C. HARI SHANKAR
Reebok International Limited – Appellant
Versus
Focus Energy Limited – Respondent
JUDGMENT
C. Hari Shankar, J. - EX.APPL.(OS) 760/2021 in O.M.P.(EFA)(COMM.) 2/2021
1. The delay of 56 days in filing reply to EX APPL (OS) 72/2021 is condoned.
2. The reply is taken on record.
3. The application stands disposed of.
EX.APPL.(OS) 72/2021 in O.M.P.(EFA)(COMM.) 2/2021
4. This application, at the instance of the beneficiary of the award, (for the sake of convenience be referred to, hereinafter, as "the award holder"), seeks condonation of delay in preferring OMP (EFA) (COMM) 2/2021, which has been filed for execution of a partial award dated 4th November, 2009 and a final award dated 24th May, 2011, passed by the learned Arbitral Tribunal.
5. The execution petition was filed on 23rd December, 2020, admittedly, within a period of 12 years of passing of the aforesaid partial award as well as the final award of the learned Arbitral Tribunal.
6. By virtue of the judgment of the Supreme Court in Government of India v. Vedanta Ltd. 2020 SCC OnLine SC 749, the limitation for filing of an application for execution/enforcement of a foreign award is required to be reckoned on the basis of Article 137 of the Schedule to the Limitation Act, 1963. Under the said Article, an application for e
Furest Day Lawson Ltd. vs. Jindal Exports Ltd. (2001) 6 SCC 356
Shriram EPC Ltd. vs. Rioglass Solar Sa (2018) 18 SCC 313
Thirumalai Chemicals Ltd. vs. U.O.I. (2011) 6 SCC 739
Thyssen Stahlunion Gmbh vs. Steel Authority Of India Ltd
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.