2020 Supreme(Del) 664
IN THE HIGH COURT OF DELHI AT NEW DELHI
Prathiba M Singh, J.
Gammon India Ltd & Anr. - Appellant
Versus
National Highways Authority Of India - Respondent
Original Miscellaneous Petition (Comm) No. 392 of 2020; Interlocutory Application No. 11671 of 2018
Decided On : 23-06-2020
P.C. Markanda, Advocate, Chirag Shroff, Advocate, Neihal Dogra, Advocate, Padma Priya, Advocate, Dhruv Nayar, Advocate
The court emphasized the need to avoid multiplicity in arbitral proceedings and to streamline the process.
Headnote:
FACT OF THE CASE: A contract was executed between Gammon-Atlanta JV and National Highways Authority of India for a project. Disputes arose between the parties, leading to arbitration. FINDING OF THE COURT: The court found that the arbitration process had become complex due to multiple invocations, references, tribunals, awards, and challenges. The court upheld Award No.1, which allowed some claims and rejected others. Award No.2, which rejected the claims of the Contractor, was also upheld. ISSUES: The main issues were the delays in the project, compensation claims, and challenges to the awards. RATIO DECIDENDI: The court emphasized the need to avoid multiplicity in arbitral proceedings and to streamline the process. FINAL DECISION: The court rejected the petition challenging Award No.2.
JUDGMENT
Prathiba M. Singh, J. - Arbitration was to be the panacea for the woes of litigation. As an ''alternate dispute resolution'' mechanism, arbitration has however become complex, owing to several reasons such as long delays, challenges in enforcement, high costs etc., One other reason rendering arbitral processes complex is ''MULTIPLICITY'' - multiple invocations, multiple references, multiple Arbitral Tribunals, multiple Awards and multiple challenges, between the same parties, in respect of the same contract or the same series of contracts. Repeated steps have been taken in judgments and by amendments to the law, to make the system efficient, but more needs to be done.
Brief Facts
2. In the present case, a contract was executed between Gammon-Atlanta JV, a Joint Venture of Gammon India Ltd. and Atlanta Ltd. (hereinafter "Contractor") and National Highways Authority of India (hereinafter "NHAI") on 23rd December, 2000 for the work of widening to 4/6 lanes and strengthening of existing 2 lane carriageway of NH-5 in the State of Orissa from km 387.700 to 414.000 (Khurda to Bhubaneswar) Contract Pkg. OR-1 (hereinafter "Project"). The value of the work was approximately Rs.118.9 crores. The date of commencement of the contract was fixed as 15th January, 2001 and the project was to be executed within 36 months i.e., by 14th January, 2004.
3. The Project was not executed within the prescribed time. Extensions for completing the Project were granted till 31st December, 2006. Vehicular traffic was allowed on the main carriageway in March, 2007 and according to the Contractor, this amounted to a deemed ''taking over'' of the carriageway by NHAI and hence completion.
Award No.1 - 5th October, 2007
4. During the course of execution of the Project, disputes had arisen between the parties in respect of some claims. The same were raised both by the Contractor and by NHAI. On 1st August, 2004, the Disputes Review Board (hereinafter "DRB") was constituted in terms of sub-clause 67.1 of the Conditions of Particular Application (hereinafter, "COPA"). The DRB is stated to have expressly communicated its inability to resolve issues pertaining to a period earlier to its constitution. The DRB thus did not resolve the issues and accordingly, the Contractor invoked arbitration under sub-clause 67.3 of COPA vide notice dated 27th January, 2005. The relevant claims referred for arbitration are as under:
"Claim 2.1: Compensation for losses incurred on account of overhead and expected profit
Claim 2.2: Compensation for reduced productivity of machinery and equipment deployed.
Claim 2.3: Revision of rates to cover for increase of cost of materials and labour during extended period over and above the relief available under escalation (price adjustment) provision in the agreement."
5. The Arbitral Tribunal, consisting of Mr. P.B. Vijay, Mr. C.C. Bhattacharya and Mr. R.T. Atre, was appointed and the award was rendered on 5th October, 2007 (hereinafter "Award No.1"). The findings in Award No.1 with respect to Claim Nos. 2.1, 2.2 & 2.3 are as under:
Claim No.2 was found to not be barred by limitation as even though the DRB was constituted on 1st August, 2004, it expressed its inability to give its recommendation only on 17th November, 2004. Thus, the limitation period of 56 days was considered to begin from 17th November, 2004, making the notice dated 27th January, 2005 within the prescribed limitation period.
The Contractor claimed compensation on the basis of the following six alleged breaches by NHAI: (1) Late appointment of key personnel, (2) Delay in payments, (3) Virtual suspension of BC work from December, 2003 to March, 2005, (4) Failure to sanction adequate extension of time, (5) Failure to constitute Dispute Review Board and (6) Delay in handing over of site.
As regards the first five alleged breaches, the Arbitral Tribunal (hereinafter, "AT") found that the actions of NHAI either did not materially affect the progress of the work, the Claimant