IN THE HIGH COURT OF DELHI AT NEW DELHI
Suresh Kumar Kait, J.
Enkebee Infratech India Private Limited - Appellant
Versus
Bharat Heavy Electricals Ltd. - Respondent
Arb.P. 632/2021
Decided On : 29-07-2021
Arbitration - Appointment of Sole Arbitrator - The court allowed the petition and appointed Justice Deepak Mishra as the Sole Arbitrator to adjudicate the dispute between the parties.
Fact of the Case:
The petitioner, a company engaged in construction projects, sought appointment of an Arbitrator for adjudication of disputes with the respondent, a state-owned Public-Sector Unit (PSU), arising from a civil work contract.
Finding of the Court:
The court found that the existence of an arbitration agreement and the invocation of arbitration were not disputed. As a result, the petition was allowed, and Justice Deepak Mishra was appointed as the Sole Arbitrator.
Issues: The main issue was the appointment of an Arbitrator to adjudicate the dispute between the parties.
Ratio Decidendi: The court's decision was influenced by the undisputed existence of an arbitration agreement and the invocation of arbitration by the petitioner.
Final Decision: The court allowed the petition and appointed Justice Deepak Mishra as the Sole Arbitrator to adjudicate the dispute between the parties.
JUDGMENT
(Oral)
The hearing has been conducted through video conferencing.
1. Petitioner is a company incorporated under the Companies Act, 2014 and has preferred the present petition under the provisions of Section 11 of Arbitration and Conciliation Act, 1996 seeking appointment of an Arbitrator for adjudication of disputes with respondent.
2. Petitioner-company is engaged in piling, civil structural & architectural engineering & construction of various industrial, building and infrastructural projects in India. According to petitioner, they have acquired substantial goodwill and reputation in the field of infrastructure for their efforts and quality in the execution of their projects.
3. Respondent is a state-owned Public-Sector Unit (PSU) engaged in design, engineering, construction, testing, commissioning and servicing of a wide range of products and services.
4. According to petitioners, on 09.05.2018 respondent invited bids for civil work for Visakh Refinery Modernization Project at HPCL, Vishakapatnam, Andhra Pradesh, followed by four Tender Change Notices dated 23.05.2018, 29.05.2018, 30.05.2018 and 02.06.2018 to which an offer was made by the petitioner vide its letter dated 30.05.2018. The price bid was opened on 19.06.2018 and petitioner was invited for negotiation. On 20.06.2018, negotiations were conducted and a final price offer was made by the petitioner, which was accepted by the respondent by Letter of Intent dated 23.06.2018. The said letter of intent was accepted by petitioner on 28.06.2018.
5. Thereafter, the respondent issued a work order bearing No. BHEL/NR/SCT/VRM/PILING/CI897(1104) dated 18.08.2018 in favour of the petitioner for a contract price of Rs. 26,58,33,800/-. The petitioner commenced mobilizing its equipment, funds and resources to the work site, however, from the very inception of the project respondent failed to comply with the terms and conditions of the agreement to facilitate timely execution of the project. According to petitioner, it suffered tremendous financial constraints to complete the project and delay in completing the project resulted in formal increase in the contract value from Rs.26,58,33,800/- to Rs.37,07,96,762/- by way of an amendment to the Work Order on 05.03.2020.
6. Further urged on behalf of petitioner that petitioner vide letter dated 20.12.2020 invoked Clause 2.21.1 of the General Conditions of the Contract (GCC) to refer the dispute to the Designated Engineer for settlement of disputes, which was acceded to by the respondent and the dispute was heard by the Designated Engineer. However, the Designated Engineer failed to pass the reasoned order within a period of reasonable time and, therefore, petitioner vide letter dated 11.05.2021 invoked the Arbitration Clause under GCC.
7. Next submitted on behalf of petitioner that after invocation of arbitration clause, the Designated Engineer rendered decision on 31.05.2021 but has, however, dismissed petitioner’s claim without appreciating the contentions of the petitioner. It is submitted that the arbitration clause mentioned in the 2.21.2 of the GCC, stipulates that in the event of contractor being dissatisfied with the decision of the Designated Engineer or the parties fail to settle the disputes by means of amicable settlement, the dispute shall be referred for arbitration. Hence, the present petition has been filed.
8. Notice issued.
9. Ms. Mayuri Raghuvanshi, Advocate, accepts notice on behalf of respondent.
10. Both sides have been heard and record of this case has been perused.
11. Petitioner has invoked arbitration vide notice dated 11.05.2021.
Though the present petition has been opposed by counsel for respondent, however, existence of arbitration agreement between the parties and invocation of arbitration are not disputed.
12. In view of the above, the present petition is allowed and Justice Deepak Mishra, former Chief Justice of India (Mobile: 9560333111) is appointed the Sole Arbitrator to adjudicate the dispute between the p
AI
The court confirmed that invocation of the arbitration clause is justified when dissatisfied with the Designated Engineer's decision, thus facilitating arbitration under the concurrent agreement.
The central legal point established in the judgment is the court's authority to appoint an arbitrator to resolve disputed claims between parties in accordance with Section 11(6) of the Arbitration an....
The court affirmed that when parties acknowledge disputes in a contractual agreement, an arbitrator must be appointed to resolve these disputes under the Arbitration and Conciliation Act, 1996.
Arbitration under the Arbitration and Conciliation Act, 1996 requires adherence to specified qualifications for the arbitrator as agreed in the contract.
The court ruled that a Sole Arbitrator is to be appointed to resolve disputes under the contract due to the respondent's failure to meet contractual obligations.
Disputes arising from a construction contract for unpaid dues are arbitrable under the Arbitration and Conciliation Act, prompting the appointment of a sole arbitrator.
The court ruled that claims regarding limitation and the validity of invoking arbitration must be determined by the Arbitral Tribunal, reaffirming the applicability of Article 137 of the Limitation A....
Court under Section 11(6) appoints arbitrator upon undisputed invocation of arbitration clause in contract, permitting respondents to raise limitation and merits objections before tribunal.
The court ruled that disputes under an arbitration agreement are arbitrable and can be resolved through appointed arbitrators, affirming the consent of both parties.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.