2018 Supreme(Del) 265
IN THE HIGH COURT OF DELHI AT NEW DELHI
C.HARI SHANKAR, J.
T.C. Jindgar - Petitioner
Versus
Rural Electrification Corporation - Respondent
W.P.(C) 4790 of 2002
Decided On : 20-04-2018
Important Points
Subject
Administrative Law - Disciplinary Proceedings
Act Referred
CONDUCT RULES : R.4, R.5, R.6, R.7, R.8, R.9, R.10, R.11, R.12, R.13, R.14, R.15, R.16, R.17, R.18
DISCIPLINE AND APPEAL RULES : R.3, R.4
REC CONDUCT, DISCIPLINE AND APPEAL RULES : R.25, R.5(1), R.5(9), R.24, R.33, R.5(4)
Headnote
Misconduct - Wind Energy Financing - REC (Conduct, Discipline & Appeal) Rules, 1979 - Rule 5(1), 5(4), 5(9) - The court discussed the Articles of Charge against the petitioner, the inquiry report, and the disciplinary authority's order. The court found that the petitioner's actions were prejudicial to the interests of the Corporation, invoking Rule 5(4) of the 1979 Rules. The court emphasized that misconduct must involve a transgression of an established or definite rule of conduct, and that mere negligence or carelessness is not misconduct. The court set aside the decision to enhance the penalty, as the reviewing authority failed to provide any rationale or reasons justifying the decision.
Fact of the Case:
The petitioner, while working as Deputy Chief (Engineering) in the respondent-Corporation, was charged with misconduct related to Wind Energy Financing projects. The disciplinary inquiry found the petitioner guilty of defaulting in his duties, resulting in undue financial benefit to private entrepreneurs. The disciplinary authority imposed a minor penalty, which was later reviewed and enhanced to a major penalty by the Board of Directors of the Corporation.
Finding of the Court:
The court found that the petitioner's actions were prejudicial to the interests of the Corporation, invoking Rule 5(4) of the 1979 Rules. The court emphasized that misconduct must involve a transgression of an established or definite rule of conduct, and that mere negligence or carelessness is not misconduct. The court set aside the decision to enhance the penalty, as the reviewing authority failed to provide any rationale or reasons justifying the decision.
Issues: The key issues revolved around the petitioner's alleged misconduct in the Wind Energy Financing projects, the imposition of a minor penalty by the disciplinary authority, and the subsequent review and enhancement of the penalty by the Board of Directors of the Corporation.
Ratio Decidendi: The court's decision was based on the interpretation of misconduct under Rule 5 of the 1979 Rules, emphasizing that misconduct must involve a transgression of an established or definite rule of conduct, and that mere negligence or carelessness is not misconduct. The court also highlighted the lack of rationale or reasons justifying the decision to enhance the penalty.
Final Decision: The court set aside the decision to enhance the penalty imposed on the petitioner, and directed the disbursement of all withheld benefits. The petitioner was also awarded costs amounting to Rs. 50,000.
For the Petitioner: Mr. Sanjay Mann, Adv.
For the Respondent: Mr. Deepak Khurana and Mr. Tejasv Anand, Advs.
C.HARI SHANKAR, J.
1. The petitioner T.C. Jindgar, while working as Deputy Chief (Engineering) in the office of the respondent-Corporation, was visited with a charge-sheet dated 28th February, 1999, proposing to hold an inquiry, against him, under Rule 25 of the REC (Conduct, Discipline and Appeal) Rules 1979 (hereinafter referred to “the 1979 Rules”) on the ground that he had failed to exhibit absolute integrity and honesty in connection with the business assigned to him and had, thereby violated Rule 5(1) and 5(9) of the 1979 Rules.
2. In view of the limited nature of the controversy raised by the petitioner in the present case, it is not necessary for this Court to embark on a detailed examination of the Articles of Charge contained in the said charge-sheet. Suffice it to state that the respondent-Corporation was engaged in project financing for various projects, for which it granted loans, and that, prior to such grant, due diligence was conducted with respect to the viability of the project in question. This, in turn, required technical evaluation of the project, and ascertainment of the conformity, of the equipment in question, to the project’s specifications. Mr. Deepak Khurana, learned counsel for the respondent, submits that the lapse of duty, on the part of the petitioner, pertained to certain Wind Energy Financing projects, in respect whereof, the specification of the equipment involved was disconsonant with the project’s specifications, and that the gravamen of the changes against the petitioner were basically to the effect that the petitioner, who was entrusted with the task of assessing the viability of the project and ascertaining that the equipment was as per the specifications, defaulted. As a result, Mr. Deepak Khurana, would submit, the respondent ended up advancing a loan for a project which was not viable, resulting in considerable financial prejudice to it in the long run.
3. For ready reference, the Articles of Charge, against the petitioner, as framed in the charge-sheet dated 28th February, 1999 (supra), may be reproduced as under:
“Sub: Statement of Articles of Charges framed against Sh. T.C. Jindgar, Dy. Chief (Engg.)
Article-1
That the said Sh. T.C. Jindgar, while functioning as Deputy Chief (Engg.) at Corporate Office of the Corporation was associated during the period September?94 to March ?95 with the work relating to sanction of Wind Mill projects to be sanctioned to private entrepreneurs in Tamil Nadu, as a member of the Empowered Project Management Committee (EPMC). Shri Jindgar, visited the scheme area in March 95 to comment upon the availability of equipments in the field, their technical specifications, suitability to the schemes and other technical parameters. It is seen that Shri Jindgar, did not submit the factual report to the Competent Authority regarding installation of 27 Nos. X 410 KW WEGs in these projects instead of suitable numbers of 250 KW WEGs as originally proposed in the Project Reports. This resulted in undue benefit to the borrowers and also major deviations in implementation of these projects at the time of execution.
By his above act, Shri Jindgar exhibited lack of absolute integrity and honesty in connection with the business assigned to him and thereby violated Rules 5(1) and 5(9) of “REC (Conduct, Discipline & Appeal) Rules, 1979” and acted in a manner prejudicial to the interests of the Corporation.
Article-II
That Shri Jindgar, while monitoring the above projects of Wind Mills in Tamil Nadu, failed to verify the total number of WEGs, as proposed to be installed at Kayathar and Muppandal project sites in respect of M/s Subhash Projects & Marketing Ltd., and M/s Arihant Credit Capital Ltd. It is also seen that as a Member of the Monitoring Team, Shri. Jindgar submitted a report which was not based on facts and also not supported by the required documents in support of his submissions, thereby resulting in deviation in project sites and change of size of WEGs to be in