SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Suresh Kumar Kait, J.
Sivanssh Infrastructure Development Pvt. Ltd. - Appellant
Versus
Army Welfare Housing Organization - Respondent
Arb.P. 830 of 2021
Decided On : 26-10-2021




The unilateral appointment of an arbitrator violates the principle of unbiased adjudication, requiring mutual agreement between parties for such appointments.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 11(5) and 11(6) - Appointment of Arbitrator - The petition seeks appointment of a Sole Arbitrator due to delays and disputes arising from a construction contract - The unilateral appointment of an Arbitrator by the respondent was deemed invalid as it undermines unbiased adjudication - Court emphasizes that both parties must mutually agree on the Arbitrator, following precedent set in Perkins Eastman Architects DPC & Anr. vs. HSCC (India) Ltd. - Petition allowed, and Mr. Justice (Retd.) B.D. Ahmed appointed as Sole Arbitrator. (Paras 1, 6, 10, 12)

Table of Content
1. factual background of the arbitration case. (Para 2 , 3 , 4)
2. arguments against the arbitration appointment. (Para 5 , 6)
3. court's reasoning on unilateral arbitrator appointment. (Para 9 , 10 , 11)
4. final decision and appointment of arbitrator. (Para 12 , 13 , 14 , 15 , 16)

JUDGMENT (Oral)

1. The present petition has been filed by petitioner seeking appointment of Sole Arbitrator under the provisions of Sections 11(5) and 11(6) of the Arbitration and Conciliation Act, 1996.

2. Petitioner-company registered under the provisions of Companies Act, 1956 claims to be engaged in construction related activities including construction of various industrial, institutional, commercial as well as residential projects in India. Respondent is a Society registered under the Societies Registration Act, 1860.

3. According to petitioner, in December, 2015, respondent invited bids for development of a Residential Complex to be spread over an area of 3.57 acres (approx.) for construction of 220 dwelling units to be constructed in 5 Towers located at Sector-6A, Vrindavan Awas Yojna, Lucknow, to which petitioner had submitted its bid, which was accepted by the respondent vide Acceptance Letter dated 02.06.2016. The total value of the awarded project/Contract Price according to petitioner was Rs.100,59,48,977.35.

4. Further, as per Work Order dated 28.06.2016 issued by the respondent, petitioner was instructed to commence the work at the Site on the even date with a Completion Period of 30 months expiring on 27.12.2018. However, since respondent failed to handover the site to the petitioner, a Revised Work Order dated 19.06.2017 was issued by the respondent, for petitioner to commence the project on 12.08.2016 with the Completion Date as 11.02.2019.

5. During the course of hearing, learned counsel for petitioner has averred that in view of the various delays and defaults on the part of the respondent, the contract completion was delayed and consequently, the petitioner had to seek extension of the project with Completion Period on various occasions upto to 31.05.2019 and by then, petitioner completed the work. However, thereafter, certain disputes arose between the parties with regard to handing over of the dwelling units, issuance of completion certificate, defects liability period, release of bank guarantees furnished by the petitioner etc. It is submitted that since respondent had been unwilling to release the longstanding dues of the Petitioner, Petitioner invoked arbitration vide letter dated 22.06.2021 under Clause 174 of GCC and further, vide letter dated 22.06.2021 suggested the names of three eminent persons for the Respondent to choose one person to act as the Sole Arbitrator for adjudicating the disputes between the parties. In response thereto, vide letter dated 06.07.2021 Respondent instead of choosing one therefrom, called upon the Petitioner to choose from its own list of four people. However, vide letter dated 13.07.2021, petitioner conveyed its unacceptance to the respondent's proposal. The Chairman of the respondent in complete neglect of petitioner's letter dated 13.07.2021, unilaterally appointed Mr. S.S. Bansal, ADG (Arbitration Cell), Military Engineering Service (MES) as the Sole Arbitrator. Thereafter, petitioner received a letter dated 03.08.2021 from the Mr. S.S. Bansal calling upon the parties to submit to his jurisdiction as the Sole Arbitrator.

6. Learned counsel for petitioner submitted that appointment of Mr. S.S. Bansal as Arbitrator is in violation of dictum of Hon'ble Supreme Court in Perkins Eastman Architects DPC &Anr. vs. HSCC (India) Ltd., 2019 SCC Online SC 1517.

7. Notice issued.

8. Mr. A.K.Tewari, Advocate, appearing on behalf of petitioner accepts notice and submits that upon being informed about filing of the present petition, the learned Arbitrator has stayed the proceedings. Learned counsel has disputed the claims raised in the present petition, however, existence of

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top