2020 Supreme(Del) 588

IN THE HIGH COURT OF DELHI AT NEW DELHI
Jyoti Singh, J.
Geoenpro Petroleum Ltd - Appellant
Versus
Geophysical Institute Of Israel - Respondent
Original Miscellaneous Petition (Comm) No. 509 of 2016
Decided On : 12-05-2020

Advocates Appeared:
Rajshekhar Rao, Advocate, Aashish Gupta, Advocate, Dushyant Manocha, Advocate, Sharad Kharra, Advocate, Chaitanya Puri, Advocate, Sadhika Gulati, Advocate, Abhimanyu Mahajan, Advocate, Arjun Mahajan, Advocate, Anubha Goel, Advocate, Suneha Jain, Advocate, Pulkit Thareja, Advocate

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Setting aside of arbitral award - The petitioner sought to set aside the majority award which partially favored the respondent while rejecting the petitioner's counterclaim. The court discussed the nature of the contract, obligations of the parties, and the quality of work, ultimately upholding the tribunal's conclusion of non-performance by the respondent at various stages. (Paras 16, 56, 68)

(B) Performance Obligations - Diligence and Efficiency - The court reinforced that the contractor must perform duties efficiently and in a workmanlike manner as stated under the contract, any failure to do so warrants the non-payment of claims. (Paras 41, 55)

(C) Standby Charges - Payment Entitlement - The petitioner was obliged to pay standby charges during specified periods where the work was halted due to local threats and not through any fault of the contractor. (Paras 80, 82)

(D) Counterclaims - Failure to Substantiate - The petitioner's rejection of the counterclaim for project expenses was valid due to lack of substantiation despite the tribunal's findings. (Paras 91, 92) (E) Final Award - Partial Acceptance - The court partially upheld the tribunal's award, allowing payments for specific invoices related to data acquisition, processing, and rightful claims made by the contractor, while setting aside claims for GB commission and certain standby charges. (Paras 93, 94)

Table of Content
1. government's contract with petitioner for seismic data. (Para 1 , 2 , 3)
2. details of the contractual obligations and failures. (Para 4 , 5 , 6 , 7 , 8 , 9 , 10)
3. claims filed by the respondent in arbitration. (Para 11 , 12 , 13 , 14 , 15)
4. court's observations on claims and evidence. (Para 16 , 17 , 18 , 19 , 20)
5. arguments presented by counsel for petitioner. (Para 21 , 22 , 23 , 24 , 25)
6. observations on contract terms and arbitration. (Para 26 , 27 , 28 , 29 , 30)
7. analysis of arbitral tribunal's decision. (Para 31 , 32 , 33 , 34 , 35)
8. final conclusions on the arbitration outcome. (Para 36 , 37 , 38 , 39 , 40)

JUDGMENT

Jyoti Singh, J. - Present petition has been filed under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as an "Act") seeking setting aside of majority Award dated 30.07.2012 passed by the Arbitral Tribunal whereby the Tribunal has partially allowed the Claim of the Respondent herein and rejected the Counter Claim of the Petitioner.

2. The brief background facts are that the Government of India desired that the petroleum resources at the Kharsang Oil Fields (hereinafter referred to as "KS") be exploited with utmost expedition and in accordance with international petroleum industry practices. Therefore, Government of India entered into a Production Sharing Contract (hereinafter referred to as "PSC") on 16.06.1995 with Oil India Ltd., Geopetrol International Inc., Enpro India Ltd. and the Petitioner. Petitioner was appointed as the Operator under the Contract.

3. Petitioner herein as an Operator for and on behalf of KS required services for acquisition, processing and interpretation of Seismic 3D data in KS. Thus an Agreement dated 13.12.2007 was entered into between the Respondent herein and the Petitioner. Respondent Geophysical Institute of Israel is an Israeli Government Company. On 03.01.2008, a Sub-Contract Agreement was entered into between the Respondent and Asian Oilfields Services Ltd. with Respondent as the Contractor and Asian Oilfields as a sub-Contractor. This was with the approval of the Petitioner. Contract was to be performed by the Respondent in three stages (a) Data collection/acquisition (b) processing and (c) interpretation.

    Case of the Petitioner (Respondent before the Arbitral Tribunal)

4. Under the terms of the Contract, in order to collect acceptable Seismic Data, Respondent had to drill shot holes of 20 m for loading the charge and exploding the same. It was mentioned in the Contract itself, that in case where drilling up to 20 m was not possible, two holes of 10 m could be drilled or four holes of 5 m, called pattern holes. It was mentioned that Respondent will not drill any holes less than 5 m and the area covered under the survey shall be 52.5 km with 2760 shots of work.

5. Respondent had admittedly in the past, undertaken similar operations in the State of Assam and Tripura. Further, Respondent as per the terms of the Contract, before commencing its operations had undertaken an experimental drilling at the site from 29.08.2007 to 02.09.2007 and had, therefore, acquainted itself with the geological and other working conditions of the site. Parties had expressly agreed that time shall be the essence of the Contract as the work had to be undertaken by the Respondent before the onset of monsoon on account of fair weather in Arunachal Pradesh coming to an end by mid-June for purposes of drilling. Therefore, the Contract specifically provided that mobilisation of equipment, which was the sole responsibility of the Respondent, had to be completed within 60 days from signing of the Contract. Contract was signed on 13.12.2007 and, therefore, Respondent ought to have mobilised its equipment latest by 11.02.2008. However, mobilisation was completed only around late April 2008 and it was only on 15.04.2008 that shooting commenced. Thus,



Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top