharing Contract between the Government of India and Esveegee Steel (Gujarati) Private Limited” (hereinafter referred to as an ‘Agreement’). It is to be noted that the petitioner was earlier called Esveegee Steel (Gujarati) Private Limited.
2. It is the case of the petitioner that the petitioner was awarded “S” Type Block in Cambay Basin to undertake the exploration activities under the above mentioned agreement. The initial exploration period in respect of Block-1 was for a period of four years from the effective date, i.e., 15.10.2010 to 14.10.2014. An extension of six months was granted vide 12th MCR dated 08.10.2014 extending the period till 14.04.2015. The petitioner was also granted a Petroleum Exploration license on 15.10.2014 (hereinafter referred to as PEL) validity whereof was extended till 14.10.2017. The petitioner contends that on grant of PEL, the petitioner floated tender for pre-seismic Environmental Impact Assessment ("EIA") and 3D seismic data acquisition and also proceeded to appoint consultant for this work. However, as the consultant was unable to accept the proposal, a fresh tender had to be issued where after a fresh consultant was appointed, who also refused to carry out the work. It is alleged that in January 2014, the petitioner was finally able to engage the services of a consultant and commenced the work of digging of 123 upholes, which were completed between January 2014 and March 2014. However, as soon as the activities were commenced, the petitioner started getting rigid resistance from the villagers who started to obstruct / create hurdles as the villagers were afraid that the exploratory activities to be undertaken by the petitioner might shake the upper strata of earth dis-balancing the water table, which was earlier experienced by them when similar activities were undertaken by an another operator in the same area. The villagers further feared that the activities of the petitioner may damage their crops resulting in loss of livelihood.
3. Relying upon Article 9.1 of the agreement, it was contended that it was the duty of the respondent no.1 to provide to the petitioner, the right to ingress and egress from the contract area and to assist the petitioner in procurement or commencing of facilities required for execution of work, which the respondent nos. 1 and 2 failed to comply with.
4. The petitioner further claims that various litigations were filed against it making it impossible for the petitioner to carry out the work and the same constituted ‘force majeure’. Paragraph 33 of the petition is important in this regard and is reproduced herein below:-
“33. Further, the Respondent No.2 vide letter dated 15th March,
Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engineering Works (P) Ltd. (1997) 6 SCC 450
Himadri Chemicals Industries Ltd. v. Coal Tar Refining Co.
Hindustan Steel Workers Construction Ltd. v. G.S. Atwal & Co. (Engineers) (P) Ltd.[(1995) 6 SCC 76]
Larsen & Toubro Ltd. v. Maharashtra SEB [(1995) 6 SCC 68]
Svenska Handelsbanken v. Indian Charge Chrome [(1994) 1 SCC 502]
U.P. State Sugar Corpn. v. Sumac International Ltd. [(1997) 1 SCC 568]
U.P. Coop. Federation Ltd. v. Singh Consultants and Engineers (P) Ltd. [(1988) 1 SCC 174]
Vinitec Electronics Private Ltd. v. HCL Infosystems Ltd. (2008)1 SCC 544
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.