PUNJAB AND HARYANA HIGH COURT AT CHANDIGARH
Harsimran Singh Sethi and Vikas Suri, JJ.
Punjab Small Industries And Export Corporation Ltd. – Appellant
Versus
M/s. Bhullar Construction Company And Another – Respondent
CM-117-FCARB-2023 in/and FAO-CARB-37-2023 (O&M)
Decided on : 11-08-2025
JUDGMENT :
Vikas Suri, J. -
CM-117-FCARB-2023
2. Prayer in this application under Section 5 of the Limitation Act, 1963, is for condoning the delay of 130 days in filing the accompanying First Appeal from Order (FAO).
3. Upon notice of the application, the respondents have put in appearance through counsel and opposed the same.
4. Learned counsel for the applicant-appellant submits that the applicant-appellant-corporation had preferred objections under Section 34 of the Arbitration and Conciliation Act, 1996 (for short, 'Arbitration Act') against the award dated 02.04.2017 passed by the learned Arbitrator, whereby the appellant was ordered to pay a sum of Rs.60,74,075/- to the claimant-respondent within three months, failing which the awarded amount was to carry interest @ 10% per annum from the date of the award. The application/objections filed under Section 34 of the Arbitration Act, were dismissed by the learned Additional District Judge-cum-Presiding Officer, Commercial Court, Chandigarh, vide judgment dated 20.01.2023.
5. Aggrieved by the said judgment, the applicant-appellant-corporation has moved the present appeal along with the instant application seeking condonation of delay of 130 days in filing the appeal.
6. It is pleaded that upon receipt of intimation by the appellant-applicant from its counsel before the learned Commercial Court, about the passing of the impugned judgment dated 23.01.2023, request for applying for a certified copy thereof, was made. The application for obtaining the certified copy was moved on 08.02.2023, which was delivered on 15.04.2023. Thereafter, on retrieving the entire record from the counsel who had conducted the matter before the learned Commercial Court, Chandigarh, an opinion had to be sought from the concerned officials regarding suitability for preferring an appeal before the High Court. It is further pleaded that the applicant-corporation is a Government organization, with a pedantic system having many formalities that involve hierarchical structure, which resulted in taking some time for appointment of counsel to prefer the appeal. It is further pleaded that there is no intentional delay on the part of the applicant in filing the appeal, but for the circumstances beyond its control.
7. Learned counsel for the applicant has submitted that initially the appeal was filed under Section 37 of the Arbitration Act for which the period of limitation is 90 days, provided under Article 116 of the Limitation Act, 1973. Thus, the delay, in fact, is only of 100 days. It is further submitted that on certain objections having been raised by the Registry of this Court, whereafter, the matter was refiled after removing the said objections and upon refiling, the Registry has treated the present appeal as First Appeal from Order (Commercial Arbitration) under the provision of Section 13(1A) of the Commercial Courts Act, 2015. The period of limitation for preferring an appeal under the said provision has been reckoned to be 60 days and thus, delay of 130 days in filing the appeal has been calculated.
8. Per contra, learned counsel for the respondents has opposed the present application and defended the impugned order passed by the learned Commercial Court, Chandigarh. It is contended on behalf of the respondents that in view of the provision of Section 37 of the Arbitration Act, delay beyond a period of 120 days in filing the appeal cannot be condoned. It is further submitted that the provision of Section 5 of the Limitation Act would not apply to an appeal preferred under Section 13 of the Commercial Courts Act, 2015. Reliance has been placed on N.V. International vs. State of Assam and others, (2020) 2 SCC 109, which followed and applied the ratio in Union of India vs. Varindera Constructions Ltd., (2020) 2 SCC 111.
9. Heard learned counsel for the parties and with their able assistance perused the record.
10. Learned counsel for the applicant-appellant refuting the contentions of learned counsel for the re
The main legal point established in the judgment is that the doctrine of condonation of delay should be applied judiciously, taking into account the circumstances and the impact of external factors s....
The court may condone delays in filing appeals where sufficient cause is shown, including circumstances beyond a party's control, advocated particularly in light of unprecedented events like a pandem....
The Court held that the 60-day limitation for appeals under the Arbitration Act is strict and can only be extended in exceptional cases where sufficient cause is demonstrated, which was not establish....
(1) Condonation of delay under Section 5 of Limitation Act has to be seen in context of object of speedy resolution of disputes. Section 5 of Limitation Act will apply to appeals, both by virtue of S....
The court emphasized that delay in filing appeals under the Arbitration Act must be justified by sufficient cause, with negligence being insufficient for condonation.
Setting aside or refusing to set aside arbitral award under Section 34 of Act and an appeal lies where an order is passed under Section 34.
The court emphasized that appeals under the Arbitration Act must adhere to strict timelines, and administrative delays do not constitute sufficient cause for condonation of delay.
The court established that the limitation period for appeals under the Arbitration Act is 60 days as per the Commercial Courts Act, but delays can be condoned based on sufficient cause, including rel....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.