SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Suresh Kumar Kait, J.
Ashutosh Builders Contractors and Engineers - Appellant
Versus
Union of India - Respondent
Arb.P. 900 of 2021
Decided On : 10-11-2021




No party can unilaterally appoint an arbitrator; appointment requires either mutual consent or judicial appointment to ensure impartiality.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11(6) - Appointment of sole arbitrator - Petitioner seeks appointment of an arbitrator for disputes arising from construction contract with respondent, which is a state under Article 12 of the Constitution of India. The Court reiterated that no single party can unilaterally appoint an Arbitrator, citing Perkins Eastman Architects DPC & Anr. vs. HSCC (India) Ltd. - Court appointed Mr. P.B. Vijay as sole Arbitrator to adjudicate disputes. (Paras 1, 13, 15)

(B) Arbitration Agreement - Requirement for consensus - It is necessary that an Arbitrator is appointed with the consensus of the parties or by the Court to maintain impartiality in the arbitration process. (Paras 13, 15)

Facts of the case:
Petitioner filed for the appointment of a sole arbitrator under Section 11 of the Arbitration and Conciliation Act due to multiple disputes arising from a construction contract awarded by the respondent.

Findings of Court:
The Court found that unilateral appointment of an arbitrator defeats unbiased adjudication. A consensus must be achieved or the Court must appoint an Arbitrator.

Issues: Whether the petitioner can seek the appointment of an arbitrator unilaterally or if it requires consensus from both parties.

Ratio Decidendi: The court emphasized the impartiality in the arbitration process requires an Arbitrator to be appointed by consensus or by the Court to prevent bias.

Result: The petition is disposed of with the appointment of Mr. P.B. Vijay as sole Arbitrator.

Table of Content
1. facts of the case and contractual agreements. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 10)
2. request for arbitration initiation. (Para 11 , 12)
3. court's reasoning on arbitrator appointment. (Para 13 , 14)
4. appointment of arbitrator and order conclusion. (Para 15 , 16 , 17 , 18 , 19 , 20)

JUDGMENT (Oral)

1. Petitioner has filed the present petition under the provisions of Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of sole arbitrator for adjudication of all the disputes with respondents in terms of arbitration clause 70 of IAFW 2249.

2. Petitioner is a contractor and has been engaged by the respondent on several occasions for carrying out various constructions and other activities of respondent. Respondent is an establishment fully controlled and supervised by the Ministry of Defence, Union of India and is a state under Article 12 of the Constitution of India. Respondent no.1 is Union of India through Engineer in Chief (E-IN-C) of the Wing of Army for carrying out works of infrastructure. Respondent nos.2, 3 & 4 are subordinate offices to respondent no.1.

3. Petitioner was awarded the acceptance letter of the contract agreement vide letter dated 28.06.2019 for the work "CA NO.CWE/WEST-02/2019 20;SPL REPAIR OF ROMNEY HUTS T-156,T-165,T-166,T-167,T-168 AND T-169 OF CENTRAL STORAGE FACILITY AT CVD UNDER GE (WEST)DELHI CANTT.-10" to the tune of Rs.31,19,233/-.

4. Thereafter, respondent no.4 issued work order dated 02.07.2019 to the petitioner wherein date of commencement was mentioned as 12.07.2019 and date of completion was mentioned as 11.01.2020. Upon this, petitioner firm issued a letter dated 26.07.2019 requesting to handover the complete vacant site and thereafter, petitioner time and again sent letters dated 13.08.2019, 09.09.2019 and 21.09.2019 requesting to handover Shed No. T-156, T-167 & T-165.

5. Subsequently, again petitioner sent letter on 05.12.2019 and stated that Hon'ble Supreme Court vide order dated 04.11.2019 has enforced the ban upon the construction activities carried in Delhi. He also stated that the work could only be started after the ban is uplifted and requests for extension of time.

6. In response to the abovementioned letter, respondent no.4 vide letter dated 20.12.2019 stated that the Hon'ble Supreme Court has given relaxation in time for construction activities from 09.12.2019 and also alleged that no activity can be seen at the site and stated to levy compensation as time being essence of contract and granted two weeks time to cancel the contract at certain risk and cost.

7. Thereafter petitioner again sent a letter dated 09.01.2020 to respondent no.4 in response to its letter dated 20.12.2019 expressing delay attributable to the respondent while proceeding with the execution of the work at site, delay in handing over site, delay in taking decision at paint, delay decision in installing the CG sheets, etc.

8. It is averred on behalf of the petitioner that despite of the due date of completion of work as per work Order No.1 which was expired on 11.01.2020, vacant site of the shed T-165 was not handed over. Thereafter petitioner again sent letter dated 22.01.2020 wherein stated that respondent no.4 has not granted extension of time to the petitioner and on the other side, notice of levying compensation was sent but complete vacant site was not handed over to the petitioner even after lapse of due date of completion of contract work. Respondent no.4 in response to the petitioner's abovementioned letter sent letters dated 20.08.2020 and 21.08.2020 stating that CGI sheet of M/s Bhushan has developed defect of rust from many places.

9. Upon this, petitioner sent a letter to respondent no.5 as well as TATA Steel (manufacturer) along with letter of respondent no.4 to replace the steel/material as rust can be seen on CGI sheet.

10. Petitioner being aggrieved with the high handed attitude of respondent no.4 issued legal notice on 24.10.20

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top