IN THE HIGH COURT OF DELHI AT NEW DELHI
Suresh Kumar Kait, J.
Mcl Ksipl (JV) - Appellant
Versus
Union Of India - Respondent
Arb. P. 901/2021
Decided On : 22-09-2021
Arbitration - Appointment of Arbitrator - The court appointed a sole arbitrator to adjudicate the disputes between the parties in a construction works contract, in accordance with Section 11(6) of the Arbitration and Conciliation Act, 1996.
Fact of the Case:
The petitioner, engaged in construction works, sought appointment of an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 due to disputes with the respondent regarding completion of work, bill clearance, and appointment of an arbitrator.
Finding of the Court:
The court appointed a sole arbitrator, Justice (Retd.) B. S. Chauhan, to adjudicate the disputes between the parties, as the claims made in the petition were disputed and the respondent agreed to the appointment of an arbitrator.
Issues: Disputes over completion of work, bill clearance, and appointment of an arbitrator.
Ratio Decidendi: The court's decision was influenced by the need to resolve the disputed claims between the parties through arbitration, as provided under Section 11(6) of the Arbitration and Conciliation Act, 1996.
Final Decision: The court appointed Justice (Retd.) B. S. Chauhan as the sole arbitrator and disposed of the petition accordingly.
JUDGMENT
(Oral)
1. Present petition has been preferred under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of an Arbitrator.
2. Petitioner claims to be carrying its business of construction works in India. According to petitioner, respondent invited item rate tenders for the work of “Completion of balance works for construction of dwelling units including allied services for Officers JCOS/OR at Port Blair (Army)” and petitioner’s bid was accepted vide its letter dated 28/10/2014 for an amount of Rs. 438,29,06,684/ and time for completion of work was stipulated as 28 months.
3. Petitioner claims that the site for work was handed over to it by the respondent on 22.12.2014 and therefore, the work was to be concluded by 21.04.2017. However, due to various hindrances on the part of respondent, like non-availability of site, decisions and other hindrances and beaches of contract, petitioner could complete the work on 15.05.2018. Further claimed that the final bill was required to be submitted within three months so, petitioner submitted the same on 14.08.2018 and respondent was under obligation to clear it within six months i.e. on or before 13.02.2019.
However, respondent cleared the final bill on 06.09.2019 ignoring various legitimate payments towards the petitioner. Also that even the defect liability period of 24 months has been successfully accomplished by the petitioner on 14.05.2020.
4. According to petitioner, when its persistent requests to clear the outstanding amount failed, the petitioner finally invoked the arbitration clause as per condition 60 on page 188 of the Contract Agreement vide its letters dated 31.10.2019; 30.10.2020; 05.03.2021 and 17.06.2021 written to the Engineer in Chief of the respondent requesting to appoint Arbitrator within 30 days from 17.06.2021. However, since respondent did not appoint any Arbitrator, hence, the present petition has been filed seeking appointment of Arbitrator.
5. Learned Central Government Standing Counsel submits that the claims made in the present petition are disputed, however, she has agreed that an Arbitrator can be appointed to resolve the disputes between the parties.
6. In view of the aforesaid, Justice (Retd.) B. S. Chauhan, former Judge of Hon’ble Supreme Court, (Mobile: 9717393516) is appointed sole Arbitrator to adjudicate the disputes between the parties.
7. The fees of the learned Arbitrator shall be according to Fourth Schedule of the Arbitration and Conciliation Act, 1996.
8. The learned Arbitrator shall ensure compliance of Section 12 of Arbitration and Conciliation Act, 1996 before commencing the arbitration.
9. A copy of this order be sent to the learned Arbitrator for information.
9. The present petition is accordingly disposed of.
The central legal point established in the judgment is the court's authority to appoint an arbitrator to resolve disputed claims between parties in accordance with Section 11(6) of the Arbitration an....
The court affirmed that when parties acknowledge disputes in a contractual agreement, an arbitrator must be appointed to resolve these disputes under the Arbitration and Conciliation Act, 1996.
The court applied the provisions of the Arbitration and Conciliation Act, 1996 to appoint a sole arbitrator and ensure compliance before commencing the arbitration.
Disputes concerning contract completion and payment arise, necessitating arbitration as per the Arbitration and Conciliation Act, 1996.
Disputes under contracts with the Union of India are arbitrable, and the appointment of an independent arbitrator is necessary for their resolution under Section 11(6) of the Arbitration and Concilia....
The court upheld the validity of the arbitration agreement and recognized the petitioner’s adherence to the procedural requirements for arbitration, irrespective of the respondent's claims regarding ....
The court ruled that a Sole Arbitrator is to be appointed to resolve disputes under the contract due to the respondent's failure to meet contractual obligations.
Court under Section 11(6) appoints arbitrator upon undisputed invocation of arbitration clause in contract, permitting respondents to raise limitation and merits objections before tribunal.
The court has the authority to appoint a sole Arbitrator in accordance with the Arbitration Clause forming a part of the Contract.
The main legal point established is the court's authority to appoint a sole arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 to adjudicate disputes between parties.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.