2018 Supreme(Del) 123

IN THE HIGH COURT OF DELHI AT NEW DELHI
PRATHIBA M. SINGH, J.
North Delhi Municipal Corporation – Appellant
Versus
Vipin Gupta – Respondent
RFA No. 160 of 2017 & CM APPL. 5807 of 2017 (Stay)
Decided On : 22-03-2018

Advocates Appeared:
For the Appellant :Ms. Renu Gupta, Advocate
For the Respondent:Mr. Vinay Kumar, Advocate

Headnote:

The court examined the validity of clauses 7 and 9 of the General Conditions of Contract (GCC) and the amendment of 2006, which dealt with the payment of bills to contractors by the North Delhi Municipal Corporation (NrDMC) and East Delhi Municipal Corporation (EDMC). The court held that the clauses were unreasonable and contrary to law as they did not specify a fixed time limit for payment, leaving the contractors with no remedy if the corporations failed to pay for the work executed. The court interpreted the clauses to mean that the reasonable time for making payments of final bills would be 6 months for work orders up to Rs.5 lakhs and 9 months for work orders exceeding Rs.5 lakhs from the date the bill is passed by the Engineer-in-Charge. The court also held that the queue basis for payments could be applied only for clearing payments within the 6-month and 9-month periods and not beyond that, as it would be unreasonable. The court issued guidelines for both the contractors and the corporations to follow to ensure proper execution of work orders, timely submission and passing of bills, and prompt payments to contractors.

Fact of the Case:

The case involved a batch of appeals filed by contractors who had executed work orders for the NrDMC and EDMC. The contractors had not been paid for the work executed, and they filed suits for recovery. The corporations relied on clauses 7 and 9 of the GCC and the amendment of 2006 to justify the delay in payments. The contractors argued that the clauses were unreasonable and contrary to law.

Finding of the Court:

The court held that clauses 7 and 9 of the GCC and the amendment of 2006 were unreasonable and contrary to law as they did not specify a fixed time limit for payment, leaving the contractors with no remedy if the corporations failed to pay for the work executed. The court interpreted the clauses to mean that the reasonable time for making payments of final bills would be 6 months for work orders up to Rs.5 lakhs and 9 months for work orders exceeding Rs.5 lakhs from the date the bill is passed by the Engineer-in-Charge. The court also held that the queue basis for payments could be applied only for clearing payments within the 6-month and 9-month periods and not beyond that, as it would be unreasonable.

Issues: 1. Whether clauses 7 and 9 of the GCC and the amendment of 2006 were valid and enforceable. 2. Whether the corporations were justified in delaying payments to the contractors. 3. Whether the contractors were entitled to interest on the delayed payments.

Ratio Decidendi: The court held that clauses 7 and 9 of the GCC and the amendment of 2006 were unreasonable and contrary to law as they did not specify a fixed time limit for payment, leaving the contractors with no remedy if the corporations failed to pay for the work executed. The court interpreted the clauses to mean that the reasonable time for making payments of final bills would be 6 months for work orders up to Rs.5 lakhs and 9 months for work orders exceeding Rs.5 lakhs from the date the bill is passed by the Engineer-in-Charge. The court also held that the queue basis for payments could be applied only for clearing payments within the 6-month and 9-month periods and not beyond that, as it would be unreasonable.

Final Decision: The court decreed the contractors' suits for recovery of the principal amount, minus the payments already made. The court also directed the corporations to make the payments within a period of eight weeks, failing which, interest @ 12% p.a. would be payable upon the expiry of the said period, on the decretal amount, till the date of payment. The court also issued guidelines for both the contractors and the corporations to follow to ensure proper execution of work orders, timely submission and passing of bills, and prompt payments to contractors.

JUDGMENT :

Prathiba M. Singh, J.

1. These are a batch of appeals which have arisen out of disputes between Contractors/Plaintiffs (hereinafter, ‘Contractors’) on the one hand and the North Delhi Municipal Corporation (hereinafter, ‘NrDMC’) and East Delhi Municipal Corporation (hereinafter, ‘EDMC’), on the other. NrDMC and EDMC are collectively referred to as ‘Corporations'. The facts in each appeal are different and hence separate judgments are being passed in each of the appeals.

2. Briefly, these are cases where various work orders were placed on Contractors by both the Corporations. The works were executed by the Contractors and thereafter, the Engineer-in-Charge has passed the final bills. Payments in respect thereof were not made. Suits for recovery were filed by the Contractors. The Trial Court decreed the suits in favour of the Contractors.

3. In the work orders, the Contractors seek either/all of the following payments:

(a). Payment of the principal amount as passed in the final bill;

(b). Refund of security deposit;

(c). Interest on account of late payment of the principal amount, as also due to delay in refund of security deposit.

4. The Corporations rely on Clauses 7 and 9 of the General Conditions of Contract in respect of payment of principal amount and interest, read with the amendment of 19th May, 2006. In respect of the security deposit, the Corporations rely on Clauses 17 and 45 of the General Conditions of Contract for Municipal Corporation of Delhi Works (hereinafter, ‘General Conditions of Contract’). In addition, the Corporations also rely upon Circular dated 10th June 2014 signed by the Chief Engineer, MCD which was issued in the nature of a clarification.

5. In the present case, the following work orders were placed on the Contractor by the Corporation:

S No.

Work Order No.

Contractual Amount (In Rs.)

Dated

1.

EE (M-KBZ)-I [EE I]/SYS/2013-2014/152

Rs. 3,98,276/-

10.06.2013

2.

EE (M-KBZ)-I [EE I]/SYS/2013-2014/151

Rs. 4,00,787/-

10.06.2013

3.

EE (M-KBZ)-I [EE I]/SYS/2013-2014//153

Rs. 3,94,588/-

10.06.2013

4.

EE (M-KBZ)-I [EE I]/SYS/2014-2015/30

Rs. 2,07,933/-

13.06.2014

5.

EE (M-KBZ)-I [EE I]/SYS/2014-2015/211

Rs. 3,39,615/-

24.11.2014

6.

EE (M-KBZ)-I [EE I]/SYS/2014-2015/243

Rs. 4,52,195/-

04.12.2014

7.

EE (M-KBZ)-II [EE XXIX]/SYS/2012-2013/401

Rs. 2,68,359/-

19/02/2013

8.

EE (M-KBZ)-II [EE XXIX]/SYS/2012-2013/465

Rs. 5,58,763/-

21.03.2013

9.

EE (M-KBZ)-II [EE XXIX]/SYS/2013-2014/479

Rs. 3,41,076/-

27.02.2014

10.

EE (M-KBZ)-II [EE XXIX]/SYS/2014-2015/66

Rs. 3,80,750/-

18.06.2014

11.

EE (M-KBZ)-II [EE XXIX]/SYS/2014-2015/149

Rs. 4,97,834/-

28.10.2014

12.

EE (M-KBZ)-II [EE XXIX]/SYS/2014-2015/283

Rs. 4,70,586/-

13.12.2014

13.

EE (M-KBZ)-II [EE XXIX]/SYS/2014-2015/416

Rs. 10,58,145/-

09.01.2015

6. The final bills were prepared by the Corporation, the details of which are as under:

S No.

Work Order No.

Final Bill Amount (In Rs.)

Security Deposit (In Rs.)

Bill Passed on

1.

EE (M-KBZ)-I [EE I]/SYS/2013-2014/152

3,44,756

40,640

13.12.2013

2.

EE (M-KBZ)-I [EE I]/SYS/2013-2014/151

3,40,982

41,749

25.10.2013

3.

EE (M-KBZ)-I [EE I]/SYS/2013-2014//153

3,35,430

41,536

09.12.2013

4.

EE (M-KBZ)-I [EE I]/SYS/2014-2015/30

1,75,274

23,104

15.09.2014

5.

EE (M-KBZ)-I [EE I]/SYS/2014-2015/211

2,90,536

30,874

23.03.2015

6.

EE (M-KBZ)-I [EE I]/SYS/2014-2015/243

3,74,821

45,220/-

13.03.2015

7.

EE (M-KBZ)-II [EE XXIX]/SYS/2012-2013/401

2,27,503

28,567/-

29.04.2013

8.

EE (M-KBZ)-II [EE XXIX]/SYS/2012-2013/465 (First Bill)

3,68,563

52,245/-

11.03.2014

9.

EE (M-KBZ)-II [EE XXIX]/SYS/2012-2013/465 (2nd and Final Bill)












































































































































































































































Click Here to Read the rest of this document