2021 Supreme(Del) 1498
IN THE HIGH COURT OF DELHI AT NEW DELHI
Suresh Kumar Kait, J.
M/s Ashutosh Builders Contractors And Engineers - Appellant
Versus
Union Of India & Ors. - Respondents
Arbitration Petition No. 900 of 2021
Decided On : 10-11-2021
Seema Singh, Advocate, Arti Bansal, Advocate
The main legal point established is that the appointment of an arbitrator must be with the consensus of the parties or by the court, and no single party can unilaterally appoint the arbitrator.
Headnote:
Arbitration - Appointment of Sole Arbitrator - Section 11(6) of the Arbitration and Conciliation Act, 1996 - IAFW 2249 - The court appointed Mr.P.B. Vijay as the sole Arbitrator to adjudicate the disputes between the parties under the Delhi International Arbitration Centre (DIAC) in accordance with the schedule of fees prescribed under the DIAC rules.
Fact of the Case:
The petitioner, a contractor, sought the appointment of a sole arbitrator for adjudication of disputes with the respondents under the provisions of Section 11(6) of the Arbitration and Conciliation Act, 1996. The respondents contended that the serving officer with requisite qualifications should be appointed as an arbitrator by the appointing authority.
Finding of the Court:
The court held that no single party can unilaterally appoint the arbitrator, and the arbitrator must be appointed with the consensus of the parties or by the court, citing the decision in Perkins Eastman Architects DPC & Anr. vs. HSCC (India) Ltd. 2019 SCC Online SC 1517 and Proddatur Cable TV Digi Services Vs. Citi Cable Network Limited: (2020) 267 DLT 51. The court appointed Mr.P.B. Vijay as the sole arbitrator to adjudicate the disputes between the parties under the DIAC.
Issues: Appointment of sole arbitrator, unilateral appointment of arbitrator, consensus of parties for arbitrator appointment.
Ratio Decidendi: The court emphasized that no single party can unilaterally appoint the arbitrator, and the arbitrator must be appointed with the consensus of the parties or by the court.
Final Decision: Mr.P.B. Vijay is appointed as the sole Arbitrator to adjudicate the disputes between the parties under the DIAC in accordance with the schedule of fees prescribed under the DIAC rules. The present petition is accordingly disposed of.
JUDGMENT
Suresh Kumar Kait, J. - Petitioner has filed the present petition under the provisions of Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of sole arbitrator for adjudication of all the disputes with respondents in terms of arbitration clause 70 of IAFW 2249.
2. Petitioner is a contractor and has been engaged by the respondent on several occasions for carrying out various constructions and other activities of respondent. Respondent is an establishment fully controlled and supervised by the Ministry of Defence, Union of India and is a state under Article 12 of the Constitution of India. Respondent no.1 is Union of India through Engineer in Chief (E-IN-C) of the Wing of Army for carrying out works of infrastructure. Respondent nos.2, 3 & 4 are subordinate offices to respondent no.1.
3. Petitioner was awarded the acceptance letter of the contract agreement vide letter dated 28.06.2019 for the work "CA NO.CWE/WEST-02/2019-20;SPL REPAIR OF ROMNEY HUTS T-156,T-165,T-166,T-167,T-168 AND T-169 OF CENTRAL STORAGE FACILITY AT CVD UNDER GE (WEST)DELHI CANTT.-10" to the tune of Rs.31,19,233/-.
4. Thereafter, respondent no.4 issued work order dated 02.07.2019 to the petitioner wherein date of commencement was mentioned as 12.07.2019 and date of completion was mentioned as 11.01.2020. Upon this, petitioner firm issued a letter dated 26.07.2019 requesting to handover the complete vacant site and thereafter, petitioner time and again sent letters dated 13.08.2019, 9. 09.2019 and 21.09.2019 requesting to handover Shed No. T-156, T-167 & T-165.
5. Subsequently, again petitioner sent letter on 05.12.2019 and stated that Honble Supreme Court vide order dated 04.11.2019 has enforced the ban upon the construction activities carried in Delhi. He also stated that the work could only be started after the ban is uplifted and requests for extension of time.
6. In response to the abovementioned letter, respondent no.4 vide letter dated 20.12.2019 stated that the Honble Supreme Court has given relaxation in time for construction activities from 09.12.2019 and also alleged that no activity can be seen at the site and stated to levy compensation as time being essence of contract and granted two weeks time to cancel the contract at certain risk and cost.
7. Thereafter petitioner again sent a letter dated 09.01.2020 to respondent no.4 in response to its letter dated 20.12.2019 expressing delay attributable to the respondent while proceeding with the execution of the work at site, delay in handing over site, delay in taking decision at paint, delay decision in installing the CG sheets, etc.
8. It is averred on behalf of the petitioner that despite of the due date of completion of work as per work Order No.1 which was expired on 11.01.2020, vacant site of the shed T-165 was not handed over. Thereafter petitioner again sent letter dated 22.01.2020 wherein stated that respondent no.4 has not granted extension of time to the petitioner and on the other side, notice of levying compensation was sent but complete vacant site was not handed over to the petitioner even after lapse of due date of completion of contract work. Respondent no.4 in response to the petitioners abovementioned letter sent letters dated 20.08.2020 and 21.08.2020 stating that CGI sheet of M/s Bhushan has developed defect of rust from many places.
9. Upon this, petitioner sent a letter to respondent no.5 as well as TATA Steel (manufacturer) along with letter of respondent no.4 to replace the steel/material as rust can be seen on CGI sheet.
10. Petitioner being aggrieved with the high handed attitude of respondent no.4 issued legal notice on 24.10.2020 stating that site T-165 has not been handed over after lapse of 10 months from the due date of completion and also failure in providing the extension despite of numerous requests.
11. During the course of hearing, learned counsel for the petitioner informed that the petitioner firm had previously sent notice for conciliat