SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Del) 202

IN THE HIGH COURT OF DELHI AT NEW DELHI
VIBHU BAKHRU, J.
Gupta And Co. – Appellant
Versus
DDA - Respondent
O.M.P. (COMM) 150 of 2021 and IA No. 5424 of 2021
Decided on : 13-05-2021

Advocates:
Advocate Appeared:
For the Appellant :Mr S.K. Jain, Advocate with Ms Stuti Jain and Mr Akshu Jain, Advocate.
For the Respondent: Ms Shobhana Takiar, Standing Counsel for DDA.

Point of Law : Arbitration and Conciliation - Application for set aside Arbitral Award - Claim for pre-reference interest on Claims - While Arbitral Tribunal has awarded interest on amounts that were released belatedly, it has not awarded interest on amount that had not been released.

Headnote:

Arbitration and Conciliation Act, 1996 - Sections 9, 34 and 42 - Tenders - work for Construction of 160 SFS houses category - Final Bill - Limitation - Petitioner claims that it was informed that Quality Control Cell of DDA had inspected works and therefore, final bill could not be finalised until Quality Control observations were closed - Arbitral Tribunal had found that entire amount had been withheld by DDA from bills raised by petitioner but amount had been released belatedly.

Finding of the Court: Arbitral Tribunal found that petitioner was also entitled to escalation, however, Arbitral Tribunal computed amount of escalation payable under Clause 10-CC of General Conditions of the Contract at 8,03,348/- instead of 18,50,000/- as claimed by petitioner - Court considers it apposite to set aside impugned award to extent that Arbitral Tribunal has not considered petitioner’s claim for pre-reference interest on Claims - It is clarified that nothing stated in this order shall preclude - DDA from pursuing its petition to set aside impugned award - All rights and contentions of parties including on question of maintainability of petition are reserved.

Result: Petition is disposed of.

JUDGMENT :

VIBHU BAKHRU, J. (ORAL)

1. The petitioner has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the ‘A&C Act’) impugning an arbitral award dated 02.12.2020 to the extent that the Arbitral Tribunal has not awarded pre-reference interest in respect of petitioner‘s Claim Nos. 1 to 4.

2. The respondent (hereinafter ‘the DDA’) had issued a notice inviting tenders for the work of “Construction of 1600 SFS houses category II & III at Trilok Puri, Pocket ‘B’ SH: Construction of 160 SFS houses category II & III 80 Nos. Two bedroom category II, 80 nos. three bedroom category III & 120 scooter garages under SFS pocket ‘E’ including internal development Group V”.

3. Subsequently, by a letter dated 10.03.1986, the DDA awarded the said work to the petitioner. The works were to be completed within a period of twelve months from the 10th day of issuance of the letter of award, that is, by 20.03.1987. The petitioner states that it completed the contracted works on 29.08.1989 and there appears to be no dispute that the works were taken over by the DDA. However, the petitioner states that the completion of the works was not recorded and the petitioner‘s final bill was not made. The petitioner claims that it was informed that the Quality Control Cell of the DDA had inspected the works and therefore, the final bill could not be finalised until the Quality Control observations were closed. The petitioner claims that it continued to pursue with the DDA for processing its final bill. However, the DDA did not do so. The petitioner further claims that it was informed by the DDA that the original agreement executed between the parties was not traceable. The petitioner states that thereafter, the DDA directed the petitioner to handover surplus store material so that the final bill could be prepared by the department. The petitioner complied with the said direction, but the DDA failed to finalise the bill. The petitioner had issued a Bank Guarantee, which was renewed from time to time as the preparation of the final bill was pending.

4. The petitioner by its letter dated 09.04.2007 once again requested the DDA to finalise the bill. However, the same was not done.

5. Aggrieved by the inaction on the part of the DDA in not releasing the payments and not finalising its bill, the petitioner approached the Grievance Cell of the DDA. On 26.06.2009, the petitioner‘s complaint to the Grievance Cell was referred to the concerned office.

6. By a letter dated 10.12.2010, the Executive Engineer Eastern Division No.3, DDA informed the petitioner that its case was under active consideration. Thereafter, the DDA constituted a Committee to examine the petitioner‘s complaint. The said Committee submitted its report on 05.01.2011. The petitioner claims that the Committee recommended that the amount withheld, be released.

7. The petitioner claims that thereafter, on 17.01.2011, the petitioner was informed that the Final Bill had been prepared and was lying in the DDA‘s office. The petitioner claims that the said Final Bill was not in conformity with the measurements recorded by the DDA in various measurement books. However, the said Bill was accepted by the petitioner under protest. Thereafter, on 31.01.2011, the petitioner submitted its Final Bill in accordance with the measurements recorded in various measurement books.

8. Thereafter, the DDA released part payment for a sum of Rs.1,64,000/- to the petitioner by a cheque dated 16.03.2011.

9. The disputes between the parties persisted and after exchange of some correspondence, the petitioner issued a legal notice dated 11.07.2011 for recovery of the balance payment. In all, the petitioner raised thirteen claims in its notice. The petitioner claims that by a letter dated 18.07.2011, the DDA responded to the said notice admitting two of the claims but denied the others.

10. In view of the aforesaid disputes, by its letter dated 20.07.2011, the petitioner invoked the arbitra

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top