NAVIN CHAWLA
North Delhi Municipal Corporation – Appellant
Versus
Ravi Builders – Respondent
1. This petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘Act’) has been filed by the petitioner challenging the Arbitral Award dated 16.03.2015 passed by the Sole Arbitrator adjudicating the disputes that have arisen between the parties in relation to Work Order No. EE (Br.)/II/TC/99 dated 19.01.2007 relating to construction of Storm Water Drainage System and Footpath as per work of improvement and strengthening of Sarai Phoose Road starting from Burf Khana Chowk to Daffrin Bridge Crossing in Civil Line Zone.
2. The Work Order mentioned the contractual amount of the work as Rs. 1,40,00,050/-. The stipulated time for completion of work was fifteen months starting from 28.01.2007. The work was finally completed by 30.09.2009.
3. The Arbitrator in his Impugned Award has awarded the following claims in favour of the respondent and against the petitioner:-
| “(i) | Claim no. 1 | Payment of alleged Final Bill | Rs.26,96,636/- |
| (ii) | Claim no. 4 | Escalation under Clause 10CC | Rs.16,83,902/- |
| (iii) | Cla | ||
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.