SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2018 Supreme(Del) 1963

IN THE HIGH COURT OF DELHI AT NEW DELHI
JAYANT NATH, J.
NATIONAL HIGHWAYS AUTHORITY OF INDIA - Petitioner
Versus
SOM DUTT BUILDERS-NCC(JV) - Respondent
O.M.P. (COMM) 252 of 2017
Decided on : 20-08-2018

Advocate Appeared:
For the Appellant :Ms.Bhavana, Advocate
For the Respondent:Mr.Milenka Chaudhary, Mr.Abhishek Sharma & Mr.Vineet Dwivedi, Advocates

The main legal point established in the judgment is that the arbitral tribunal's decision, based on authenticated evidence and within its jurisdiction, is not subject to review by the court unless it is found to be perverse or in violation of contractual or statutory provisions.

Headnote:

Arbitration and Conciliation Act - Impugning arbitral tribunal award - Section 34

Fact of the Case:

The petitioner filed a petition under section 34 of the Arbitration and Conciliation Act, 1996 to challenge the award passed by the arbitral tribunal. The respondent emerged as the highest successful bidder for a road construction project, but the project faced delays and disputes arose between the parties. The respondent raised 8 claims before the arbitral tribunal, out of which only claim Nos. 1 and 3 were awarded in their favor.

Finding of the Court:

The court found that the arbitral tribunal had considered the evidence and documents presented by both parties, and had relied on authenticated records and reports to arrive at its findings. The court held that the tribunal's decision was based on the evidence and within its jurisdiction, and therefore, dismissed the petition.

Issues: The issues raised included the delay in project completion, quantification of damages, and the award of interest. The petitioner argued that the evidence was overlooked, damages were not properly quantified, and the interest awarded was exorbitant.

Ratio Decidendi: The court held that the arbitral tribunal's reliance on authenticated documents and reports, as well as the use of Standard Data Book and Hudson's formula for quantifying damages, was within its jurisdiction and not perverse. The court also found that the interest awarded was in line with the contractual provisions and statutory provisions.

Final Decision: The court dismissed the petition, finding no merit in the petitioner's arguments against the arbitral tribunal's award.

JUDGMENT :

JAYANT NATH, J.

1. The present petition is filed under section 34 of the Arbitration and Conciliation Act, 1996 to impugn the award passed by the learned arbitral tribunal dated 14.02.2017. The majority award has been passed by the presiding arbitrator and the co-arbitrator rejecting the claims of the respondent except claim Nos.1 and 3. The second co-arbitrator Sh.Puran Chand has passed a separate award also rejecting all the claims of the respondent other than claim Nos.1 and 3. However, in the separate award, the quantification of the claims have been reduced.

2. The brief facts are that pursuant to the issuance of a notice inviting tenders, the respondent emerged as the highest successful bidder regarding the work of four laning and strengthening of existing two lanes between Km. 110 to Km.140 on NH-2 in the State of Bihar. Letter of acceptance was issued to the respondent on 23.02.2002. A contract agreement was executed on 27.03.2002. The stipulated date of commencement was 31.03.2002 and the entire project was to be completed within 36 months.

3. The project was divided into two sections. Section 1- New and Old Carriageway Bridge Km 130.500 to Km 140.00 (period of completion 24 months). Section 2 - New Carriageway (Bypass) Km 110.00 to Km 130.500 (period of completion 36 months).

4. A supplementary agreement dated 31.03.2004 was entered into between the petitioner and respondent wherein time for completion of Section 1 was amended. The scheduled date for completion of Section 1A was 30.3.2004, for Section 1B was 30.03.2005 and Section 2 was 30.03.2005. The work was however completed on 30.11.2007, 03.09.2007 and 10.07.2008, respectively. Taking over certificate was issued by the Engineer on 24.12.2007 for Section 1A, on 12.10.2007 for Section 1B and on 09.07.2008 for Section 2. The disputes having been arisen between the parties, the matter was referred to arbitration.

5. The respondent raised 8 claims before the learned Arbitral Tribunal. Details of the claims and the awarded amounts are as follows:

Sl. No.

Description of the Claim

Amount Claimed

Amount Awarded

1.

The losses incurred/suffered due to deployment of plant and machinery during the extended period of the Contract

Rs.77,54,28,747

Rs.6,37,71,803

2.

The losses incurred/suffered due to deployment of manpower during the extended period of the Contract

Rs.5,50,74,139

NIL

3.

The losses due to overheads incurred/suffered during the extended period of the Contract

Rs.34,96,97,908

Rs.5,10,17,227

4.

The loss of contractor’s profit during the extended period of the Contract

Rs.25,91,18,255

NIL

5.

Claim against losses incurred/ suffered on account of additional expenditure due to extension of BGs towards performance security, mobilization advance and key construction equipment advance and also extra interest liability on advance drawn due to extension of period of the contract

Rs.11,32,65,338

NIL

6.

Loss on account Additional Expenditure on Insurance charges (CAR Policy)

Rs.1,13,09,282

NIL

7.

Losses due unprecedented and phenomenally abnormal rise in price of steel

Rs.3,20,00,125

NIL

8.

Extra cost incurred due to change of foundation of Sone Bridge from Pile foundation of Well foundation

Rs.3,51,78,894

NIL

6. In addition, the learned arbitral tribunal awarded interest @ 12% per annum compounded monthly on the awarded amount from 01.12.2011 till the date of award and 8% simple interest from the date of award to the date of actual payment.

7. A perusal of the award would show that the learned arbitral tribunal has first adjudicated the two preliminary objections raised by the petitioner, namely, that the statement of claim has not been signed and verified by a duly authorized





















































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top